Financier | Commitments |
---|---|
IBRD Guarantee | 300.00 |
Bilateral Agencies (unidentified) | 150.00 |
Borrower/Recipient | 70.00 |
Foreign Multilateral Institutions (unidentified) | 280.00 |
P157734
Active
Ahmed Ousman Abani , Patrice Caporossi, Olayinka Edebiri
Government of Cameroon
April 23, 2018
(as of board presentation)
July 19, 2018
N/A
US$ 1120.00 million
Nachtigal Hydro Power Company
2019
US$ 430.00 million
N/A
December 19, 2024
June 30, 2025
BANK APPROVED
Financier | Commitments |
---|---|
IBRD Guarantee | 300.00 |
Bilateral Agencies (unidentified) | 150.00 |
Borrower/Recipient | 70.00 |
Foreign Multilateral Institutions (unidentified) | 280.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 430.00 |
Total Project Cost** | 1120.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 1, 2021 | IBRD-G2640 | Int Charges | 633,366.20 |
May 24, 2022 | IBRD-G2630 | Fee Charges | 115,121.75 |
Dec 19, 2023 | IBRD-G2630 | Fee Charges | 21.88 |
Dec 19, 2023 | IBRD-G2630 | Int Charges | 21.88 |
Dec 19, 2023 | IBRD-G2640 | Fee Charges | 39,375.00 |
Dec 19, 2023 | IBRD-G2640 | Int Charges | 39,375.00 |
Nov 10, 2023 | IBRD-G2640 | Fee Charges | 21.35 |
Nov 10, 2023 | IBRD-G2640 | Int Charges | 21.35 |
Nov 17, 2023 | IBRD-G2640 | Fee Charges | 704,073.30 |
Nov 17, 2023 | IBRD-G2640 | Int Charges | 704,073.30 |
May 24, 2022 | IBRD-G2630 | Int Charges | 115,121.75 |
May 24, 2022 | IBRD-G2640 | Fee Charges | 643,831.75 |
May 24, 2022 | IBRD-G2640 | Int Charges | 643,831.75 |
Dec 19, 2022 | IBRD-G2640 | Fee Charges | 679,865.25 |
Nov 28, 2019 | IBRD-G2630 | Int Charges | 118,282.25 |
Nov 28, 2019 | IBRD-G2640 | Fee Charges | 463,893.97 |
Nov 28, 2019 | IBRD-G2640 | Int Charges | 463,893.97 |
Nov 19, 2020 | IBRD-G2630 | Fee Charges | 127,258.50 |
May 18, 2020 | IBRD-G2640 | Int Charges | 496,322.47 |
May 18, 2020 | IBRD-G2630 | Fee Charges | 116,229.00 |
May 18, 2020 | IBRD-G2630 | Int Charges | 116,229.00 |
May 20, 2019 | IBRD-G2630 | Fee Charges | 2,627.88 |
May 20, 2019 | IBRD-G2630 | Int Charges | 2,627.88 |
May 21, 2019 | IBRD-G2630 | Fee Charges | 117,193.50 |
May 21, 2019 | IBRD-G2630 | Int Charges | 117,193.50 |
May 21, 2019 | IBRD-G2640 | Fee Charges | 391,679.00 |
Nov 19, 2020 | IBRD-G2640 | Fee Charges | 581,804.94 |
Nov 19, 2020 | IBRD-G2640 | Int Charges | 581,804.94 |
May 18, 2021 | IBRD-G2640 | Fee Charges | 637,259.44 |
May 18, 2021 | IBRD-G2640 | Int Charges | 637,259.44 |
May 18, 2021 | IBRD-G2640 | Fee Charges | 8,087.80 |
May 18, 2021 | IBRD-G2640 | Int Charges | 8,087.80 |
May 18, 2021 | IBRD-G2640 | Fee Charges | 0.24 |
May 18, 2021 | IBRD-G2640 | Int Charges | 0.24 |
May 18, 2021 | IBRD-G2630 | Fee Charges | 128,359.80 |
May 18, 2021 | IBRD-G2630 | Int Charges | 128,359.80 |
May 18, 2021 | IBRD-G2630 | Fee Charges | 2,876.20 |
May 18, 2021 | IBRD-G2630 | Int Charges | 2,876.20 |
May 18, 2020 | IBRD-G2640 | Fee Charges | 496,322.47 |
Dec 19, 2022 | IBRD-G2640 | Int Charges | 679,865.25 |
Dec 20, 2022 | IBRD-G2630 | Fee Charges | 114,412.25 |
Dec 20, 2022 | IBRD-G2630 | Int Charges | 114,412.25 |
May 6, 2024 | IBRD-G2630 | Fee Charges | 21.54 |
May 6, 2024 | IBRD-G2630 | Int Charges | 21.54 |
May 6, 2024 | IBRD-G2640 | Fee Charges | 43.09 |
May 6, 2024 | IBRD-G2640 | Int Charges | 43.09 |
May 20, 2024 | IBRD-G2640 | Fee Charges | 732,995.90 |
May 20, 2024 | IBRD-G2640 | Int Charges | 732,995.90 |
May 20, 2024 | IBRD-G2630 | Fee Charges | 420,685.97 |
May 20, 2024 | IBRD-G2630 | Int Charges | 420,685.97 |
Jun 1, 2024 | IBRD-G2640 | Loan Cancel | 2,634,597.00 |
