Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 180.00 |
Borrowing Country's Fin. Intermediary/ies | 100.00 |
Municipalities of Borrowing Country | 32.63 |
P158215
Active
Ahmed Eiweida , Minghe Tao
People's Republic of China
June 19, 2017
(as of board presentation)
June 4, 2019
November 11, 2019
US$ 250.00 million
Gansu Provincial Department of Culture and Tourism,Gansu Financing Holding Group
2019
US$ 180.00 million
A
August 15, 2024
June 30, 2025
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 180.00 |
Borrowing Country's Fin. Intermediary/ies | 100.00 |
Municipalities of Borrowing Country | 32.63 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 180.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 180.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 250.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 1, 2020 | IBRD-89710 | Int Charges | 160,972.84 |
Feb 17, 2020 | IBRD-89700 | Fee Charges | 120,860.43 |
Feb 17, 2020 | IBRD-89710 | Fee Charges | 314,074.50 |
Jun 1, 2020 | IBRD-89710 | Int Charges | 67,885.80 |
Jun 1, 2020 | IBRD-89700 | Int Charges | 26,123.43 |
Jun 1, 2020 | IBRD-89700 | Int Charges | 61,944.68 |
Dec 2, 2020 | IBRD-89700 | Loan Disb | 4,820,800.00 |
Mar 22, 2021 | IBRD-89710 | Loan Disb | 595,525.00 |
Dec 1, 2020 | IBRD-89700 | Int Charges | 66,732.74 |
Dec 1, 2020 | IBRD-89710 | Int Charges | 173,415.39 |
Jun 1, 2021 | IBRD-89710 | Int Charges | 176,216.19 |
Jun 1, 2021 | IBRD-89710 | Int Charges | 831.67 |
Jun 1, 2021 | IBRD-89700 | Int Charges | 61,866.38 |
Jun 1, 2021 | IBRD-89700 | Int Charges | 21,877.84 |
Jun 18, 2021 | IBRD-89710 | Loan Disb | 595,900.00 |
Jun 21, 2021 | IBRD-89700 | Loan Disb | 1,784,325.00 |
Oct 28, 2021 | IBRD-89700 | Loan Disb | 4,410,470.00 |
Dec 1, 2021 | IBRD-89710 | Int Charges | 162,387.55 |
Dec 1, 2021 | IBRD-89710 | Int Charges | 3,951.20 |
Dec 1, 2021 | IBRD-89700 | Int Charges | 54,716.16 |
Dec 1, 2021 | IBRD-89700 | Int Charges | 28,252.80 |
Jun 24, 2022 | IBRD-89700 | Loan Disb | 3,161,400.00 |
Oct 15, 2021 | IBRD-89710 | Loan Disb | 2,322,300.00 |
Jun 1, 2022 | IBRD-89700 | Int Charges | 948.43 |
Jun 1, 2022 | IBRD-89700 | Int Charges | 2,590.25 |
Jun 1, 2022 | IBRD-89700 | Int Charges | 47,161.42 |
Jun 1, 2022 | IBRD-89700 | Int Charges | 44,847.22 |
Dec 8, 2021 | IBRD-89710 | Loan Disb | 1,850,932.80 |
Jun 2, 2022 | IBRD-89710 | Loan Disb | 1,442,973.00 |
Jun 24, 2022 | IBRD-89710 | Loan Disb | 2,107,600.00 |
Jun 10, 2022 | IBRD-89710 | Loan Disb | 100,627.40 |
Aug 12, 2022 | IBRD-89710 | Loan Disb | 1,029,200.00 |
Aug 16, 2022 | IBRD-89710 | Loan Disb | 2,111,366.00 |
Jun 1, 2022 | IBRD-89710 | Int Charges | 1,324.85 |
Jun 1, 2022 | IBRD-89710 | Int Charges | 148,403.42 |
Jun 1, 2022 | IBRD-89710 | Int Charges | 18,023.92 |
Jun 1, 2022 | IBRD-89710 | Int Charges | 690.04 |
Jan 6, 2023 | IBRD-89710 | Loan Disb | 2,784,451.20 |
Nov 17, 2022 | IBRD-89710 | Loan Disb | 3,192,565.80 |
Dec 23, 2021 | IBRD-89710 | Loan Disb | 312,750.12 |
Dec 1, 2022 | IBRD-89700 | Int Charges | 42,750.15 |
Dec 1, 2022 | IBRD-89700 | Int Charges | 81,605.33 |
Dec 1, 2022 | IBRD-89710 | Int Charges | 138,336.73 |
Dec 1, 2022 | IBRD-89710 | Int Charges | 57,387.72 |
Sep 12, 2023 | IBRD-89710 | Loan Disb | 4,229,837.00 |
Apr 3, 2023 | IBRD-89710 | Loan Disb | 3,351,576.50 |
Jul 27, 2023 | IBRD-89710 | Loan Disb | 4,513,036.00 |
May 26, 2023 | IBRD-89710 | Loan Disb | 2,788,625.00 |
Jun 1, 2023 | IBRD-89710 | Int Charges | 316.86 |
Jun 1, 2023 | IBRD-89710 | Int Charges | 1,083.85 |
Jun 1, 2023 | IBRD-89710 | Int Charges | 131,033.40 |
Jun 1, 2023 | IBRD-89710 | Int Charges | 326,502.28 |
Jun 30, 2023 | IBRD-89710 | Loan Disb | 2,289,807.50 |
Sep 7, 2023 | IBRD-89700 | Loan Disb | 1,391,780.00 |
Jun 1, 2023 | IBRD-89700 | Int Charges | 43,119.14 |
Jun 1, 2023 | IBRD-89700 | Int Charges | 254,381.95 |
Dec 1, 2023 | IBRD-89710 | Int Charges | 20,165.96 |
Dec 1, 2023 | IBRD-89710 | Int Charges | 117,599.53 |
Dec 1, 2023 | IBRD-89710 | Int Charges | 793,532.40 |
Nov 7, 2023 | IBRD-89710 | Loan Disb | 5,082,168.00 |
Dec 8, 2023 | IBRD-89710 | Loan Disb | 1,055,241.10 |
Dec 1, 2023 | IBRD-89700 | Int Charges | 43,292.44 |
Dec 1, 2023 | IBRD-89700 | Int Charges | 365,253.94 |
Dec 1, 2023 | IBRD-89710 | Int Charges | 1,474.00 |
Aug 27, 2024 | IBRD-89700 | Loan Disb | 89,320.00 |
May 31, 2024 | IBRD-89700 | Loan Disb | 6,000,050.00 |
Feb 29, 2024 | IBRD-89710 | Loan Disb | 2,447,900.00 |
Apr 12, 2024 | IBRD-89710 | Loan Disb | 4,060,810.80 |
Jan 12, 2024 | IBRD-89710 | Loan Disb | 2,391,603.80 |
Jul 3, 2024 | IBRD-89710 | Loan Disb | 2,988,201.80 |
Mar 22, 2024 | IBRD-89710 | Loan Disb | 201,474.20 |
Jun 1, 2024 | IBRD-89710 | Int Charges | 16,060.73 |
Jun 1, 2024 | IBRD-89710 | Int Charges | 99,434.80 |
Jun 1, 2024 | IBRD-89710 | Int Charges | 1,187,873.60 |
Aug 16, 2024 | IBRD-89700 | Loan Disb | 4,100,575.50 |
