Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 90.50 |
Borrower/Recipient | 11.96 |
P157425
Closed
Helena Rovner
N/A
June 20, 2016
(as of board presentation)
November 23, 2016
March 22, 2017
US$ 102.47 million
Deconcentrated Operating Entity (EOD) - PRETT SENESCYT
2017
US$ 90.50 million
B
May 28, 2024
November 30, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 90.50 |
Borrower/Recipient | 11.96 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 90.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 90.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 102.47 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2021 | IBRD-86670 | Int Charges | 1,877.87 |
May 15, 2022 | IBRD-86670 | Int Charges | 27,673.08 |
May 15, 2022 | IBRD-86670 | Int Charges | 281,468.88 |
May 15, 2020 | IBRD-86670 | Int Charges | 66,478.15 |
Jul 13, 2020 | IBRD-86670 | Loan Disb | 8,554,230.00 |
Nov 17, 2020 | IBRD-86670 | Int Charges | 44,056.41 |
Nov 17, 2020 | IBRD-86670 | Int Charges | 115,861.98 |
May 15, 2021 | IBRD-86670 | Int Charges | 47,215.18 |
May 15, 2021 | IBRD-86670 | Int Charges | 119,141.92 |
Apr 23, 2021 | IBRD-86670 | Loan Disb | 12,462,220.00 |
May 15, 2019 | IBRD-86670 | Int Charges | 34,221.61 |
May 15, 2019 | IBRD-86670 | Int Charges | 431.50 |
Sep 27, 2018 | IBRD-86670 | Loan Cancel | 18,000,000.00 |
Nov 15, 2019 | IBRD-86670 | Int Charges | 60,697.44 |
Nov 15, 2019 | IBRD-86670 | Int Charges | 39,829.63 |
Nov 15, 2019 | IBRD-86670 | Int Charges | 28,356.16 |
Sep 3, 2019 | IBRD-86670 | Loan Disb | 828,528.90 |
Dec 12, 2019 | IBRD-86670 | Loan Disb | 1,580,003.60 |
Mar 10, 2020 | IBRD-86670 | Loan Cancel | 20,400,000.00 |
May 15, 2020 | IBRD-86670 | Int Charges | 85,611.88 |
May 15, 2018 | IBRD-86670 | Int Charges | 111,918.09 |
May 15, 2018 | IBRD-86670 | Int Charges | 3,674.95 |
Nov 15, 2018 | IBRD-86670 | Int Charges | 113,341.58 |
Nov 15, 2018 | IBRD-86670 | Int Charges | 4,764.06 |
Sep 27, 2018 | IBRD-86670 | Loan Disb | 1,285,677.60 |
May 15, 2019 | IBRD-86670 | Int Charges | 6,865.80 |
May 15, 2019 | IBRD-86670 | Int Charges | 81,968.05 |
Jul 18, 2017 | IBRD-86670 | Loan Disb | 223,525.95 |
Mar 22, 2017 | IBRD-86670 | Fee Charges | 226,250.00 |
Nov 15, 2017 | IBRD-86670 | Int Charges | 52,068.49 |
Nov 15, 2017 | IBRD-86670 | Int Charges | 113,871.07 |
May 15, 2024 | IBRD-86670 | Int Charges | 1,713,783.00 |
May 15, 2024 | IBRD-86670 | Int Charges | 8,051.79 |
Nov 15, 2017 | IBRD-86670 | Int Charges | 2,302.32 |
Nov 23, 2016 | IBRD-86670 | Loan Commitment | 90,500,000.00 |
May 23, 2024 | IBRD-86670 | Loan Disb | 2,769,279.00 |
May 15, 2023 | IBRD-86670 | Int Charges | 1,184,546.10 |
Jul 6, 2023 | IBRD-86670 | Loan Disb | 9,512,000.00 |
Nov 15, 2023 | IBRD-86670 | Int Charges | 1,536,283.10 |
Nov 15, 2023 | IBRD-86670 | Int Charges | 11,544.64 |
Dec 19, 2022 | IBRD-86670 | Loan Disb | 5,900,000.00 |
Nov 15, 2022 | IBRD-86670 | Int Charges | 27,580.12 |
Nov 15, 2022 | IBRD-86670 | Int Charges | 557,514.50 |
May 15, 2023 | IBRD-86670 | Int Charges | 21,190.03 |
Nov 30, 2021 | IBRD-86670 | Loan Disb | 5,281,580.00 |
Nov 15, 2021 | IBRD-86670 | Int Charges | 12,592.15 |
Nov 15, 2021 | IBRD-86670 | Int Charges | 34,236.36 |
