Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 250.00 |
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 78.00 |
P157585
Active
IJsbrand de Jong
Republic of Indonesia
March 30, 2017
(as of board presentation)
June 21, 2018
August 23, 2018
US$ 578.00 million
Republic of Indonesia
2018
US$ 500.00 million
B
June 5, 2024
June 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 250.00 |
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 78.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 250.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | 250.00 |
Total Project Cost** | 578.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 15, 2024 | IBRD-88910 | Int Charges | 5,292,521.00 |
Mar 5, 2024 | IBRD-88910 | Loan Disb | 6,750,000.00 |
Aug 16, 2024 | IBRD-88910 | Loan Disb | 8,250,000.00 |
Jul 15, 2024 | IBRD-88910 | Int Charges | 147,682.42 |
Jul 15, 2024 | IBRD-88910 | Int Charges | 48,911.72 |
Jul 15, 2024 | IBRD-88910 | Int Charges | 4,550.21 |
May 6, 2024 | IBRD-88910 | Loan Disb | 16,500,000.00 |
Jul 15, 2024 | IBRD-88910 | Int Charges | 6,908,370.50 |
Jun 21, 2018 | IBRD-88910 | Loan Commitment | 250,000,000.00 |
Sep 13, 2023 | IBRD-88910 | Loan Disb | 20,000,000.00 |
Jan 15, 2023 | IBRD-88910 | Int Charges | 3,082.19 |
Jan 15, 2023 | IBRD-88910 | Int Charges | 229,301.02 |
Jan 15, 2023 | IBRD-88910 | Int Charges | 1,418,746.00 |
Jan 15, 2023 | IBRD-88910 | Int Charges | 75,833.87 |
Jun 26, 2023 | IBRD-88910 | Loan Disb | 23,500,000.00 |
Jul 15, 2023 | IBRD-88910 | Int Charges | 174,216.38 |
Jul 15, 2023 | IBRD-88910 | Int Charges | 2,940,689.20 |
Dec 8, 2023 | IBRD-88910 | Loan Disb | 17,500,000.00 |
Oct 19, 2023 | IBRD-88910 | Loan Disb | 25,000,000.00 |
Jan 15, 2024 | IBRD-88910 | Int Charges | 3,058.21 |
Jan 15, 2024 | IBRD-88910 | Int Charges | 115,636.81 |
Jan 15, 2024 | IBRD-88910 | Int Charges | 105,896.65 |
Jul 15, 2022 | IBRD-88910 | Int Charges | 9,096.67 |
Jul 15, 2022 | IBRD-88910 | Int Charges | 252,729.03 |
Jul 15, 2022 | IBRD-88910 | Int Charges | 253,469.62 |
Jul 15, 2022 | IBRD-88910 | Int Charges | 3,541.11 |
Aug 25, 2022 | IBRD-88910 | Loan Disb | 5,100,000.00 |
Jan 15, 2022 | IBRD-88910 | Int Charges | 280,683.88 |
Jan 15, 2022 | IBRD-88910 | Int Charges | 110,077.07 |
Jan 11, 2023 | IBRD-88910 | Loan Disb | 20,750,000.00 |
Nov 14, 2022 | IBRD-88910 | Loan Disb | 21,000,000.00 |
May 11, 2023 | IBRD-88910 | Loan Disb | 10,000,000.00 |
Jul 15, 2023 | IBRD-88910 | Int Charges | 568.49 |
Jul 15, 2023 | IBRD-88910 | Int Charges | 119,407.18 |
Jan 15, 2020 | IBRD-88910 | Int Charges | 307,456.94 |
Jan 15, 2020 | IBRD-88910 | Int Charges | 88,768.42 |
Jul 15, 2020 | IBRD-88910 | Int Charges | 303,347.20 |
Jul 15, 2020 | IBRD-88910 | Int Charges | 77,206.57 |
Oct 29, 2020 | IBRD-88910 | Loan Disb | 5,000,000.00 |
Jan 15, 2021 | IBRD-88910 | Int Charges | 304,079.34 |
Jan 15, 2021 | IBRD-88910 | Int Charges | 43,100.86 |
Jul 15, 2021 | IBRD-88910 | Int Charges | 291,596.00 |
Jul 15, 2021 | IBRD-88910 | Int Charges | 72,129.90 |
May 12, 2021 | IBRD-88910 | Loan Disb | 10,750,000.00 |
May 31, 2022 | IBRD-88910 | Loan Disb | 10,000,000.00 |
Mar 8, 2022 | IBRD-88910 | Loan Disb | 10,125,000.00 |
Sep 1, 2021 | IBRD-88910 | Loan Disb | 3,700,000.00 |
Nov 29, 2021 | IBRD-88910 | Loan Disb | 11,000,000.00 |
Feb 1, 2019 | IBRD-88910 | Loan Disb | 5,988,873.50 |
Oct 2, 2018 | IBRD-88910 | Fee Charges | 625,000.00 |
Jan 15, 2019 | IBRD-88910 | Int Charges | 195,205.47 |
Jul 15, 2019 | IBRD-88910 | Int Charges | 97,126.21 |
Jul 15, 2019 | IBRD-88910 | Int Charges | 303,204.28 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-02-05 |
