Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 136.29 |
P158713
Closed
Xiaokai Li , James Tay
PEOPLE'S REPUBLIC OF CHINA
July 27, 2016
(as of board presentation)
June 6, 2018
October 23, 2018
US$ 386.29 million
Liaoning Urban Construction and Renewal Project Management Company Limited (LUCRPMC)
2018
US$ 250.00 million
B
Not Applicable
June 30, 2024
Yes
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Borrower/Recipient | 136.29 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 250.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 386.29 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2021 | IBRD-88370 | Int Charges | 15,470.85 |
Nov 1, 2021 | IBRD-88370 | Int Charges | 240,379.31 |
Oct 20, 2021 | IBRD-88370 | Loan Disb | 4,693,976.50 |
Nov 22, 2021 | IBRD-88370 | Loan Disb | 4,126,892.00 |
Mar 25, 2022 | IBRD-88370 | Loan Cancel | 99,299,968.00 |
Aug 14, 2020 | IBRD-88370 | Loan Disb | 5,000,000.00 |
Mar 15, 2021 | IBRD-88370 | Loan Disb | 4,066,768.50 |
Dec 18, 2020 | IBRD-88370 | Loan Disb | 4,601,321.00 |
Dec 18, 2020 | IBRD-88370 | Loan Disb | 3,839,030.20 |
Mar 16, 2021 | IBRD-88370 | Loan Disb | 9,396,738.00 |
Dec 21, 2020 | IBRD-88370 | Loan Disb | 3,076,896.20 |
Oct 16, 2019 | IBRD-88370 | Loan Disb | 8,000,000.00 |
Jul 19, 2019 | IBRD-88370 | Loan Disb | 2,000,000.00 |
May 1, 2020 | IBRD-88370 | Int Charges | 876.71 |
May 1, 2020 | IBRD-88370 | Int Charges | 11,603.29 |
May 1, 2020 | IBRD-88370 | Int Charges | 297,856.94 |
May 1, 2020 | IBRD-88370 | Int Charges | 150,939.94 |
Oct 15, 2020 | IBRD-88370 | Loan Disb | 10,000,000.00 |
Nov 1, 2020 | IBRD-88370 | Int Charges | 296,994.53 |
Nov 1, 2020 | IBRD-88370 | Int Charges | 110,319.45 |
Oct 23, 2018 | IBRD-88370 | Loan Disb | 625,000.00 |
Oct 23, 2018 | IBRD-88370 | Fee Charges | 625,000.00 |
May 1, 2019 | IBRD-88370 | Int Charges | 46,194.35 |
May 1, 2019 | IBRD-88370 | Int Charges | 532.81 |
May 1, 2019 | IBRD-88370 | Int Charges | 309,156.70 |
May 1, 2019 | IBRD-88370 | Int Charges | 11,595.33 |
Nov 1, 2019 | IBRD-88370 | Int Charges | 311,965.75 |
Nov 1, 2019 | IBRD-88370 | Int Charges | 31,687.51 |
Jun 18, 2024 | IBRD-88370 | Loan Disb | 11,124,952.00 |
Jun 6, 2018 | IBRD-88370 | Loan Commitment | 250,000,000.00 |
Nov 7, 2023 | IBRD-88370 | Loan Disb | 13,588,074.00 |
Nov 1, 2023 | IBRD-88370 | Int Charges | 54,749.24 |
Nov 1, 2023 | IBRD-88370 | Int Charges | 3,853,794.80 |
Nov 1, 2023 | IBRD-88370 | Int Charges | 296.25 |
Nov 1, 2023 | IBRD-88370 | Int Charges | 38,001.16 |
Jan 25, 2024 | IBRD-88370 | Loan Disb | 5,440,067.50 |
May 1, 2024 | IBRD-88370 | Int Charges | 23,156.24 |
May 1, 2024 | IBRD-88370 | Int Charges | 4,620,633.50 |
May 1, 2024 | IBRD-88370 | Int Charges | 17,566.03 |
Nov 1, 2022 | IBRD-88370 | Int Charges | 42,382.25 |
Nov 1, 2022 | IBRD-88370 | Int Charges | 1,582,462.80 |
Oct 31, 2022 | IBRD-88370 | Loan Disb | 5,567,643.00 |
Oct 31, 2022 | IBRD-88370 | Loan Disb | 9,306,835.00 |
Apr 26, 2023 | IBRD-88370 | Loan Disb | 8,650,589.00 |
May 1, 2023 | IBRD-88370 | Int Charges | 101.88 |
May 1, 2023 | IBRD-88370 | Int Charges | 84,232.11 |
May 1, 2023 | IBRD-88370 | Int Charges | 47,809.69 |
May 1, 2023 | IBRD-88370 | Int Charges | 2,965,468.20 |
May 1, 2022 | IBRD-88370 | Int Charges | 993.50 |
May 1, 2022 | IBRD-88370 | Int Charges | 3,599.80 |
May 1, 2022 | IBRD-88370 | Int Charges | 202,389.38 |
May 1, 2022 | IBRD-88370 | Int Charges | 488,480.25 |
Feb 15, 2022 | IBRD-88370 | Loan Disb | 6,535,375.00 |
Feb 15, 2022 | IBRD-88370 | Loan Disb | 10,192,395.00 |
May 1, 2021 | IBRD-88370 | Int Charges | 195,453.19 |
May 1, 2021 | IBRD-88370 | Int Charges | 1,161.21 |
May 1, 2021 | IBRD-88370 | Int Charges | 6,819.34 |
May 1, 2021 | IBRD-88370 | Int Charges | 263,133.03 |
