Additional Financing Quito Metro Line One Project

Development Objective

The proposed Project development objective (PDO) is to improve urban mobility in the city of Quito serving the growing demand for public transport. The Project will reduce travel times, decrease operational costs of the transport service, improve connectivity, security and comfort of the current system and reduce emissions of pollutants and greenhouse gases.

Key Details

Project Details

  • P158756

  • Closed

  • Bianca Bianchi Alves , Alejandro Hoyos Guerrero

  • N/A

  • Ecuador

  • April 20, 2018

  • (as of board presentation)

    June 22, 2018

  • N/A

  • US$ 632.20 million

  • A

  • N/A

  • December 31, 2023

  • TBD

  • BANK APPROVED

  • P144489

  • November 1, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 230.00
Inter-American Development Bank 250.00
Development Bank of Latin America (CAF) 152.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 230.00
IDA Commitment N/A
IBRD + IDA Commitment 230.00
Lending Instrument
Grant Amount 402.20
Total Project Cost** 632.20

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Operating costs of Quito's vehicle fleet (amount [USD])Value0.000.00-59400000.00
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment
  • GHG emissions from transport in MDMQ (tons/year)Value0.000.00-58170.00
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment
  • Adequate passenger capacity is provided by PLMQ (Yes/No)ValueNoNoYes
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment
  • Percentage of users satisfied with overall Metro service, its security and comfort, differentiated by gender and income (percentange)Value0.000.0065.00
    DateDecember 31, 2013June 30, 2017December 31, 2018
    Comment
  • Percentage of female users satisfied with overall Metro service, its security and comfort (percentage)Value0.000.0065.00
    DateDecember 31, 2013June 30, 2017December 31, 2018
    Comment
  • Percentage of low-income users satisfied with overall Metro service, its security and comfort (percentage)Value0.000.0065.00
    DateDecember 31, 2013June 30, 2017December 31, 2018
    Comment
  • Percentage of jobs accessible in 60 minutes of travel time (percentage)Value45.3045.3050.80
    DateDecember 31, 2013December 29, 2017December 31, 2021
    Comment
  • Passengers per day in the PLMQValue0.000.00295999.00
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment
  • Travel time for public transportation users (minutes)Value38.5038.5023.10
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of physical work progress in stations and universal accessValue0.0045.87100.00
    DateMay 31, 2013July 20, 2017December 31, 2021
    Comment
  • % of physical work progress in rail yardValue0.0034.18100.00
    DateDecember 31, 2013July 20, 2017December 31, 2021
    Comment
  • % of progress in installation of power supply, auxiliary, signaling and telecom systemsValue0.0038.47100.00
    DateDecember 31, 2013July 20, 2017December 31, 2021
    Comment
  • % of rolling stock completedValue0.0011.12100.00
    DateDecember 31, 2013September 29, 2017December 31, 2021
    Comment
  • % of fare collection system installedValue0.000.00100.00
    DateDecember 31, 2013June 30, 2017December 31, 2021
    Comment
  • % of Metro feeder routes in operationValue0.000.0090.00
    DateDecember 31, 2013June 30, 2018December 31, 2021
    Comment
  • % of MDMQ bus fleet under unified fare-collection systemValue0.000.0090.00
    DateDecember 31, 2013June 30, 2018December 31, 2021
    Comment
  • % of progress in installation of permanent wayValue0.000.00100.00
    DateJanuary 30, 2018January 30, 2018December 31, 2021
    Comment
  • Implementation of a reporting mechanism for cases of violence against women and girls in the PMLQValueNoNoYes
    DateDecember 31, 2021
    Comment
  • Percentage of technical and professional staff, directly employed by the operator of the PLMQ, that is female.Value0.000.0020.00
    DateDecember 31, 2013February 5, 2018December 31, 2021
    Comment
  • % of physical work progress in civil works other than stationsValue0.0019.84100.00
    DateDecember 31, 2013July 20, 2017December 31, 2021
    Comment