Financier | Commitments |
---|---|
State and Peace Building Fund | 4.90 |
P157923
Closed
Marc Navelet Noualhier , Aguiratou Savadogo-Tinto
Government of Central African Republic
December 15, 2015
(as of board presentation)
April 3, 2016
April 15, 2016
US$ 4.90 million
United Nations Office for Project Services
2016
US$ 4.90 million
B
Not Applicable
September 30, 2019
BANK APPROVED
January 24, 2023
Financier | Commitments |
---|---|
State and Peace Building Fund | 4.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.90 |
Total Project Cost** | 4.90 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2019-10-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2019-10-21 |
Overall | High | 2019-10-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2020 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Female beneficiaries | Value | 0.00 | 50.00 | 50.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Share of man-days created for women | Value | 0.00 | 33.00 | 27.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 37000.00 | 37000.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of man-days created through the Labor Intensive Public Works activities (including share of man-days created for women) | Value | 0.00 | 75000.00 | 100830.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Average daily traffic (all types of vehicle included) (vehicle per day) | Value | 3.00 | 120.00 | 20.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of bridges rehabilitated | Value | 0.00 | 13.00 | 12.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of culverts rehabilitated | Value | 0.00 | 49.00 | 25.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of culverts constructed | Value | 0.00 | 57.00 | 57.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of ditches constructed | Value | 0.00 | 200000.00 | 63000.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of bridges constructed | Value | 0.00 | 1.00 | 1.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of rain barriers constructed | Value | 0.00 | 14.00 | 12.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of MINTP offices rehabilitated and re-equipped | Value | 0.00 | 2.00 | 2.00 |
Date | March 1, 2016 | September 30, 2019 | October 12, 2018 | |
Comment |
Number of technical assistance workshops delivered to MINTP | Value | 0.00 | 4.00 | 4.00 |
Date | March 1, 2016 | September 30, 2019 | October 12, 2018 | |
Comment |
Number of functioning rain barriers | Value | 0.00 | 14.00 | 12.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |
Number of kilometers of road maintained under the project | Value | 0.00 | 333.00 | 333.00 |
Date | March 1, 2016 | March 1, 2016 | October 12, 2018 | |
Comment |