China: Jiangxi Eco-industrial Parks Project

Development Objective

To strengthen Jiangxi’s institutional and regulatory framework for eco-industrial parks (EIP) to be consistent with the International EIP Framework and demonstrate its implementation in the Fuzhou New Industries Zone.

Key Details

Project Details

  • P158079

  • Active

  • Minghe Tao

  • People's Republic of China

  • China

  • February 18, 2020

  • (as of board presentation)

    June 18, 2020

  • October 16, 2020

  • US$ 400.00 million

  • Jiangxi Development and Reform Commission,Fuzhou New Industries Zone

  • East Asia and Pacific

  • 2020

  • US$ 200.00 million

  • B

  • April 21, 2024

  • December 31, 2026

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 127.35
International Bank for Reconstruction and Development 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 200.00
IDA Commitment N/A
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 1, 2023 IBRD-91190 Int Charges 1,564.08
Jun 1, 2023 IBRD-91190 Int Charges 248,068.47
Jun 1, 2023 IBRD-91190 Int Charges 30,085.09
Dec 1, 2023 IBRD-91190 Int Charges 640.48
Dec 1, 2023 IBRD-91190 Int Charges 248,123.28
Dec 1, 2023 IBRD-91190 Int Charges 69,245.70
Nov 22, 2023 IBRD-91190 Loan Disb 1,000,000.00
Jun 26, 2024 IBRD-91190 Loan Disb 2,000,000.00
Jun 26, 2024 IBRD-91190 Loan Disb 3,010,686.50
Mar 12, 2024 IBRD-91190 Loan Disb 14,000,000.00
Feb 20, 2024 IBRD-91190 Loan Disb 2,504,128.00
Jun 1, 2024 IBRD-91190 Int Charges 2,000.24
Jun 1, 2024 IBRD-91190 Int Charges 235,623.12
Jun 1, 2024 IBRD-91190 Int Charges 422,854.16
Jun 1, 2024 IBRD-91190 Int Charges 61.64
Jun 18, 2020 IBRD-91190 Loan Commitment 200,000,000.00
Mar 17, 2021 IBRD-91190 Fee Charges 500,000.00
Jun 1, 2021 IBRD-91190 Int Charges 96,994.54
Jun 1, 2021 IBRD-91190 Int Charges 249,199.03
Dec 1, 2021 IBRD-91190 Int Charges 250,684.92
May 27, 2022 IBRD-91190 Loan Disb 1,000,000.00
Jun 1, 2022 IBRD-91190 Int Charges 249,280.81
Dec 1, 2022 IBRD-91190 Int Charges 249,431.48
Dec 1, 2022 IBRD-91190 Int Charges 20,624.34
Dec 1, 2022 IBRD-91190 Int Charges 34.24
Dec 1, 2022 IBRD-91190 Int Charges 199.09
Sep 1, 2023 IBRD-91190 Loan Disb 2,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2025-01-21
Project Management Moderately Satisfactory 2025-01-21
Monitoring and Evaluation Moderately Satisfactory 2025-01-21
Progress towards achievement of PDO Moderately Satisfactory 2025-01-21
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-01-21
Financial Management Satisfactory 2025-01-21

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDO #1 Share of industrial parks in Jiangxi regularly reporting data under the new provincial EIP performance monitoring systemValue0.003.7075.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • PDO #2 Beneficiaries' aggregated satisfaction rate of the FNIZValue0.0081.4970.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • PDO #2-1 Satisfaction rate of environmental qualityValue0.000.000.00
    Date
    Comment
  • PDO #2-2 Satisfaction rate of social inclusivenessValue0.000.000.00
    Date
    Comment
  • PDO #2-3 Satisfaction rate of doing business environmentValue0.000.000.00
    Date
    Comment
  • PDO #3 Amount of attracted investment meeting the green industries screening criteria developed under this projectValue0.00276528571.00100000000.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • #PDO 4 Companies in the FNIZ become eligible for greening financingValueNoNoYes
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IRI #1-1 Number of capacity building events for the industrial parks to contribute to and deploy the new provincial EIP frameworkValue0.003.0010.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #2-1 Floor area of buildings receiving EDGE certificateValue0.000.00362000.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #3-1 Increase in area of green open spaceValue0.000.00281000.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #4-1 Number of citizen engagement events organizedValue0.0016.0010.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #1-2 Number of industrial parks that develop comprehensive action plans to adopt the new EIP frameworkValue0.004.004.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #2-2 Percentage of project-financed public buildings with dedicated nursing rooms meeting national standardValue0.000.0080.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #3-2 Water quality of the two lakesValueClass IVClass IVClass III
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #4-2 Number of people trained to help the zone narrow its gaps against the international EIP frameworkValue0.0074.00500.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #2-3 Number of firms receiving clean production certificateValue40.0051.0060.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #3-3 Increase in area of storm-water management facilities (i.e., green rooftop, permeable pavement and retention pond)Value0.000.0070000.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment
  • IRI #4-2-1 Percentage of female participantsValue0.000.0040.00
    Date
    Comment
  • IRI #4-3 Number of technical assistance (TA) activities completedValue0.000.004.00
    DateJune 30, 2020November 27, 2023December 31, 2026
    Comment