Financier | Commitments |
---|---|
IDA Grant | 15.00 |
P157036
Closed
Gbetoho Boko , Friederike Rother
Republic of Togo
January 30, 2017
(as of board presentation)
March 21, 2017
November 30, 2017
US$ 15.00 million
Agence Nationale d’Appui au Développement à la Base (ANADEB)
2017
US$ 15.00 million
B
January 17, 2024
December 31, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 21, 2017 | IDA-D1730 | Loan Commitment | 15,000,000.00 |
May 17, 2022 | IDA-D1730 | Loan Cancel | 970.98 |
Dec 2, 2021 | IDA-D1730 | Loan Disb | 2,986.77 |
Sep 1, 2021 | IDA-D1730 | Loan Disb | 10,224.67 |
May 17, 2022 | IDA-D1730 | Loan Disb | -584.48 |
Oct 1, 2021 | IDA-D1730 | Loan Disb | 9,276.16 |
Nov 17, 2021 | IDA-D1730 | Loan Disb | 5,042.16 |
Apr 13, 2021 | IDA-D1730 | Loan Disb | 265,449.38 |
Mar 8, 2021 | IDA-D1730 | Loan Disb | 493,568.25 |
Feb 19, 2021 | IDA-D1730 | Loan Disb | 1,060,863.80 |
Dec 9, 2020 | IDA-D1730 | Loan Disb | 683,755.90 |
Jan 28, 2021 | IDA-D1730 | Loan Disb | 716,203.75 |
Oct 22, 2020 | IDA-D1730 | Loan Disb | 830,089.30 |
Oct 9, 2020 | IDA-D1730 | Loan Disb | 346,609.84 |
Nov 18, 2020 | IDA-D1730 | Loan Disb | 878,334.00 |
Aug 14, 2020 | IDA-D1730 | Loan Disb | 394,868.44 |
Jul 15, 2020 | IDA-D1730 | Loan Disb | 139,169.81 |
Jan 2, 2020 | IDA-D1730 | Loan Disb | 432,063.25 |
Jun 2, 2020 | IDA-D1730 | Loan Disb | 245,943.75 |
May 20, 2020 | IDA-D1730 | Loan Disb | 598,668.50 |
May 20, 2020 | IDA-D1730 | Loan Disb | 401,678.34 |
Oct 21, 2019 | IDA-D1730 | Loan Disb | 275,219.44 |
Apr 3, 2020 | IDA-D1730 | Loan Disb | 465,074.34 |
Jan 21, 2020 | IDA-D1730 | Loan Disb | 348,084.80 |
Mar 6, 2020 | IDA-D1730 | Loan Disb | 416,749.34 |
Jul 1, 2019 | IDA-D1730 | Loan Disb | 253,914.66 |
Apr 8, 2019 | IDA-D1730 | Loan Disb | 52,699.51 |
Aug 1, 2019 | IDA-D1730 | Loan Disb | 284,162.88 |
Aug 30, 2019 | IDA-D1730 | Loan Disb | 2,451,932.00 |
Jun 4, 2019 | IDA-D1730 | Loan Disb | 333,487.88 |
Sep 10, 2019 | IDA-D1730 | Loan Disb | 482,565.20 |
Nov 7, 2019 | IDA-D1730 | Loan Disb | 821,386.56 |
Dec 11, 2018 | IDA-D1730 | Loan Disb | 8,168.47 |
Jan 17, 2019 | IDA-D1730 | Loan Disb | 52,484.69 |
May 15, 2019 | IDA-D1730 | Loan Disb | 229,188.48 |
May 15, 2019 | IDA-D1730 | Loan Disb | 19,862.99 |
Feb 22, 2019 | IDA-D1730 | Loan Disb | 38,935.85 |
Jun 24, 2019 | IDA-D1730 | Loan Disb | 171,193.67 |
Mar 22, 2019 | IDA-D1730 | Loan Disb | 35,475.31 |
Feb 23, 2018 | IDA-D1730 | Loan Disb | 1,017,580.10 |
Nov 30, 2017 | IDA-D1730 | Loan Disb | 84,528.05 |
Jun 28, 2018 | IDA-D1730 | Loan Disb | 8,353.51 |
Aug 31, 2018 | IDA-D1730 | Loan Disb | 30,098.38 |
Jul 26, 2018 | IDA-D1730 | Loan Disb | 32,438.80 |
Jun 28, 2018 | IDA-D1730 | Loan Disb | 60,440.21 |
Jun 28, 2018 | IDA-D1730 | Loan Disb | 6,505.51 |
Nov 29, 2018 | IDA-D1730 | Loan Disb | 34,621.88 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2021-12-03 |
Procurement | Satisfactory | 2021-12-03 |
Financial Management | Satisfactory | 2021-12-03 |
Project Management | Moderately Satisfactory | 2021-12-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-12-03 |
Overall Implementation Progress (IP) | Satisfactory | 2021-12-03 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-16-2022 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 08-23-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 14415.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | September 20, 2016 | December 19, 2017 | ||
Comment |
Number of person-days of participation in community service subprojects | Value | 0.00 | 1120219.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Targeted youth initiating or expanding household enterprises with support from the project | Value | 0.00 | 11494.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries of components 1 and 2 living with a disability, or not having finished primary school - living in the poorest 150 cantons targeted in Togo | Value | 0.00 | 95.00 | 0.00 |
Date | October 31, 2019 | September 30, 2021 | ||
Comment |
Beneficiaries that feel project investments reflected their needs (percentage) | Value | 0.00 | 97.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries that feel project inv. reflected their needs - female (percentage) | Value | 0.00 | 0.00 | 0.00 |
Date | September 20, 2016 | December 19, 2017 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Community service sub-projects with satisfactory technical quality | Value | 0.00 | 91.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Number of youth receiving start up grants | Value | 0.00 | 11495.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Communities receiving Grassroots Management Training (GMT) to manage community service sub-projects | Value | 0.00 | 200.00 | 0.00 |
Date | February 7, 2017 | September 30, 2021 | ||
Comment |
Grievance redress mechanism functional | Value | No | Yes | |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Proportion of total cost of community service sub-projects allocated to wages | Value | 0.00 | 67.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries who are employed or self-employed 6 motnhs after receiving the start-up grant | Value | 0.00 | 94.00 | 0.00 |
Date | February 7, 2017 | September 30, 2021 | ||
Comment |
Grievances treated according to the GRM manual | Value | 0.00 | 94.00 | 0.00 |
Date | October 31, 2019 | September 30, 2021 | ||
Comment |
Payments to beneficiaries under component 1 made within one week of due dates specified in Project Implementation Manual | Value | 0.00 | 52.00 | 0.00 |
Date | February 7, 2017 | September 30, 2021 | ||
Comment |
Grievances submitted by women and treated | Value | 0.00 | 100.00 | 0.00 |
Date | October 31, 2019 | September 30, 2021 | ||
Comment |
Beneficiaries of Labor Market programs (number) | Value | 0.00 | 14415.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries of Labor Market programs - Supporting entrepreneurship (number) | Value | 0.00 | 11495.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries of Labor Market programs - Female (number) | Value | 0.00 | 8600.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Beneficiaries of Labor Market programs - Training and re-training (number) | Value | 0.00 | 14415.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Number of youth preparing simple business plans | Value | 0.00 | 14083.00 | 0.00 |
Date | September 20, 2016 | September 30, 2021 | ||
Comment |
Youth completing community service activity and micro-entrepreneurship training | Value | 0.00 | 14120.00 | 0.00 |
Date | February 7, 2017 | September 30, 2021 | ||
Comment |