Financier | Commitments |
---|---|
MDTF for SEMCAR Phase 1 | 2.82 |
P158239
Closed
Ruxandra Burdescu , Davide Zucchini
Treasury Department,Government of Antigua and Barbuda,Government of Saint Lucia,Inland Revenue Department,Ministry of Finance
February 2, 2016
(as of board presentation)
March 9, 2016
March 22, 2016
US$ 2.82 million
Project Coordination Unit,Ministry of Sustainable Development,Government of Antigua and Barbuda
2016
US$ 2.82 million
C
Not Applicable
April 30, 2017
BANK APPROVED
September 12, 2023
Financier | Commitments |
---|---|
MDTF for SEMCAR Phase 1 | 2.82 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.82 |
Total Project Cost** | 2.82 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-08-30 |
Progress towards achievement of PDO | Moderately Satisfactory | 2016-08-30 |
Overall | Satisfactory | 2016-08-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Countries with upgraded or modernized IT systems that enhance Tax Administration, Customs Management or PFM | Value | 1.00 | 1.00 | 4.00 |
Date | February 2, 2016 | August 15, 2016 | August 31, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Infrastructure equipment is acquired to support implementation of the ASYCUDA World Customs Administration System | Value | No | No | Yes |
Date | February 2, 2016 | August 15, 2016 | August 31, 2016 | |
Comment |
Countries with updated FMIS | Value | 0.00 | 0.00 | 1.00 |
Date | February 2, 2016 | August 15, 2016 | August 31, 2016 | |
Comment |
Countries with tax systems that can perform business analytics and generate performance management reports | Value | 1.00 | 1.00 | 2.00 |
Date | February 2, 2016 | August 15, 2016 | August 31, 2016 | |
Comment |