Cameroon Nachtigal Hydropower Project

Abstract*

The objective of the Nachtigal Hydro Power Project for Cameroon is to increase the availability of renewable energy power and leverage private finance for the project. The Project Company (under Local Loan Guarantee) will covenant, among other things, that it will: (i) use the proceeds of the disbursements under the IBRD-Guaranteed Loan Facility exclusively for the Project and in accordance with the terms and conditions of the IBRD-Guaranteed Loan...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project development objective is to increase the availability of renewable e nergy power and leverage private finance for the Nachtigal Hydropower Project.

Key Details

Project Details

  • P157734

  • Active

  • Ahmed Ousman Abani , Patrice Caporossi, Olayinka Edebiri

  • Government of Cameroon

  • Cameroon

  • April 23, 2018

  • (as of board presentation)

    July 19, 2018

  • N/A

  • US$ 1120.00 million

  • Nachtigal Hydro Power Company

  • Western and Central Africa

  • 2019

  • US$ 430.00 million

  • N/A

  • December 19, 2024

  • June 30, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IBRD Guarantee 300.00
Bilateral Agencies (unidentified) 150.00
Borrower/Recipient 70.00
Foreign Multilateral Institutions (unidentified) 280.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 430.00
Total Project Cost** 1120.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 1, 2021 IBRD-G2640 Int Charges 633,366.20
May 24, 2022 IBRD-G2630 Fee Charges 115,121.75
Dec 19, 2023 IBRD-G2630 Fee Charges 21.88
Dec 19, 2023 IBRD-G2630 Int Charges 21.88
Dec 19, 2023 IBRD-G2640 Fee Charges 39,375.00
Dec 19, 2023 IBRD-G2640 Int Charges 39,375.00
Nov 10, 2023 IBRD-G2640 Fee Charges 21.35
Nov 10, 2023 IBRD-G2640 Int Charges 21.35
Nov 17, 2023 IBRD-G2640 Fee Charges 704,073.30
Nov 17, 2023 IBRD-G2640 Int Charges 704,073.30
May 24, 2022 IBRD-G2630 Int Charges 115,121.75
May 24, 2022 IBRD-G2640 Fee Charges 643,831.75
May 24, 2022 IBRD-G2640 Int Charges 643,831.75
Dec 19, 2022 IBRD-G2640 Fee Charges 679,865.25
Nov 28, 2019 IBRD-G2630 Int Charges 118,282.25
Nov 28, 2019 IBRD-G2640 Fee Charges 463,893.97
Nov 28, 2019 IBRD-G2640 Int Charges 463,893.97
Nov 19, 2020 IBRD-G2630 Fee Charges 127,258.50
May 18, 2020 IBRD-G2640 Int Charges 496,322.47
May 18, 2020 IBRD-G2630 Fee Charges 116,229.00
May 18, 2020 IBRD-G2630 Int Charges 116,229.00
May 20, 2019 IBRD-G2630 Fee Charges 2,627.88
May 20, 2019 IBRD-G2630 Int Charges 2,627.88
May 21, 2019 IBRD-G2630 Fee Charges 117,193.50
May 21, 2019 IBRD-G2630 Int Charges 117,193.50
May 21, 2019 IBRD-G2640 Fee Charges 391,679.00
Nov 19, 2020 IBRD-G2640 Fee Charges 581,804.94
Nov 19, 2020 IBRD-G2640 Int Charges 581,804.94
May 18, 2021 IBRD-G2640 Fee Charges 637,259.44
May 18, 2021 IBRD-G2640 Int Charges 637,259.44
May 18, 2021 IBRD-G2640 Fee Charges 8,087.80
May 18, 2021 IBRD-G2640 Int Charges 8,087.80
May 18, 2021 IBRD-G2640 Fee Charges 0.24
May 18, 2021 IBRD-G2640 Int Charges 0.24
May 18, 2021 IBRD-G2630 Fee Charges 128,359.80
May 18, 2021 IBRD-G2630 Int Charges 128,359.80
May 18, 2021 IBRD-G2630 Fee Charges 2,876.20
May 18, 2021 IBRD-G2630 Int Charges 2,876.20
May 18, 2020 IBRD-G2640 Fee Charges 496,322.47
Dec 19, 2022 IBRD-G2640 Int Charges 679,865.25
Dec 20, 2022 IBRD-G2630 Fee Charges 114,412.25
Dec 20, 2022 IBRD-G2630 Int Charges 114,412.25
May 6, 2024 IBRD-G2630 Fee Charges 21.54
May 6, 2024 IBRD-G2630 Int Charges 21.54
May 6, 2024 IBRD-G2640 Fee Charges 43.09
May 6, 2024 IBRD-G2640 Int Charges 43.09
May 20, 2024 IBRD-G2640 Fee Charges 732,995.90
May 20, 2024 IBRD-G2640 Int Charges 732,995.90
May 20, 2024 IBRD-G2630 Fee Charges 420,685.97
May 20, 2024 IBRD-G2630 Int Charges 420,685.97
Jun 1, 2024 IBRD-G2640 Loan Cancel 2,634,597.00
May 18, 2023 IBRD-G2630 Fee Charges 116,239.62
May 18, 2023 IBRD-G2630 Int Charges 116,239.62
May 18, 2023 IBRD-G2640 Fee Charges 739,724.40
May 18, 2023 IBRD-G2640 Int Charges 739,724.40
Nov 17, 2023 IBRD-G2630 Fee Charges 116,766.04
Nov 17, 2023 IBRD-G2630 Int Charges 116,766.04
Nov 10, 2023 IBRD-G2630 Fee Charges 21.35
Nov 10, 2023 IBRD-G2630 Int Charges 21.35
Dec 1, 2021 IBRD-G2630 Fee Charges 121,706.13
Dec 1, 2021 IBRD-G2630 Int Charges 121,706.13
Dec 1, 2021 IBRD-G2640 Fee Charges 633,366.20
May 21, 2019 IBRD-G2640 Int Charges 391,679.00
May 20, 2019 IBRD-G2640 Fee Charges 7,389.53
May 20, 2019 IBRD-G2640 Int Charges 7,389.53
Nov 28, 2019 IBRD-G2630 Fee Charges 118,282.25
Dec 23, 2018 IBRD-G2630 Fee Charges 638,629.56
Dec 23, 2018 IBRD-G2630 Int Charges 638,629.56
Dec 20, 2018 IBRD-G2640 Fee Charges 795,908.60
Dec 20, 2018 IBRD-G2640 Int Charges 795,908.60
Dec 20, 2018 IBRD-G2640 Fee Charges 1,274,390.40
Dec 20, 2018 IBRD-G2640 Int Charges 1,274,390.40
Dec 22, 2018 IBRD-G2630 Fee Charges 353,972.12
Dec 22, 2018 IBRD-G2630 Int Charges 353,972.12
Jul 19, 2018 IBRD-G2600 Loan Commitment 300,000,000.00
Nov 19, 2020 IBRD-G2630 Int Charges 127,258.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-03-01
Project Management Satisfactory 2024-03-01
Progress towards achievement of PDO Satisfactory 2024-03-01
Financial Management Satisfactory 2024-03-01
Monitoring and Evaluation Satisfactory 2024-03-01
Overall Implementation Progress (IP) Moderately Satisfactory 2024-03-01