Nov 15, 2021 | IBRD-86670 | Int Charges | 234,492.17 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2023-11-30 |
Counterpart Funding | Satisfactory | 2023-11-30 |
Overall Implementation Progress (IP) | Satisfactory | 2023-11-30 |
Procurement | Satisfactory | 2023-11-30 |
Financial Management | Moderately Satisfactory | 2023-11-30 |
Project Management | Satisfactory | 2023-11-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2023-11-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-24-2024 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-20-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO Indicator 1: Enrollment in public technical and technological programs designed and implemented in collaboration with employers. | Value | 10629.00 | 19965.00 | 19965.00 |
Date | April 30, 2019 | March 26, 2024 | December 31, 2021 | |
Comment |
PDO Indicator 3: Availability of reliable data produced by the new integrated administrative and academic management system, is used for decision making by main stakeholders. | Value | No | Yes | No |
Date | December 31, 2016 | March 26, 2024 | June 9, 2023 | |
Comment |
PDO Indicator 2: Persistence rate in technical and technological programs designed and implemented in collaboration with employers. | Value | 0.00 | 49.00 | 49.00 |
Date | December 31, 2016 | March 26, 2024 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IRI 4: Number of teachers and management staff trained. | Value | 0.00 | 462.00 | 462.00 |
Date | December 31, 2016 | March 26, 2024 | December 31, 2021 | |
Comment |
IRI 7: Development and implementation of the module to track graduates. | Value | No | No | No |
Date | December 31, 2016 | March 26, 2024 | December 30, 2022 | |
Comment |
IRI 5: Percentage of programs designed in collaboration with employers. | Value | 30.00 | 37.00 | 37.00 |
Date | December 31, 2016 | March 26, 2024 | December 31, 2020 | |
Comment |
IRI 2: Number of ISTs built or rehabilitated in the targeted provinces. | Value | 0.00 | 4.00 | 3.00 |
Date | December 31, 2016 | March 26, 2024 | June 9, 2023 | |
Comment |
IRI 6: Development and implementation of the administrative and academic management system of ISTs. | Value | No | Yes | Yes |
Date | December 31, 2016 | March 26, 2024 | June 9, 2023 | |
Comment |
IRI 9: Percentage of graduates tracked out of total graduates in the administrative and academic management system | Value | 0.00 | 10.00 | 10.00 |
Date | December 31, 2016 | March 27, 2024 | June 9, 2023 | |
Comment |
IRI 3: Number of ISTs fully equipped in the targeted provinces. | Value | 0.00 | 13.00 | 13.00 |
Date | December 31, 2016 | March 26, 2024 | December 31, 2021 | |
Comment |
IRI 10: Implementation of Gender Plan. | Value | Very Limited gender specific information available | Achieved: Monitoring of access, persistence and gr | Diagnostic of access, persistence, and graduation |
Date | December 31, 2016 | March 26, 2024 | June 9, 2023 | |
Comment |
IRI 11: Survey on beneficiary communities’ satisfaction in the targeted provinces regarding: (a) the process of social management and (b) the results of the implemented new ISTs (Text). | Value | Not available | Partially completed | Not available |
Date | December 31, 2016 | March 26, 2024 | June 9, 2023 | |
Comment |