Rajasthan State Highways Development Program II

Abstract*

The development objective of Second Rajasthan State Highways Development Program Project for India is to build capacity for better management of state highways and to improve traffic flows on selected state highways in the state of Rajasthan. This project has five components. 1) The first component, Operationalization of the Rajasthan State Highways Authority, aims to support operationalization of the Rajasthan State Highways Authority (RSHA), in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to build capacity for better management of state highways and to improve traffic flows on selected state highways in the state of Rajasthan.

Key Details

Project Details

  • P157141

  • Closed

  • Reenu Aneja

  • India

  • India

  • October 17, 2017

  • (as of board presentation)

    March 29, 2019

  • October 14, 2019

  • US$ 525.00 million

  • The State of Rajasthan,Rajasthan State Highway Authority (RSHA)

  • South Asia

  • 2019

  • US$ 250.00 million

  • B

  • April 2, 2024

  • December 31, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 125.55
International Bank for Reconstruction and Development 250.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 250.00
IDA Commitment N/A
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 525.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2024 IBRD-89390 Int Charges 4,690,932.50
May 15, 2024 IBRD-89390 Loan Repay 2,248,309.50
Mar 29, 2019 IBRD-89390 Loan Commitment 250,000,000.00
Nov 15, 2021 IBRD-89390 Int Charges 259,279.03
Nov 15, 2021 IBRD-89390 Int Charges 253,408.10
May 15, 2022 IBRD-89390 Int Charges 252,650.58
May 15, 2022 IBRD-89390 Int Charges 268,379.38
Nov 15, 2022 IBRD-89390 Int Charges 232.87
Nov 15, 2022 IBRD-89390 Int Charges 799,360.06
Nov 15, 2022 IBRD-89390 Int Charges 862.68
Nov 15, 2022 IBRD-89390 Int Charges 240,809.44
Nov 15, 2022 IBRD-89390 Int Charges 196,652.40
Sep 28, 2022 IBRD-89390 Loan Disb 1,930,000.00
Feb 4, 2022 IBRD-89390 Loan Disb 3,080,000.00
Mar 21, 2023 IBRD-89390 Loan Disb 2,150,000.00
Apr 25, 2023 IBRD-89390 Loan Disb 33,258,000.00
Dec 15, 2022 IBRD-89390 Loan Disb 1,370,000.00
Jun 15, 2023 IBRD-89390 Loan Disb 6,034,000.00
Aug 24, 2020 IBRD-89390 Loan Disb 17,430,000.00
Jan 21, 2021 IBRD-89390 Loan Disb 7,690,000.00
Feb 12, 2021 IBRD-89390 Loan Disb 6,610,000.00
May 15, 2021 IBRD-89390 Int Charges 267,672.70
May 15, 2021 IBRD-89390 Int Charges 196,154.06
May 18, 2021 IBRD-89390 Loan Disb 2,900,000.00
Nov 15, 2020 IBRD-89390 Int Charges 303,540.38
Nov 15, 2020 IBRD-89390 Int Charges 68,107.05
Dec 2, 2020 IBRD-89390 Loan Disb 2,520,000.00
Jul 7, 2022 IBRD-89390 Loan Disb 3,580,000.00
May 23, 2022 IBRD-89390 Loan Disb 6,770,000.00
Apr 28, 2022 IBRD-89390 Loan Disb 2,000,000.00
Oct 14, 2019 IBRD-89390 Fee Charges 625,000.00
Oct 14, 2019 IBRD-89390 Loan Disb 625,000.00
May 15, 2020 IBRD-89390 Int Charges 138,561.62
May 15, 2020 IBRD-89390 Int Charges 1,788.89
May 15, 2020 IBRD-89390 Int Charges 310,234.72
May 15, 2020 IBRD-89390 Int Charges 8,878.84
May 15, 2023 IBRD-89390 Int Charges 226,688.64
May 15, 2023 IBRD-89390 Int Charges 95,208.50
Dec 17, 2020 IBRD-89390 Loan Disb 6,540,000.00
May 15, 2023 IBRD-89390 Int Charges 1,687,777.50
Jun 23, 2023 IBRD-89390 Loan Disb 8,334,800.00
Nov 15, 2023 IBRD-89390 Int Charges 160,722.77
Nov 15, 2023 IBRD-89390 Int Charges 176,183.80
Nov 15, 2023 IBRD-89390 Int Charges 3,532,742.80
Nov 8, 2023 IBRD-89390 Loan Disb 4,295,000.00
Dec 18, 2023 IBRD-89390 Loan Disb 5,093,000.00
May 15, 2023 IBRD-89390 Int Charges 634.52
Jan 22, 2024 IBRD-89390 Loan Disb 8,598,000.00
Jul 9, 2024 IBRD-89390 Loan Disb 8,410,000.00
Jul 26, 2024 IBRD-89390 Loan Disb 5,261,000.00
Dec 4, 2023 IBRD-89390 Loan Disb 7,862,000.00
Nov 15, 2023 IBRD-89390 Int Charges 5,365.83
Mar 7, 2024 IBRD-89390 Loan Disb 13,243,000.00
May 3, 2024 IBRD-89390 Loan Disb 6,757,000.00
May 15, 2024 IBRD-89390 Int Charges 205.92
May 16, 2024 IBRD-89390 Loan Disb 22,728,000.00
May 15, 2024 IBRD-89390 Int Charges 137,880.25
May 15, 2024 IBRD-89390 Int Charges 26,693.45

