Skip to Main Navigation

Cameroon Nachtigal Hydropower Project

Abstract*

The objective of the Nachtigal Hydro Power Project for Cameroon is to increase the availability of renewable energy power and leverage private finance for the project. The Project Company (under Local Loan Guarantee) will covenant, among other things, that it will: (i) use the proceeds of the disbursements under the IBRD-Guaranteed Loan Facility exclusively for the Project and in accordance with the terms and conditions of the IBRD-Guaranteed Loan...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project development objective is to increase the availability of renewable e nergy power and leverage private finance for the Nachtigal Hydropower Project.

Key Details

Project Details

  • P157734

  • Active

  • Ahmed Ousman Abani , Patrice Caporossi, Olayinka Edebiri

  • Government of Cameroon

  • Cameroon

  • April 23, 2018

  • (as of board presentation)

    July 19, 2018

  • N/A

  • US$ 1120.00 million

  • Nachtigal Hydro Power Company

  • Western and Central Africa

  • 2019

  • US$ 430.00 million

  • N/A

  • December 19, 2024

  • June 30, 2025

  • BANK APPROVED

  • Notes