Financier | Commitments |
---|---|
Borrower/Recipient | 28.45 |
IDA Credit | 78.74 |
P158976
Closed
Luis Blancas Mendivil
Ministry of Transport
November 3, 2016
(as of board presentation)
May 5, 2017
N/A
US$ 82.30 million
Project Management Unit for Waterways (PMU-W)
2017
US$ 78.74 million
A
July 15, 2021
June 30, 2023
No
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 28.45 |
IDA Credit | 78.74 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 78.74 |
IBRD + IDA Commitment | 78.74 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 82.30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Travel time of 4x400-DWT barges from Quang Ninh to Viet Tri during the dry season | Value | 47 hrs/280 km | 31 hrs/276.5 kms | 42.3 hrs (10% reduction)/276 km (4 km reduction) |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Vessel travel time from Quang Ninh to Ninh Phuc port | Value | 60.00 | 0.00 | 48.00 |
Date | September 15, 2016 | June 30, 2020 | ||
Comment | The baseline value (60 hours) refers to the current routing along Corridor 2 by self-propelled 200-600 DWT barges and 800-1,200 DWTpush convoys. The project will enable a new coastal routing through the Lach Giang estuary bypass access channel and the DNC canal,for sea-river vessels 2,000 DWT in capacity. | Target represents a 20% reduction from baseline. |
Travel time of 4x400-DWT barges from Hanoi to Lach Giang estuary during the dry season | Value | 43 hrs/259 km | 37.5 hrs/257.8 km | 40.85 (5% reduction)/257.5 km (1.5 km reduction) |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Average vessel waiting time to enter/exit river system at Lach Giang estuary during the dry season | Value | 20.00 | 1.00 | 10.00 |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Traffic accidents/fatalities related to river crossings at the pilot ferry boat stages | Value | 7 | 0 | 6 (20% reduction) |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Waiting time for vessels calling at the Viet Tri Port | Value | 24.00 | 17.30 | 19.20 |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Total Suspended Solids (TSS) in effluent from coal storage area in Ninh Phuc Port | Value | 50 mg/l | 44 mg/l | 45 mg/l |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Total Suspended Solids (TSS) in effluent from coal storage area in Viet Tri Port | Value | 50 mg/l | 42 mg/l | 45 mg/l |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Emissions of PM10 at Viet Tri Port | Value | 150 mg/m3 | 78 mg/m3 | 135 mg/m3 |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
Emissions of PM10 at Ninh Phuc Port | Value | 128 mg/m3 | 46 mg/m3 | 103 mg/m3 |
Date | November 30, 2011 | December 14, 2016 | December 31, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of waterways improved to desired operating standards | Value | 0.00 | 539.00 | 539.00 |
Date | June 24, 2008 | December 14, 2016 | December 31, 2016 | |
Comment |
Ferry Boat stages with improved safety design | Value | none | 31 | 28 |
Date | June 24, 2008 | December 14, 2016 | December 31, 2016 | |
Comment |
Timely completion of physical works | Value | 0.00 | 100.00 | 100.00 |
Date | June 24, 2008 | December 14, 2016 | December 31, 2016 | |
Comment | Refers to civil works financed by the original credit. |
Delivery to MoT/VIWA of draft framework for the planning and sustainable management of inland waterways | Value | No | Yes | Yes |
Date | June 24, 2008 | December 14, 2016 | December 31, 2016 | |
Comment |
Delivery to MoT/VIWA of draft framework for the planning and sustainable management of ferry boat stages | Value | No | Yes | Yes |
Date | June 24, 2008 | December 14, 2016 | December 31, 2016 | |
Comment |
Percentage of DNC canal civil works completed | Value | 0.00 | 0.00 | 100.00 |
Date | September 15, 2016 | December 31, 2019 | ||
Comment |