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of energy constructed or rehabilitatedValue0.000.00420.00
    DateDecember 24, 2018February 14, 2024November 29, 2024
    Comment
  • Additional operating net capacity available (MW)Value0.000.00400.00
    DateDecember 24, 2018February 14, 2024November 29, 2024
    Comment
  • Private cumulative Capital Mobilized for the Nachtigal Hydropower Project (EUR million), of which from cumulative local sources (EUR million equivalent)Value0 (0)321 (144)351.6 (161.6)
    DateDecember 24, 2018February 14, 2024August 20, 2023
    Comment
  • Avoided global GHG emissions (teqCO2)Value0.000.00836000.00
    DateDecember 24, 2018February 14, 2024November 29, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Construction of the civil works (% of progress)Value093.6%100%
    DateDecember 24, 2018December 29, 2023September 30, 2024
    Comment
  • Supply, erection and commissioning of equipment (% of progress)Value0%87.8%100%
    DateDecember 24, 2018December 29, 2023September 30, 2024
    Comment
  • Construction of the transmission line (% progress)Value0%100%100%
    DateDecember 24, 2018December 29, 2023August 20, 2023
    Comment
  • Implementation of the ESMP (% progress or milestones)Value0%95%100%
    DateDecember 24, 2018December 29, 2023September 30, 2024
    Comment
  • Trial run results of the Nachtigal hydropower Project meet owner's performance targets (yes/no)ValueNoNoYes
    DateDecember 24, 2018December 29, 2023September 30, 2024
    Comment
  • Project related grievances registered under the Project grievance redress mechanism and addressed (percentage)Value0%86%100%
    DateDecember 24, 2018December 29, 2023September 30, 2024
    Comment