Northern Delta Transport Development Project Additional Financing

Development Objective

The Project's development objective is to enhance the efficiency, environmental sustainability and safety of transport infrastructure and services, through the alleviation of physical and institutional bottlenecks in two major waterway corridors in the Northern Delta Region.

Key Details

Project Details

  • P158976

  • Closed

  • Luis Blancas Mendivil

  • Ministry of Transport

  • Viet Nam

  • November 3, 2016

  • (as of board presentation)

    May 5, 2017

  • N/A

  • US$ 82.30 million

  • Project Management Unit for Waterways (PMU-W)

  • East Asia and Pacific

  • 2017

  • US$ 78.74 million

  • A

  • July 15, 2021

  • June 30, 2023

  • No

  • BANK APPROVED

  • P095129

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 28.45
IDA Credit 78.74

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 78.74
IBRD + IDA Commitment 78.74
Lending Instrument
Grant Amount N/A
Total Project Cost** 82.30

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Travel time of 4x400-DWT barges from Quang Ninh to Viet Tri during the dry seasonValue47 hrs/280 km31 hrs/276.5 kms42.3 hrs (10% reduction)/276 km (4 km reduction)
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Vessel travel time from Quang Ninh to Ninh Phuc portValue60.000.0048.00
    DateSeptember 15, 2016June 30, 2020
    CommentThe baseline value (60 hours) refers to the current routing along Corridor 2 by self-propelled 200-600 DWT barges and 800-1,200 DWTpush convoys. The project will enable a new coastal routing through the Lach Giang estuary bypass access channel and the DNC canal,for sea-river vessels 2,000 DWT in capacity.Target represents a 20% reduction from baseline.
  • Travel time of 4x400-DWT barges from Hanoi to Lach Giang estuary during the dry seasonValue43 hrs/259 km37.5 hrs/257.8 km40.85 (5% reduction)/257.5 km (1.5 km reduction)
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Average vessel waiting time to enter/exit river system at Lach Giang estuary during the dry seasonValue20.001.0010.00
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Traffic accidents/fatalities related to river crossings at the pilot ferry boat stagesValue706 (20% reduction)
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Waiting time for vessels calling at the Viet Tri PortValue24.0017.3019.20
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Total Suspended Solids (TSS) in effluent from coal storage area in Ninh Phuc PortValue50 mg/l44 mg/l45 mg/l
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Total Suspended Solids (TSS) in effluent from coal storage area in Viet Tri PortValue50 mg/l42 mg/l45 mg/l
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Emissions of PM10 at Viet Tri PortValue150 mg/m378 mg/m3135 mg/m3
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment
  • Emissions of PM10 at Ninh Phuc PortValue128 mg/m346 mg/m3103 mg/m3
    DateNovember 30, 2011December 14, 2016December 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of waterways improved to desired operating standardsValue0.00539.00539.00
    DateJune 24, 2008December 14, 2016December 31, 2016
    Comment
  • Ferry Boat stages with improved safety designValuenone3128
    DateJune 24, 2008December 14, 2016December 31, 2016
    Comment
  • Timely completion of physical worksValue0.00100.00100.00
    DateJune 24, 2008December 14, 2016December 31, 2016
    CommentRefers to civil works financed by the original credit.
  • Delivery to MoT/VIWA of draft framework for the planning and sustainable management of inland waterwaysValueNoYesYes
    DateJune 24, 2008December 14, 2016December 31, 2016
    Comment
  • Delivery to MoT/VIWA of draft framework for the planning and sustainable management of ferry boat stagesValueNoYesYes
    DateJune 24, 2008December 14, 2016December 31, 2016
    Comment
  • Percentage of DNC canal civil works completedValue0.000.00100.00
    DateSeptember 15, 2016December 31, 2019
    Comment