Tuvalu Aviation Investment Project Additional Financing II

Development Objective

The project development objective is to improve the safety and security of air transport and associated infrastructure.

Key Details

Project Details

  • P157779

  • Closed

  • Christopher De Serio

  • Ministry of Finance and Economic Development

  • Tuvalu

  • February 12, 2016

  • (as of board presentation)

    March 31, 2016

  • N/A

  • US$ 2.88 million

  • Ministry of Communications and Transport

  • East Asia and Pacific

  • 2016

  • US$ 2.88 million

  • B

  • July 15, 2021

  • June 15, 2023

  • Yes

  • BANK APPROVED

  • P128940

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 2.88

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 2.88
IBRD + IDA Commitment 2.88
Lending Instrument
Grant Amount N/A
Total Project Cost** 2.88

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated, Non-ruralValue0.000.007.40
    DateMay 23, 2013April 27, 2015June 30, 2015
    Comment
  • Roads in good and fair condition as a share of total classified roadsValue50.00100.00100.00
    DateMay 23, 2013October 1, 2015June 30, 2015
    CommentAchieved.
  • Roads rehabilitated, RuralValue0.008.008.00
    DateMay 23, 2013December 1, 2015June 30, 2015
    CommentAchieved.
  • Indicator One: ICAO certification of safety and security at project airportsValueFUN currently not certifiedFUN currently not certifiedCertification of airports in accordance with agree
    DateDecember 13, 2011February 1, 2016September 30, 2017
    CommentBased on the Tuvalu legislative equivalent of the New Zealand Civil Aviation Rule Part 139 and applicable portions of ICAO Annex14, which will be undertaken by either a third party Civil Aviation Authority or the Pacific Aviation Safety Office (PASO)
  • Indicator Two: Resolution of safety concerns at participating airports reaches global ICAO averageValue95.0095.0040.00
    DateDecember 13, 2011February 1, 2016September 30, 2017
    CommentThe extent (in percentage) of lack of compliance is determined based on the findings of the audit and reported as a lack ofeffective implementation
  • Indicator Three: Modernization of air traffic managementValueNo VSAT or ADS-BNo VSAT or ADS-BVSAT and ADS-B operational
    DateDecember 13, 2011February 1, 2016September 30, 2017
    CommentRegional procurement for ADS-B ground stations underway
  • Indicator Four: Implementation of a regional safety levy for international passengersValueNo levyAU$5 collected from each departing international pAU$5 collected from each departing international p
    DateDecember 13, 2011December 1, 2015June 30, 2014
    CommentAchieved. Levy is currently being collected in the ticket price. Disbursement framework finalized.
  • Size of the total classified networkValue15.4015.4015.40
    DateMay 23, 2013October 1, 2015June 30, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component A - Intermediate Result indicator Five: Number of kilometers of paved roads improvedValue0.0015.4015.40
    DateMay 23, 2013February 1, 2016June 30, 2015
    CommentAchieved
  • Component A: Intermediate Result indicator Two: Rehabilitation of Funafuti runwayValue0.0060.00100.00
    DateDecember 13, 2011February 1, 2016June 30, 2015
    Comment
  • Component A: Intermediate Result indicator One: Navigation and safety aids fully operationalValue0.0010.00100.00
    DateDecember 13, 2011February 1, 2016June 30, 2017
    CommentEquipment procured and under acceptance testing
  • Component A: Intermediate Result indicator Three: Achievement of Fire StandardsValueN/APartially achieved.Category 5
    DateDecember 13, 2011February 1, 2016September 30, 2017
    CommentRegional tender for fire rescue vehicles under procurement
  • Component A: Intermediate Result indicator Four: Funafuti terminal and control tower upgradeValue0.0020.00100.00
    DateDecember 13, 2011February 1, 2016June 30, 2017
    Comment
  • Component B: Intermediate Result indicator One: Successful implementation of agreed training planValueNo training planTraining plan under implementation.Training plan completed
    DateDecember 13, 2011February 1, 2016June 30, 2018
    Comment