Project Management | Satisfactory | 2025-02-05 |
Financial Management | Moderately Satisfactory | 2025-02-05 |
Monitoring and Evaluation | Satisfactory | 2025-02-05 |
Overall Implementation Progress (IP) | Satisfactory | 2025-02-05 |
Procurement | Moderately Satisfactory | 2025-02-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Area provided with new/improved irrigation or drainage services | Value | 0.00 | 225171.00 | 253102.00 |
Date | July 2, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Number of irrigation service agreements with clear allocation of responsibilities implemented. | Value | 0.00 | 12.00 | 9.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Percentage of crop intensity (paddy) | Value | 180.00 | 194.00 | 200.00 |
Date | July 2, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Number of asset management systems with transparent budget allocation operational | Value | 0.00 | 15.00 | 9.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of farmer households provided with improved irrigation services (Component B) | Value | 0.00 | 295.00 | 362.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Annual performance report of irrigation service providers published (Component A) | Value | 0.00 | 11.00 | 8.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Annual performance report of irrigation service providers published (Component B) | Value | 0.00 | 1.00 | 1.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Irrigation Commission (KOMIR) established and operational (Component A) | Value | 8.00 | 27.00 | 24.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Irrigation Commission (KOMIR) established and operational (Component B) | Value | 1.00 | 3.00 | 3.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Participatory Irrigation Development and Management (PPISP) included in planning documents (Component A) | Value | 9.00 | 30.00 | 19.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Participatory Irrigation Development and Management (PPISP) included in planning documents (Component B) | Value | 1.00 | 4.00 | 2.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
WUAs with trained members in decision making (Component A) | Value | 0.00 | 1207.00 | 390.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
WUAs with trained members in decision making (Component B) | Value | 0.00 | 1826.00 | 480.00 |
Date | October 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
WUAs with trained female members in decision making (Component A) | Value | 0.00 | 66.00 | 50.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Number of WUAFs established and operational (Component A) | Value | 0.00 | 136.00 | 90.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
WUAs with trained female members in decision making (Component B) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component A) | Value | 0.00 | 10.00 | 6.00 |
Date | July 1, 2018 | November 6, 2023 | June 30, 2024 | |
Comment |
Number of WUAFs established and operational (Component B) | Value | 0.00 | 163.00 | 160.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Number of farmer households provided with improved irrigation services (Component A) | Value | 0.00 | 407.00 | 429.00 |
Date | July 1, 2018 | March 10, 2024 | June 30, 2024 | |
Comment |
Establishment and operationalization of grievance mechanism for water users in delivery of irrigation services (Component B) | Value | 0.00 | 1.00 | 1.00 |
Date | April 5, 2022 | March 10, 2024 | June 30, 2024 | |
Comment |