Financier | Commitments |
---|---|
IDA Credit | 75.00 |
P157898
Closed
Foluso Okunmadewa , Antonia T. Koleva
N/A
May 5, 2016
(as of board presentation)
June 7, 2016
N/A
US$ 75.00 million
N/A
2016
US$ 75.00 million
B
January 17, 2024
June 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 75.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 75.00 |
IBRD + IDA Commitment | 75.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 75.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Poor communities with access to social services (of which IDPs constitute more than 10% of residents) | Value | 1000 Communities (about 500,000 households) | 3,200 new communities(about 1,550,000 households | 3750 Communities (about 1,500,000 households of wh |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Poor communities with access to natural resource management services (of which IDPs constitute more than 10% of residents) | Value | 50 Communities (about 25,000 households) | 750 new communities (about 375,000 households) | 800 communities (about 400,000 households of which |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Annual Local Government budget in participating States incorporating Community development plans increases yearly | Value | 1% | 42% | 45% |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Direct project Beneficiaries, including IDPs (measured by the number of poor people with access to social services) | Value | 0.00 | 2500000.00 | 3200000.00 |
Date | July 1, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Completed microprojects, that are operational and maintained one year after completion. | Value | 300 microprojects | 7947 (6677 new ones) | 8500 |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Health Centers built or rehabilitated | Value | 50 | 1094 (1044 new ones) | 1500 |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Classrooms built or rehabilitated | Value | 100 | 1533 (1433 new ones) | 2000 |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Students enrolled in primary education schools supported by project | Value | 0 | 32,000 new enrolments (Boys 18,000 and Girls 14,00 | 50000 |
Date | March 31, 2009 | November 25, 2015 | December 31, 2017 | |
Comment |
LGAs that received training have integrated CDD approach in the formation of their Local development plans | Value | 0 | 60% | 65% |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Project funds that are channeled to community-driven investments | Value | 0% | 72% | 75% |
Date | March 31, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Community Development Plans that are approved and funded | Value | 0.00 | 2683.00 | 3750.00 |
Date | June 30, 2009 | November 25, 2015 | June 30, 2020 | |
Comment |
Gender and Vulnerable Groups (GVG) (women/gender and other vulnerable groups) register or list available in communities implementing CSDP. | Value | 0.00 | 0.00 | 500.00 |
Date | June 30, 2020 | |||
Comment |
Gender and Vulnerable Groups (GVG) (women/gender and other vulnerable groups) with functional micro-projects or specialized services | Value | 175.00 | 385.00 | 500.00 |
Date | March 26, 2014 | November 25, 2015 | June 30, 2020 | |
Comment |
Number of damaged / host communities supported by CSDA | Value | 0.00 | 0.00 | 250.00 |
Date | April 20, 2016 | June 30, 2020 | ||
Comment |
Number of community housing created / supported by CSDA | Value | 0.00 | 0.00 | 1000.00 |
Date | April 20, 2016 | June 30, 2020 | ||
Comment |
Number of trauma and psychosocial support sessions conducted | Value | 0.00 | 0.00 | 200.00 |
Date | April 20, 2016 | June 30, 2020 | ||
Comment |
Percentage of project beneficiaries satisfied with the project interventions | Value | 0.00 | 0.00 | 60.00 |
Date | April 20, 2016 | June 30, 2020 | ||
Comment |
Percentage of grievances addressed within the timeframe stipulated in the Operations Manual | Value | 0.00 | 0.00 | 70.00 |
Date | April 20, 2016 | June 30, 2020 | ||
Comment |