Skip to Main Navigation

Capacity Building Project for Extractive Industries Management Frameworks

Development Objective

The Project Development Objective is to improve capacity to develop legal, regulatory, and institutional frameworks for an effective and transparent management of extractive industries.

Key Details

Project Details

  • P158889

  • Closed

  • Remi Pelon

  • Republic of Madagascar

  • Madagascar

  • March 18, 2016

  • (as of board presentation)

    February 28, 2017

  • April 6, 2017

  • US$ 1.40 million

  • C

  • Not Applicable

  • June 29, 2019

  • BANK APPROVED

  • October 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Africa Extractive Industries Trust Fund 1.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 1.40
Total Project Cost** 1.40

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2017-09-06
Overall Implementation Progress (IP) Moderately Unsatisfactory 2017-09-06
Overall Moderable 2017-09-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Transparent and effective licensing procedures submitted for adoption to relevant Ministries (mining and oil)ValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Regulations and related documents for improved enforcement submitted for adoption (mining)ValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Action Plan on State Participation (mining) and Statutes of the National Oil Company (oil)ValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Share of participants to Project-financed events reporting they had adequate capacity to provide inputValue0.000.0080.00
    DateFebruary 27, 2017December 27, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Adminsitrative procedures for processing mining titles updatedValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Number of oil license bidding rounds organizedValue0.000.001.00
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Study on management of state participation in mining venturesValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Statutes of the National Oil CompanyValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Assessment of Environmental and Social frameworks completedValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Number of EITI events supportedValue0.000.005.00
    DateJanuary 16, 2017December 27, 2019
    Comment
  • Review of ASM formalisation effortsValueNoNoYes
    DateJanuary 16, 2017December 27, 2019
    Comment