Financier | Commitments |
---|---|
Global Environment Facility - IBRD as Implementing Agency | 13.70 |
P157909
Closed
Andrew Zakharenka , Maud Juquois, Mampionona Amboarasoa
Republic of Madagascar
March 23, 2017
(as of board presentation)
March 23, 2017
October 26, 2017
US$ 0.00 million
Project Implementation Unit-PADAP,Ministry of Environment and Sustainable Development,Ministry of Water, Sanitation and Hygiene,Ministry of Agriculture and Livestock
2017
US$ 13.70 million
B
Not Applicable
April 30, 2024
BANK APPROVED
April 17, 2024
Financier | Commitments |
---|---|
Global Environment Facility - IBRD as Implementing Agency | 13.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 13.70 |
Total Project Cost** | N/A |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2023-12-22 |
Financial Management | Moderately Satisfactory | 2023-12-22 |
Counterpart Funding | Satisfactory | 2023-12-22 |
Project Management | Satisfactory | 2023-12-22 |
Monitoring and Evaluation | Satisfactory | 2023-12-22 |
Overall Implementation Progress (IP) | Satisfactory | 2023-12-22 |