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-08-05
Procurement Satisfactory 2024-08-05
Financial Management Moderately Satisfactory 2024-08-05
Overall Implementation Progress (IP) Moderately Satisfactory 2024-08-05
Monitoring and Evaluation Satisfactory 2024-08-05
Overall Safeguards Rating Moderately Unsatisfactory 2024-08-05
Project Management Satisfactory 2024-08-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel times on project highways for carsValue0.000.0010.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • State Highways actively managed by RSHAValue0.003227.005000.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • Share of State Road Fund resources earmarked for State HighwaysValue0.0050.0050.00
    DateJanuary 1, 2019March 15, 2024January 1, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • RSHA organizational structure and staffing plan approved by RSHA BoardValueNoNoYes
    DateJanuary 1, 2019March 15, 2024December 31, 2020
    Comment
  • Roads rehablitatedValue0.00809.00881.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • RADMS established and operationalValueVery basic data is being collected in a subjectiveIRAD rolled out and functionalPilot implementation in 4 districts
    DateJanuary 1, 2019March 15, 2024December 31, 2022
    Comment
  • Electronic project management system (e-PMS) developed and operationalValue0.004.004.00
    DateJanuary 1, 2019March 15, 2024December 31, 2020
    Comment
  • RSHA rules and regulations notifiedValueNoYesYes
    DateJanuary 1, 2019March 15, 2024December 31, 2019
    Comment
  • Number of kilometres (km) of roads executed under EPC contractsValue0.00577.000.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • Speed Management Program implementedValue0.000.00100.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • Electronic system for monitoring Resettlement Plans (e-RAP) developed and operationalValueManual and paper base data collection, no online mBeing DevelopedEnter the RAP data for all the eleven project corr
    DateJanuary 1, 2019March 15, 2024December 31, 2019
    Comment
  • RSHA Chairperson and Board members appointedValueNoYesYes
    DateJanuary 1, 2019March 15, 2024December 31, 2019
    Comment
  • Number of kilometres (km) executed through PPP/HAM contractsValue0.00232.00293.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • Road safety strategy developed and adoptedValueNoNoYes
    DateJanuary 1, 2019March 15, 2024December 31, 2020
    Comment
  • Improvement in perception of safety among women along project corridorsValue0.000.0040.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • RSHA management (minimum 60%) and technical staff (minimum 60%) appointedValue0.000.00100.00
    DateJanuary 1, 2019March 15, 2024December 31, 2020
    Comment
  • Digital technology solutions implemented on project financed roadsValue0.000.00110.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • improvement in the number of employees aware of and comfortable with approaching the Internal Compliants CommitteeValue0.000.0050.00
    DateFebruary 20, 2020March 15, 2024December 29, 2023
    Comment
  • RSHA investment plan approved by RSHA BoardValueNoNoYes
    DateJanuary 1, 2019March 15, 2024December 30, 2021
    Comment
  • RSHA adopts RAMSValueNoNoYes
    DateJanuary 1, 2019March 15, 2024December 31, 2021
    Comment
  • RSHA training plan developed and implementedValue0.000.00100.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment
  • Grievances filed through project GRM are properly tracked and receive satisfactory responsesValue0.0090.0090.00
    DateJanuary 1, 2019March 15, 2024December 31, 2023
    Comment