Financier | Commitments |
---|---|
Borrower/Recipient | 10.00 |
IDA Credit from CRW | 50.00 |
IDA Credit | 5.00 |
P157607
Closed
Luquan Tian , Dominic Patella
N/A
May 25, 2016
(as of board presentation)
August 25, 2016
N/A
US$ 15.00 million
N/A
2017
US$ 55.00 million
B
April 3, 2024
January 15, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 10.00 |
IDA Credit from CRW | 50.00 |
IDA Credit | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 55.00 |
IBRD + IDA Commitment | 55.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Employment generated- Male | Value | 0.00 | 6017663.00 | 0.00 |
Date | April 30, 2016 | |||
Comment |
Employment generated- Female | Value | 0.00 | 663211.00 | 0.00 |
Date | April 30, 2016 | |||
Comment |
Employment Generated- Dalit | Value | 0.00 | 1280907.00 | 0.00 |
Date | October 31, 2014 | |||
Comment |
Employment Generated- Janajatis | Value | 0.00 | 3280292.00 | 0.00 |
Date | April 30, 2016 | |||
Comment |
Enhanced resilience of RSDP roads | Value | 0.00 | 0.00 | 20.00 |
Date | June 16, 2016 | June 30, 2019 | ||
Comment |
Reduced bridge vulnerability | Value | 74.00 | 0.00 | 100.00 |
Date | June 16, 2016 | June 30, 2019 | ||
Comment |
Enhanced access as reported by beneficiaries | Value | 0.00 | 0.00 | 70.00 |
Date | May 16, 2016 | May 16, 2016 | July 15, 2019 | |
Comment | % of users reporting positive perception of project interventions. Gender disaggregated satisfaction level results to be reported. |
Percent increase in population in project districts to have all season road access within 20 minutes walking distance | Value | 8.00 | 15.00 | 14.00 |
Date | June 25, 2007 | January 31, 2015 | June 30, 2015 | |
Comment |
Percent decrease in journey times in the project area | Value | 0.00 | 35.00 | 35.00 |
Date | June 25, 2007 | October 31, 2013 | June 30, 2015 | |
Comment |
Direct project beneficiaries | Value | 200000.00 | 752000.00 | 800000.00 |
Date | June 25, 2007 | October 31, 2014 | June 30, 2015 | |
Comment |
Employment generated | Value | 0.00 | 6681000.00 | 250000.00 |
Date | April 30, 2016 | June 30, 2015 | ||
Comment |
Reduce percentage of blacktop SRN in poor condition to 15% | Value | 18% | 11.27% | 15% |
Date | June 25, 2007 | October 31, 2014 | June 30, 2015 | |
Comment |
Decrease in journey times in the project area to key economic centers | Value | 4 hours | 2.6hours | |
Date | June 25, 2007 | October 31, 2013 | June 30, 2015 | |
Comment |
Decrease in journey times in the project ares to key social centers | Value | 4 hours | 3 hours | |
Date | June 25, 2007 | October 31, 2013 | June 30, 2015 | |
Comment |
Female beneficiaries | Value | 50.00 | 53.00 | 50.00 |
Date | June 25, 2007 | October 31, 2014 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Public disclosure of grievance redress report | Value | 0.00 | 0.00 | 3.00 |
Date | May 16, 2016 | May 16, 2016 | July 15, 2019 | |
Comment | Report on grievance redress summarizing complaints and remedies to be disclosed annually from FY 2017. |
Strengthened planning for SRN Roads and Bridges | Value | Last PIP Prepared in 2007 | Revised PIP prepared and endorsed | |
Date | April 19, 2016 | July 13, 2018 | ||
Comment |
Bridge rehabilitation and replacement | Value | 0.00 | 0.00 | 750.00 |
Date | June 30, 2016 | June 30, 2019 | ||
Comment |
Major bridge maintenance | Value | 0.00 | 0.00 | 2000.00 |
Date | June 16, 2016 | June 30, 2019 | ||
Comment |
Minor bridge maintenance | Value | 0.00 | 0.00 | 9500.00 |
Date | June 16, 2016 | June 30, 2019 | ||
Comment |