Jun 1, 2024 | IBRD-89700 | Int Charges | 42,022.29 |
Jun 1, 2024 | IBRD-89700 | Int Charges | 403,552.00 |
Jun 1, 2024 | IBRD-89710 | Int Charges | 849.20 |
Jun 4, 2019 | IBRD-89700 | Loan Commitment | 50,000,000.00 |
Jun 4, 2019 | IBRD-89710 | Loan Commitment | 130,000,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-12-19 |
Project Management | Satisfactory | 2024-12-19 |
Financial Management | Satisfactory | 2024-12-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-19 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-19 |
Monitoring and Evaluation | Satisfactory | 2024-12-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1A Number of new jobs created by project-supported MSEs (disaggregated by national bottom 40% and gender) | Value | 0.00 | 3168.00 | 3300.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2A Number of people benefiting from urban-rural regeneration, including improved access to infrastructure and services, in the project areas (disaggregated by bottom 40% and gender) | Value | 0.00 | 2440.00 | 4676098.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3A Number of PFIs that have completed and executed their institutional development plans with project's support. | Value | 0.00 | 1.00 | 3.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
4 Beneficiaries satisfied with project results (disaggregated by gender) | Value | 0.00 | 93.00 | 80.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
1B Number of new jobs created in project-supported creative industries and tourism facilities (disaggregated by bottom 40% and gender) | Value | 0.00 | 679.00 | 2205.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3B Number of integrated culture and tourism strategies adopted and budgeted in provincial and local plans | Value | 0.00 | 0.00 | 6.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
1C Amount of co-financing leveraged by the Participating Financial Institutions (PFIs) | Value | 0.00 | 50000000.00 | 100000000.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1.1 Number of MSEs benefiting from line of credit (disaggregated by national bottom 40% and percent of female owners) | Value | 0.00 | 4811.00 | 1380.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.1 Length of sewerage networks constructed or rehabilitated | Value | 0.00 | 5.71 | 59.50 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.1 Number of MSEs received business start-up advisory services (disaggregated by national bottom 40% and gender) | Value | 0.00 | 0.00 | 180.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.2 Number of households with access to improved sanitation | Value | 0.00 | 205.00 | 8211.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.2 Non-performing loan ratio of sub-borrowers is less than 5% in new portfolio financed under the project as a result of increasedcapacity of participating financial institutions | Value | NA | Yes | Yes |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
1.2 Number of PFIs in the project | Value | 0.00 | 1.00 | 3.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.3 Length of electricity networks constructed or rehabilitated | Value | 0.00 | 0.00 | 5.45 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.3 Number of trained staff in participating financial institutions (disaggregated by gender). | Value | 0.00 | 0.00 | 200.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.4 Length of roads constructed or rehabilitated | Value | 0.00 | 6.22 | 66.22 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.4 Site management plans in place with budget | Value | 0.00 | 0.00 | 3.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.5 Area of green space constructed or upgraded | Value | 0.00 | 0.00 | 534.33 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.5 Number of staff trained on urban-rural regeneration, creative industries, site management and tourism policies (disaggregated by gender) | Value | 0.00 | 1085.00 | 560.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.6 Number of traditional houses and public buildings restored | Value | 0.00 | 135.00 | 200.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.6 Socioeconomic impact evaluation surveys conducted and evaluated | Value | 0.00 | 2.00 | 4.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
2.7 Number of creative industry centers and tourism facilities constructed | Value | 0.00 | 0.00 | 11.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.7 Number of periodic project dissemination strategies developed and accompanying knowledge materials produced | Value | 0.00 | 1.00 | 3.00 |
Date | March 29, 2019 | November 30, 2023 | June 30, 2025 | |
Comment |
3.8 Number of global knowledge dissemination events completed (conferences, workshops and expos) | Value | 0.00 | 3.00 | 8.00 |
Date | March 17, 2022 | November 30, 2023 | June 30, 2025 | |
Comment |