Samoa Aviation Investment Project Additional Financing

Development Objective

The project development objective is to improve operational safety and oversight of international air transport and associated infrastructure.

Key Details

Project Details

  • P157241

  • Closed

  • Christopher De Serio

  • Ministry of Finance

  • Samoa

  • February 23, 2016

  • (as of board presentation)

    June 3, 2016

  • N/A

  • US$ 17.87 million

  • Samoa Airport Authority

  • East Asia and Pacific

  • 2016

  • US$ 16.62 million

  • B

  • Not Applicable

  • December 31, 2020

  • Yes

  • BANK APPROVED

  • P143408

  • July 15, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 16.62
Borrower/Recipient 1.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 16.62
IBRD + IDA Commitment 16.62
Lending Instrument
Grant Amount N/A
Total Project Cost** 17.87

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Regulatory certification of safety and security at project airportsValueAPW certifiedAPW certifiedRe-validation of certification of APW in accordan
    DateJanuary 1, 2014February 15, 2016June 30, 2019
    Comment
  • State requirements for safety measured by Universal Safety Oversight Audit Programme (USOAP) reaches global ICAO averageValue56.4356.4341.38
    DateDecember 31, 2010February 15, 2016June 30, 2019
    Comment
  • Modernization of air traffic managementValueNo VSAT or ADS-BVSAT designed and hardware on order; regional ADS-VSAT or ADS-B operational
    DateJuly 1, 2014February 15, 2016June 30, 2017
    Comment
  • Implementation of a regional safety and security levy for departing international passengersValueNo levyAU$5 collected from each departing international pAU$5 collected from each departing international p
    DateJuly 1, 2014February 15, 2016September 30, 2014
    CommentApproved by Government with collection beginning 1 November 2015.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Successful implementation of agreed training planValueNo Training PlanTraining Needs Assessment under preparationTraining Plan completed
    DateJuly 1, 2014February 15, 2016June 30, 2019
    Comment
  • Navigation and safety aids fully operationalValue0.000.00100.00
    DateJuly 1, 2014February 15, 2016June 30, 2018
    CommentDesign and Supervision contract awarded to be awarded in March 2016
  • Rehabilitation of APW pavementValue0.000.00100.00
    DateJuly 1, 2014February 15, 2016June 30, 2018
    CommentDesign of air side pavements drafted.
  • Achievement of Fire Standards at APWValueCategory 8Category 8Category 9
    DateJuly 1, 2014February 15, 2016June 30, 2017
    CommentTender issued as part of regional procurement activity.
  • SAA publishes periodic reports on GRM including resolution ratesValueYesYesYes
    DateDecember 31, 2015February 15, 2016June 30, 2019
    CommentGRM system established.