Roads Board Act Amendment and more trainining and logistics provided | Value | Act amendment drawn up and submitted to Ministry o | RBN act has been tabled in the Parliament and unde | RBN act tabled to the Parliament.100 percent of s |
Date | September 25, 2007 | October 31, 2015 | June 6, 2012 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 680.00 | 705.00 |
Date | April 30, 2016 | June 30, 2015 | ||
Comment |
Share of rural population with access to an all-season road | Value | 7.60 | 15.00 | 14.00 |
Date | November 6, 2007 | April 30, 2016 | June 30, 2015 | |
Comment |
Roads in good and fair condition as a share of total classified roads | Value | 82.00 | 88.70 | 85.00 |
Date | November 6, 2007 | October 31, 2014 | June 30, 2015 | |
Comment |
700 km of target roads received upgrading works | Value | 0.00 | 680.00 | 705.00 |
Date | February 1, 2008 | July 31, 2015 | June 30, 2015 | |
Comment |
2550 km of highways received periodic maintenance | Value | 0.00 | 2608.00 | 2550.00 |
Date | February 1, 2008 | April 30, 2016 | June 30, 2015 | |
Comment |
Road Safety Action Plan & physical works | Value | No action Plan | Road Safety Action Plan developed and approved. | Road Safety action plan implemented and physical w |
Date | February 1, 2008 | October 31, 2014 | June 30, 2015 | |
Comment |
Periodic maintenance of targeted highways and feeder roads backlog executed | Value | 0.00 | 1692.00 | 1000.00 |
Date | February 1, 2008 | January 31, 2015 | June 30, 2015 | |
Comment |
Capacity building in Geo-technical, Environmental and Social aspects and create awareness on HIV/AIDS | Value | a) Geo-technical assessments carried out as recomm | Capacity building in Geo-technical, Environmental | |
Date | July 31, 2015 | June 30, 2015 | ||
Comment |
DoR IT based MIS operational | Value | WAN installed in DoR Offices in Kathmandu | Web based system being adopted for FMIS, GRM, CMS | IT based MIS operational in all DoR divisions |
Date | September 30, 2010 | July 31, 2015 | June 30, 2015 | |
Comment |
Road assessment management tools used for prioritization of road maintenance and upgrading works | Value | This indicator will not be achieved as envisaged. | Road assessment management tools used for prioriti | |
Date | April 30, 2015 | June 30, 2015 | ||
Comment |
Improved quality assurance | Value | The Central Road Lab has been carrying out interna | Quality monitoring plan prepared each year and qua | |
Date | July 31, 2015 | June 30, 2015 | ||
Comment |
Third party technical audit | Value | Third Party Technical audit of upgrading and perio | Third party technical audit carried out for 20 per | |
Date | January 31, 2015 | June 30, 2015 | ||
Comment |
Improve staff capacity within DoR | Value | HR policy updated and 3 year training plan finaliz | Training being undertaken as per the business plan | HR policy updated and 3 year training plan finaliz |
Date | February 22, 2010 | July 31, 2015 | June 30, 2015 | |
Comment |
Government decision to benchmark RBN staff salaries to market rates | Value | RBN staff salaries are paid on a competitive basis | RBN staff salaries benchmarked to market rates | |
Date | September 25, 2007 | October 31, 2015 | June 6, 2012 | |
Comment |
Human Resource Development Plan | Value | No HRD Plan for RBN | RBN has prepared five year business plan (2012-201 | HRD prepared and implemented |
Date | September 25, 2007 | October 31, 2015 | June 6, 2012 | |
Comment |
Number of rural people with access to an all-season road | Value | 71500.00 | 328144.00 | 131000.00 |
Date | November 6, 2007 | April 30, 2016 | June 30, 2015 | |
Comment |
Size of total classified roads | Value | 9399.00 | 10835.00 | 0.00 |
Date | November 6, 2007 | October 31, 2014 | June 30, 2015 | |
Comment |