The objective of the Statistical Capacity Building Project for Haiti is to (i) assist in the production, analyses and dissemination of the findings of the fifth population and housing census and (ii) strengthen the human and technological capacities of the IHSI. There are three components to the project, the first component being human resources and technology. This component will support implementation of activities linked to the census to strengthen...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the project are to (a) assist in the preparation for the Fifth Population and Housing Census and (b) Improve budget management and oversight through timely and more comprehensive reporting

Key Details

Project Details

  • P157531

  • Active

  • Adjalou Celestin Niamien

  • MINISTRY OF ECONOMY AND FINANCE,Ministry of Economy and Finance, MEF

  • Haiti

  • January 13, 2017

  • (as of board presentation)

    March 24, 2017

  • July 7, 2017

  • US$ 19.10 million

  • C

  • N/A

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • March 28, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 5.00
CANADA, Govt. of 6.10
Borrower/Recipient 6.40
Inter-American Development Bank 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 5.00
IBRD + IDA Commitment 5.00
Lending Instrument
Grant Amount 14.10
Total Project Cost** 25.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 31, 2018 IDA-D3110 Loan Commitment 15,000,000.00
Nov 6, 2023 IDA-D3110 Loan Disb 305,932.10
Oct 10, 2017 IDA-D1690 Loan Disb 2,500,000.00
Apr 9, 2019 IDA-D3110 Loan Disb 746,929.40
Dec 18, 2018 IDA-D1690 Loan Disb 2,000,000.00
Aug 31, 2018 IDA-D3110 Loan Disb 1,000,000.00
Mar 2, 2020 IDA-D3110 Loan Disb 373,807.00
Jan 29, 2020 IDA-D3110 Loan Disb 464,422.75
Jul 18, 2019 IDA-D3110 Loan Disb 686,547.60
Nov 20, 2019 IDA-D3110 Loan Disb 326,432.16
Apr 30, 2021 IDA-D3110 Loan Disb 523,240.62
May 12, 2021 IDA-D3110 Loan Disb 414,905.00
Jun 30, 2021 IDA-D3110 Loan Disb 92,650.06
Mar 18, 2021 IDA-D3110 Loan Disb 466,728.53
Mar 11, 2021 IDA-D3110 Loan Disb 123,533.43
Nov 30, 2020 IDA-D3110 Loan Disb 344,160.25
Feb 5, 2021 IDA-D3110 Loan Disb 138,975.10
Oct 2, 2020 IDA-D3110 Loan Disb 371,537.80
Aug 17, 2020 IDA-D3110 Loan Disb 359,671.06
Jul 10, 2020 IDA-D3110 Loan Disb 255,612.86
Aug 25, 2022 IDA-D3110 Loan Disb 373,764.22
Feb 1, 2022 IDA-D3110 Loan Disb 77,208.38
Feb 1, 2022 IDA-D3110 Loan Disb 92,650.05
Feb 1, 2022 IDA-D3110 Loan Disb 290,434.00
Feb 23, 2022 IDA-D3110 Loan Disb 454,862.80
May 25, 2022 IDA-D3110 Loan Disb 30,883.35
Dec 7, 2021 IDA-D3110 Loan Disb 221,142.55
May 9, 2022 IDA-D3110 Loan Disb 237,847.98
Aug 16, 2021 IDA-D3110 Loan Disb 423,696.94
May 3, 2021 IDA-D3110 Loan Disb 92,650.06
May 30, 2023 IDA-D3110 Loan Disb 195,052.75
Jul 19, 2023 IDA-D1690 Loan Disb -753,890.44
Jun 20, 2023 IDA-D3110 Loan Disb 253,273.38
Aug 10, 2023 IDA-D3110 Loan Disb 176,954.45
Mar 20, 2023 IDA-D3110 Loan Disb 247,066.81
Apr 7, 2023 IDA-D1690 Loan Disb -1,086,318.00
Apr 7, 2023 IDA-D1690 Loan Disb -1,939,944.10
Feb 3, 2023 IDA-D3110 Loan Disb 422,931.72
Jun 12, 2024 IDA-D3110 Loan Disb 290,257.22
Jul 31, 2024 IDA-D3110 Loan Disb 8,436.68
May 17, 2024 IDA-D3110 Loan Disb 195,852.12
May 28, 2024 IDA-D3110 Loan Disb 123,551.74
Feb 21, 2024 IDA-D3110 Loan Disb 73,292.12
Jan 23, 2024 IDA-D3110 Loan Disb 186,707.10
Jan 23, 2024 IDA-D3110 Loan Disb 249,528.73
Mar 26, 2024 IDA-D3110 Loan Disb 154,435.10
Aug 30, 2024 IDA-D3110 Loan Disb 106,798.53
Dec 15, 2023 IDA-D3110 Loan Disb 499,057.47
Mar 24, 2017 IDA-D1690 Loan Commitment 5,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-07
Progress towards achievement of PDO Moderately Satisfactory 2024-12-07
Project Management Moderately Satisfactory 2024-12-07
Procurement Moderately Satisfactory 2024-12-07
Financial Management Moderately Unsatisfactory 2024-12-07
Progress towards achievement of PDO Moderately Satisfactory 2024-12-07
Project Management Moderately Satisfactory 2024-12-07
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-07
Monitoring and Evaluation Satisfactory 2024-12-07
Monitoring and Evaluation Satisfactory 2024-12-07
Procurement Moderately Satisfactory 2024-12-07
Financial Management Moderately Unsatisfactory 2024-12-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Coverage of fiscal reports produced by the budget and accounting systemValueNoNoYes
    DateDecember 22, 2017February 21, 2024December 31, 2024
    Comment
  • Timeliness of in Year financial statementValueNoNoYes
    DateDecember 22, 2017February 21, 2024December 31, 2024
    Comment
  • Modeled population distribution estimates produced by IHSIValueNoYesYes
    DateMay 1, 2017February 21, 2024June 30, 2023
    Comment
  • Accountability in the management of public accounts (audit by the SAI, CSCCA)Value0.000.003.00
    DateDecember 22, 2017February 21, 2024December 31, 2024
    Comment
  • Public Access to Procurement auditing InformationValue0.002.006.00
    DateJune 6, 2018February 21, 2024December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Pilot census process and results are evaluated by IHSI staff to identify and make needed adjustmentsValueNoYesYes
    DateNovember 30, 2016June 9, 2023September 30, 2018
    Comment
  • Data from the pilot census uploaded on the central IT systemValueNoYesYes
    DateNovember 30, 2016June 9, 2023May 31, 2018
    Comment
  • Reinforcement of CSCCA technical capacityValue0.008.0020.00
    DateJune 6, 2016February 21, 2024December 30, 2024
    Comment
  • Dissemination strategy designed by IHSI and approved by its managementValueNoYesYes
    DateNovember 30, 2016June 9, 2023September 30, 2018
    Comment
  • Fight against corruptionValue0.0021.0015.00
    DateDecember 22, 2017February 21, 2024December 31, 2024
    Comment
  • Operationalization of the IFMIS modulesValue0.003.005.00
    DateDecember 22, 2017February 21, 2024December 31, 2024
    Comment
  • Deployment of the IFMISValue0.0021.0030.00
    DateJune 6, 2018February 21, 2024December 31, 2024
    Comment
  • Reinforcement of CNMP technical capacityValue0.005.008.00
    DateJune 6, 2018February 21, 2024December 30, 2024