Jul 12, 2021 | IBRD-88370 | Loan Disb | 8,027,873.00 |
Jul 9, 2021 | IBRD-88370 | Loan Disb | 4,773,789.50 |
Oct 21, 2021 | IBRD-88370 | Loan Disb | 8,065,818.00 |
Nov 1, 2021 | IBRD-88370 | Int Charges | 340,719.62 |
Nov 1, 2021 | IBRD-88370 | Int Charges | 4,269.77 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-06-24 |
Overall Implementation Progress (IP) | Satisfactory | 2024-06-24 |
Overall Safeguards Rating | Satisfactory | 2024-06-24 |
Progress towards achievement of PDO | Satisfactory | 2024-06-24 |
Monitoring and Evaluation | Satisfactory | 2024-06-24 |
Project Management | Satisfactory | 2024-06-24 |
Financial Management | Satisfactory | 2024-06-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-17-2024 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Energy consumption by the water utilities in each project city (kWh/m3) | Value | Weighted Average:0.888 kwh/m3Shenyang:0.87Anshan | Weighted Average:0.639 kwh/m3Shenyang:-Anshan:0. | |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 1349632.00 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Female beneficiaries | Value | 0.00 | 50.50 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Percentage of population in project cities receiving water supply from rehabilitated/upgraded water treatment plants under this project (Percentage) | Value | Anshan: 0Fushun: 0Gaizhou: 0 | Anshan: 0.0Fushun: 27.5Gaizhou: 0.0 | |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Non-Revenue-Water in each project city | Value | Shenyang:31.16%Anshan:35.35%Fushun:37.02%Fuxin: | Shenyang: -Anshan:24.2%Fushun:22.7%Fuxin: -Gai | |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Working Ratio | Value | Shenyang:0.85Anshan:1.02Fushun:0.95Fuxin:0.88G | Shenyang:-Anshan:0.83Fushun:0.91Fuxin:-Gaizhou | |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Length of new or rehabilitated main pipelines for water supply | Value | 0.00 | 75.50 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Number of water utility staff received training on asset management systems, water quality monitoring, and pipe leakage detection and repairing | Value | 0.00 | 445.00 | 0.00 |
Date | January 31, 2018 | August 1, 2022 | ||
Comment |
Customer satisfaction with the quality of water supply services | Value | 65.00 | 88.49 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Number of secondary booster pumps installed or rehabilitated | Value | 0.00 | 121.00 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Number of Female Staff received training on asset management systems, water quality monitoring, and pipe leakage | Value | 0.00 | 159.00 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Percentage of women satisfied with the quality of water supply services | Value | 65.00 | 88.49 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Number of district water meters installed | Value | 0.00 | 542.00 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Number of water meters installed | Value | 0.00 | 135026.00 | 0.00 |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Grievance settlement rate within the stipulated service standards for response time (%) | Value | Fushun: 85%Anshan: 78%Gaizhou: 80% | Fushun: 98%Anshan: 97%Gaizhou: 95% | |
Date | January 31, 2018 | August 1, 2023 | ||
Comment |
Water supply capacity of rehabilitated/upgraded water treatment plants under this project (million m3/day) | Value | 0.00 | 0.10 | 0.00 |
Date | February 28, 2018 | August 1, 2023 | ||
Comment |
Establishment of Smart Water System | Value | 0.00 | 0.00 | 0.00 |
Date | February 1, 2022 | August 1, 2022 | ||
Comment |
Number of self-tested water quality parameters of each WSC | Value | Fushun: 35Gaizhou: 9 | Fushun: 47Gaizhou: 15 | |
Date | June 30, 2018 | August 1, 2023 | ||
Comment |