Financier | Commitments |
---|---|
Trust Funds | 0.67 |
P158899
Closed
Wilfried Hundertmark , Kazuhiro Yoshida
Republic of Armenia
April 24, 2016
(as of board presentation)
July 26, 2016
N/A
US$ 0.67 million
Water Sector Projects Implementation Unit State Agency
2017
US$ 0.67 million
N/A
October 12, 2023
N/A
BANK APPROVED
Financier | Commitments |
---|---|
Trust Funds | 0.67 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.67 |
Total Project Cost** | 0.67 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The Government of the Republic of Armenia meets readiness criteria for appraisal and negotiation of the Mastara Reservoir Construction Project | Value | The components of the project are not developed, n | The project documents are prepared according to WB | |
Date | June 17, 2016 | December 31, 2017 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Feasibility Study of the reservoir completed, preliminary design and project documents are available | Value | No | Yes | |
Date | June 17, 2016 | December 31, 2017 | ||
Comment |
6 staff of the PIU trained in the areas of procurement, monitoring and evaluation, environmental and social safeguards | Value | 0.00 | 0.00 | 6.00 |
Date | June 17, 2016 | December 31, 2017 | ||
Comment |
Financial audit of the Grant activities carried out | Value | No | Yes | |
Date | June 17, 2016 | December 31, 2017 | ||
Comment |