Financier | Commitments |
---|---|
IDA Credit | 100.00 |
P157890
Closed
Irajen Appasamy
N/A
May 24, 2016
(as of board presentation)
June 7, 2016
N/A
US$ 100.00 million
N/A
2016
US$ 100.00 million
B
September 13, 2022
June 30, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Bauchi - deployment to rural areas | Value | 15801.00 | 56.00 | 70.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 70 |
Bauchi - Teachers deployed by core subjects | Value | 1790.00 | 30.00 | 70.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 70 |
Anambra - Female Students enrolled in technical and vocational schools | Value | 1947.00 | 1414.00 | 2300.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | No change in end target |
Bauchi - Direct Beneficiaries | Value | 474242.00 | 1027909.00 | 1100000.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 512,656 to 1,100,000 |
Bauchi - System for learning assessment at the state level | Value | No | Yes | |
Date | November 29, 2012 | October 31, 2019 | ||
Comment |
Bauchi - Schools that meet agreed service standards | Value | 0.00 | 50.00 | 70.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 70 |
Ekiti - deployment to rural areas | Value | 4707.00 | 70.00 | 95.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 95 |
Ekiti - Teachers deployed by core subjects | Value | 271.00 | 60.00 | 90.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 86 to 90 |
Bauchi - Male Students enrolled in technical and vocational schools | Value | 5709.00 | 2586.00 | 3000.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 6,939 to 3,000 |
Ekiti - Direct Beneficiaries | Value | 174602.00 | 180000.00 | 200000.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 188,745 to 200,000 |
Ekiti - System for learning assessment at state level | Value | No | Yes | |
Date | November 29, 2012 | October 31, 2019 | ||
Comment |
Ekiti - Schools that meet agreed service standards | Value | 0.00 | 50.00 | 70.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2017 | |
Comment | End target changed from 60 to 70 |
Teachers deployed to rural areas. | Value | 0.00 | 0.00 | 0.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment |
Teachers deployed by core subjects | Value | 0.00 | 0.00 | 0.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment |
Students enrolled in technical and vocational schools | Value | 0.00 | 0.00 | 13137.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | End target changed from 14,969 to 13,137 |
Direct beneficiaries | Value | 1677776.00 | 1750000.00 | 2412275.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 1,813,675 to 2,412,275 |
System for learning assessment at the State level | Value | No | No | Yes |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment |
Schools that meet agreed service standards. | Value | 0.00 | 0.00 | 70.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | End target changed from 60 to 70 |
Anambra - deployment to rural areas | Value | 10735.00 | 70.00 | 90.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 90 |
Anambra - Teachers deployed by core subjects | Value | 1417.00 | 82.00 | 90.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 50 to 90 |
Anambra - Male Students enrolled in technical and vocational schools | Value | 2796.00 | 4971.00 | 5200.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 3,399 to 5,200 |
Anambra - Direct Beneficiaries | Value | 1028932.00 | 961595.00 | 1112275.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | No change in End target |
Anambra - System for learning assessment at State level | Value | No | No | Yes |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | In progress - pilot completed |
Anambra - Schools that meet agreed service standards | Value | 0.00 | 50.00 | 70.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 60 to 70 |
Bauchi - Female Students enrolled in technical and vocational schools | Value | 869.00 | 950.00 | 1200.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 1,056 to 1,200 |
Ekiti - Male Students enrolled in technical and vocational schools | Value | 868.00 | 1000.00 | 1200.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 1,055 to 1,200 |
Ekiti - Female Students enrolled in technical and vocational schools | Value | 126.00 | 140.00 | 170.00 |
Date | November 29, 2012 | February 25, 2016 | October 31, 2019 | |
Comment | End target changed from 153 to 170 |
Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 1944.00 |
Date | October 31, 2019 | |||
Comment |
Adamawa-Direct Beneficiaries | Value | 0.00 | 0.00 | 400000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Bauchi-Direct Beneficiaries | Value | 0.00 | 0.00 | 150000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Borno-Direct beneficiaries | Value | 0.00 | 0.00 | 450000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Gombe-Direct Beneficiaries | Value | 0.00 | 0.00 | 100000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Teachers Deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 46790.00 |
Date | October 31, 2019 | |||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Adamawa-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 9450.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Bauchi-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 9000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Taraba-Direct Beneficiaries | Value | 0.00 | 0.00 | 200000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Yobe-Direct Beneficiaries | Value | 0.00 | 0.00 | 300000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment | [State EMIS will provide disaggregation by gender and geography] |
Borno-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 16070.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Gombe-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 4500.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Taraba-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 5400.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Yobe-Teachers deployed in insurgency-affected areas | Value | 0.00 | 0.00 | 2370.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Adamawa-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 490.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Bauchi-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 160.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Borno-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 870.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Gombe-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 74.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Taraba-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 110.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Yobe-Schools receive grants against approved school improvement plans submitted by SMBCs | Value | 0.00 | 0.00 | 240.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Anambra - Program for measuring student learning and achievement levels | Value | 0 | Program in place | |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | in progress | No change in End Target |
