Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 1.40 |
P157795
Closed
Marco Aguero
Secretaria de Finanzas de Honduras (SEFIN)
October 6, 2016
(as of board presentation)
April 17, 2017
September 13, 2017
US$ 1.40 million
Honduran Strategic Investment Office (INVEST-H)
2017
US$ 1.40 million
N/A
Not Applicable
June 30, 2020
BANK APPROVED
November 14, 2022
Financier | Commitments |
---|---|
Strategic Climate Fund Grant | 1.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.40 |
Total Project Cost** | 1.40 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2020-03-11 |
Overall | Satisfactory | 2020-03-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-03-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-16-2020 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Governments Climate Resilience policies and/or climate change strategies are informed by the SPCR | Value | 0.00 | 6.00 | 6.00 |
Date | April 20, 2017 | June 30, 2020 | June 30, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of pre-feasibility studies framed within the SPCR, one for each of the prioritized areas (institutional strengthening on climate risk, water security and agriculture) prepared by ICCC | Value | 0.00 | 4.00 | 5.00 |
Date | April 20, 2017 | June 30, 2020 | June 30, 2020 | |
Comment |
Number of key sector institutions (MiAmbiente, MoF, SANAA & Ministry of Agriculture, INVEST-H, among others exchanging information & best practices to mainstream CCA capacity into development planning | Value | 0.00 | 4.00 | 4.00 |
Date | April 20, 2017 | October 30, 2020 | June 30, 2020 | |
Comment |
Proposal for strengthening the regulatory framework and inter-institutional coordination mechanism in priority sectors related to climate change developed | Value | 0.50 | 1.00 | 2.00 |
Date | April 20, 2017 | June 30, 2020 | January 31, 2020 | |
Comment |
Participants in consultation activities during project implementation (number) | Value | 0.00 | 400.00 | 680.00 |
Date | May 31, 2017 | June 30, 2020 | June 30, 2020 | |
Comment |
Participants in consultation activities during project implementation - female | Value | 0.00 | 128.00 | 250.00 |
Date | May 31, 2017 | June 30, 2020 | June 30, 2020 | |
Comment |