May 18, 2023 | IBRD-G2630 | Fee Charges | 116,239.62 |
May 18, 2023 | IBRD-G2630 | Int Charges | 116,239.62 |
May 18, 2023 | IBRD-G2640 | Fee Charges | 739,724.40 |
May 18, 2023 | IBRD-G2640 | Int Charges | 739,724.40 |
Nov 17, 2023 | IBRD-G2630 | Fee Charges | 116,766.04 |
Nov 17, 2023 | IBRD-G2630 | Int Charges | 116,766.04 |
Nov 10, 2023 | IBRD-G2630 | Fee Charges | 21.35 |
Nov 10, 2023 | IBRD-G2630 | Int Charges | 21.35 |
Dec 1, 2021 | IBRD-G2630 | Fee Charges | 121,706.13 |
Dec 1, 2021 | IBRD-G2630 | Int Charges | 121,706.13 |
Dec 1, 2021 | IBRD-G2640 | Fee Charges | 633,366.20 |
May 21, 2019 | IBRD-G2640 | Int Charges | 391,679.00 |
May 20, 2019 | IBRD-G2640 | Fee Charges | 7,389.53 |
May 20, 2019 | IBRD-G2640 | Int Charges | 7,389.53 |
Nov 28, 2019 | IBRD-G2630 | Fee Charges | 118,282.25 |
Dec 23, 2018 | IBRD-G2630 | Fee Charges | 638,629.56 |
Dec 23, 2018 | IBRD-G2630 | Int Charges | 638,629.56 |
Dec 20, 2018 | IBRD-G2640 | Fee Charges | 795,908.60 |
Dec 20, 2018 | IBRD-G2640 | Int Charges | 795,908.60 |
Dec 20, 2018 | IBRD-G2640 | Fee Charges | 1,274,390.40 |
Dec 20, 2018 | IBRD-G2640 | Int Charges | 1,274,390.40 |
Dec 22, 2018 | IBRD-G2630 | Fee Charges | 353,972.12 |
Dec 22, 2018 | IBRD-G2630 | Int Charges | 353,972.12 |
Jul 19, 2018 | IBRD-G2600 | Loan Commitment | 300,000,000.00 |
Nov 19, 2020 | IBRD-G2630 | Int Charges | 127,258.50 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-03-01 |
Project Management | Satisfactory | 2024-03-01 |
Progress towards achievement of PDO | Satisfactory | 2024-03-01 |
Financial Management | Satisfactory | 2024-03-01 |
Monitoring and Evaluation | Satisfactory | 2024-03-01 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-03-01 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 420.00 |
Date | December 24, 2018 | February 14, 2024 | November 29, 2024 | |
Comment |
Additional operating net capacity available (MW) | Value | 0.00 | 0.00 | 400.00 |
Date | December 24, 2018 | February 14, 2024 | November 29, 2024 | |
Comment |
Private cumulative Capital Mobilized for the Nachtigal Hydropower Project (EUR million), of which from cumulative local sources (EUR million equivalent) | Value | 0 (0) | 321 (144) | 351.6 (161.6) |
Date | December 24, 2018 | February 14, 2024 | August 20, 2023 | |
Comment |
Avoided global GHG emissions (teqCO2) | Value | 0.00 | 0.00 | 836000.00 |
Date | December 24, 2018 | February 14, 2024 | November 29, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Construction of the civil works (% of progress) | Value | 0 | 93.6% | 100% |
Date | December 24, 2018 | December 29, 2023 | September 30, 2024 | |
Comment |
Supply, erection and commissioning of equipment (% of progress) | Value | 0% | 87.8% | 100% |
Date | December 24, 2018 | December 29, 2023 | September 30, 2024 | |
Comment |
Construction of the transmission line (% progress) | Value | 0% | 100% | 100% |
Date | December 24, 2018 | December 29, 2023 | August 20, 2023 | |
Comment |
Implementation of the ESMP (% progress or milestones) | Value | 0% | 95% | 100% |
Date | December 24, 2018 | December 29, 2023 | September 30, 2024 | |
Comment |
Trial run results of the Nachtigal hydropower Project meet owner's performance targets (yes/no) | Value | No | No | Yes |
Date | December 24, 2018 | December 29, 2023 | September 30, 2024 | |
Comment |
Project related grievances registered under the Project grievance redress mechanism and addressed (percentage) | Value | 0% | 86% | 100% |
Date | December 24, 2018 | December 29, 2023 | September 30, 2024 | |
Comment |