Skip to Main Navigation

Kosovo Agriculture and Rural Development Project - Third Additional Financing

Development Objective

The development objective of the project is to improve productivity of and access to markets by project beneficiaries in the horticulture and livestock subsectors of Kosovo and strengthen the institutional capacity of the Ministry of Agriculture, Forestry and Rural Development.

Key Details

Project Details

  • P158710

  • Closed

  • Meeta Sehgal

  • Ministry of Finance

  • Kosovo

  • February 2, 2017

  • (as of board presentation)

    April 28, 2017

  • N/A

  • US$ 21.93 million

  • Ministry of Agriculture, Forestry and Rural Development

  • Europe and Central Asia

  • 2017

  • US$ 22.00 million

  • B

  • Not Applicable

  • December 31, 2022

  • Yes

  • BANK APPROVED

  • P112526

  • July 8, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 22.00
Local Beneficiaries 5.84

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 22.00
IBRD + IDA Commitment 22.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 21.93

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Farmers adopting improved agricultural technologiesValue0.00656.001537.00
    DateOctober 3, 2016December 5, 2016June 30, 2021
    CommentBeneficiaries supported by RDGP and Aggregators and CF
  • Sales as measured by Milk sold to processors (livestock proxy)Value19.0021.0024.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Orchards planted in the country (horticulture proxy)Value3400.003637.004185.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Direct project beneficiariesValue0.003697.003928.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Female beneficiariesValue0.0012.2010.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Yields of key crops supported by the project (Tons/ha)Value02330
    DateOctober 3, 2016December 5, 2016June 30, 2021
    CommentThese values are for peppers serving as proxy for the horticulture sector. Given the demand-driven nature of the project, theactual crops supported will be evident and subsequently the increase in yields of these crops will be measured in the latter stageof Project Year 1. Preliminary analyses demonstrate that vegetables and fruits that are of potential support include peppers,tomatoes, cucumbers, apples and berries. Target values to be determined before end of Project Year 1
  • Yields of milk production per animal on livestock farms supported by the project (Liters/cow)Value011.213.4
    DateOctober 3, 2016December 5, 2016June 30, 2021
    CommentLiters of milk per cow on farms supported under RDGP is expected to go up by 20% by Project end. Project support is provided onlyto those semi-commercial/commercial livestock farmers that own 10 or more cows
  • Farmers reached with agricultural assets or servicesValue0.003667.006983.00
    DateOctober 3, 2016December 5, 2016June 30, 2021
    Comment
  • of which femaleValue0.00550.001047.00
    DateOctober 3, 2016December 5, 2016June 30, 2021
    Comment
  • Preparation of Rural Development Grant Program (RDGP) sub-measures for investment support in line with IPARD GuidelinesValueNoNoYes
    DateOctober 3, 2016November 4, 2016June 30, 2021
    Comment
  • Sales of milk increased to processing companiesValue0.00100.00121.40
    DateOctober 3, 2016November 4, 2016June 30, 2021
    Comment
  • Sales of horticulture production from farmers supported by the AgrregatorsValue24.000.0028.80
    DateOctober 3, 2016November 3, 2016June 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Client days of training provided (number)Value0.003050.003020.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Farmers, Entrepreneurs and Association Members trained for grant application processValue0.003088.004588.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Number of extension staff trained on Extension (E) and Technical (T) ServicesValue0.00303.00400.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Increased number of farmers, entrepreneurs, and association members trained for grant applicationsValue0.002588.002500.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Number of farmers and enterprises that receive investment support under Measures 2Value0.00586.00520.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Number of farmers and enterprises that receive investment support under Measures 4Value0.0061.0032.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Increase in investments by farmers and enterprises in improved products and/or techniquesValue0 euro million15 million euros17.0 million euros
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Client days of training provided - Female (number)Value0.00280.00250.00
    DateJuly 26, 2011November 4, 2016July 31, 2017
    Comment
  • Client days of training providedValue0.001967.002861.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Livestock farmers adopting improved agricultural technologies under Measure 103Value0.0039.0067.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Increased number of Extension Staff trained in agricultural technical topicsValue0.00200.00410.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Number of Extension Staff receiving certificatesValue0.000.00120.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Livestock farmers adopting improved agricultural technologies under Measure 101Value0.00260.00348.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Farmers, Entrepreneurs and Association Members trained for grant application - of which womenValue0.00334.00688.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment15%
  • Increased number of Extension Staff trained in agricultural technical topics - of which womenValue0.0030.0062.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Extension staff receiving certificates - of which womenValue0.000.0018.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Increase in investmens by farmers and enterprises in improved products and/or techniquesValue0.00656.00772.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Grant financings appraised and approved for project aggreagatorsValue0.000.0015.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Fee collection rate towards scheme Management, Operation and MaintenanceValue55.000.0090.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    CommentBaseline is average for both schemes over past 5 years. Targets are collection rates of actual irrigators
  • Radoniqi dam safety plans prepared and adoptedValueNoNoYes
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment
  • Area provided with improved irrigation servicesValue0.000.006833.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    CommentArea in Radoniqi and Dukagjini irrigation schemes
  • Grant financings appraised and approved for project aggreagators - of which womenValue0.000.002.00
    DateJuly 26, 2011November 4, 2016June 30, 2021
    Comment10%
  • Grievances registered and responded to within agreed specified time periodValueNoNoYes
    DateApril 28, 2017April 28, 2017June 30, 2021
    Comment
  • Farmers adopting improved agricultural technologies for improved horticulture productionValue0.00318.001083.00
    DateOctober 3, 2016November 4, 2016June 30, 2021
    Comment
  • Beneficiary participation in the Working Groups for the preparation of RDGP MeasuresValueYesYesYes
    DateOctober 3, 2016November 4, 2016June 30, 2021
    Comment