Anambra - School-Based Management Committees that received education quality grants for school improvement plans for the year in accordance with performance standards specified in SBMC Manual | Value | 0.00 | 46.00 | 70.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Anambra - Courses accredited in technical and vocational schools | Value | 0.00 | 0.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | In progress | No change in end target |
Anambra - Partnerships between technical and vocational colleges and private sector | Value | 0.00 | 2.00 | 6.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Bauchi - System for school-specific core-subject teacher placement and deployment | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Bauchi - System for teacher placement and deployment to rural areas | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Bauchi - Program for measuring student learning and achievement levels | Value | 0 | Program in place | |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | in progress | No change in end target |
Bauchi - School-Based Management Committees that received education quality grants for school improvement plans for the year in accordance with performance standards specified in SBMC Manual | Value | 0.00 | 30.00 | 70.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Bauchi - Courses accredited in technical and vocational schools | Value | 0.00 | 0.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | In progress | No change in end target |
Bauchi - Partnerships between technical and vocational colleages and private sector | Value | 0.00 | 2.00 | 6.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Ekiti - System for school-specific core-subject teacher placement and deployment | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Ekiti - System for teacher placement and deployment to rural areas | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Ekiti - Program for measuring student learning and achievement levels | Value | 0 | Program in place | |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | in progress | No change in end target |
System for school-specific core-subject teacher placement and deployment. | Value | 0.00 | 0.00 | 3.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | No change in end target |
System for teacher placement and deployment to rural areas | Value | 0.00 | 0.00 | 3.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | No change in end target |
Program for measuring student learning and achievement levels | Value | 0 | Program in place | |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | in progress | No change in end target |
SBMCs that received education quality grants for school improment plans for the year in accordance with performance standards specified in SBMC Manual | Value | 0.00 | 0.00 | 70.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | No change in end target |
Courses accredited in technical and vocational schools | Value | 0.00 | 0.00 | 0.00 |
Date | November 29, 2012 | October 31, 2019 | ||
Comment | No change in end target |
Partnerships between technical and vocational colleges and private sector | Value | 0.00 | 0.00 | 6.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Anambra - System for school-specific core-subject teacher placement and deployment | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Anambra - System for teacher placement and deployment to rural areas | Value | 0.00 | 2.00 | 3.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
EKITI - School-Based Management Committees that received education quality grants for school improvement plans for the year in accordance with performance standards specified in SBMC Manual | Value | 0.00 | 40.00 | 70.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
Ekiti - Courses accredited in technical and vocational schools | Value | 0.00 | 0.00 | 5.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | In progress | No change in end target |
Ekiti - Partnerships between technical colleges and private sector | Value | 0.00 | 4.00 | 6.00 |
Date | November 29, 2012 | March 31, 2016 | October 31, 2019 | |
Comment | No change in end target |
School-based management committees (SBMCs) functional | Value | 0.00 | 0.00 | 4250.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 46800.00 |
Date | October 31, 2019 | |||
Comment |
Adamawa-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 9450.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Bauchi-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 9000.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Borno-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 16070.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Gombe-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 4500.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Taraba-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 5400.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Yobe-Teachers trained in psychosocial pedagogy | Value | 0.00 | 0.00 | 2370.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Adamawa-School-based management committees (SBMCs) functional | Value | 0.00 | 0.00 | 600.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Bauchi-School-based management committees (SBMCs) functional | Value | 590.00 | 0.00 | 1400.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Borno-School-based management committees (SBMCs) functional | Value | 40.00 | 0.00 | 700.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Gombe-School-based management committees (SBMCs) functional | Value | 75.00 | 0.00 | 450.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Taraba-School-based management committees (SBMCs) functional | Value | 337.00 | 0.00 | 700.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Yobe-School-based management committees (SBMCs) functional | Value | 59.00 | 0.00 | 400.00 |
Date | March 31, 2016 | October 31, 2019 | ||
Comment |
Communities engaged in planning and implementation of school-level management activities | Value | 0.00 | 0.00 | 4250.00 |
Date | May 31, 2019 | |||
Comment |
Adamawa - communities engaged | Value | 0.00 | 0.00 | 600.00 |
Date | October 31, 2019 | |||
Comment |
Bauchi - communities engaged | Value | 0.00 | 0.00 | 1400.00 |
Date | May 31, 2019 | |||
Comment |
Borno - Communities engaged | Value | 0.00 | 0.00 | 700.00 |
Date | May 31, 2019 | |||
Comment |
Gombe - Communities engaged | Value | 0.00 | 0.00 | 450.00 |
Date | October 31, 2019 | |||
Comment |
Taraba - Communities engaged | Value | 0.00 | 0.00 | 700.00 |
Date | May 31, 2019 | |||
Comment |
Yobe - Communities engaged | Value | 0.00 | 0.00 | 400.00 |
Date | May 31, 2019 | |||
Comment |