Financier | Commitments |
---|---|
Borrower/Recipient | 13.60 |
IDA Credit | 72.52 |
P159049
Closed
Cuong Dang , Jung Oh
N/A
September 16, 2016
(as of board presentation)
May 26, 2017
N/A
US$ 106.50 million
N/A
2017
US$ 72.52 million
B
August 15, 2024
June 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 13.60 |
IDA Credit | 72.52 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 72.52 |
IBRD + IDA Commitment | 72.52 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 106.50 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average weekday number of people using public transport service in Da Nang (including inter-provincial routes) | Value | 22000.00 | 31388.00 | 132000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Area benefiting from the increased drainage coverage and flood protection measure | Value | 0.00 | 0.00 | 500.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Travel time (in minutes) from highway 14B to costal road (by car, on week days during peak hours). | Value | 25.00 | 33.00 | 14.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Travel time (in minutes) from High Tech Park to City Center (by car, in week day at peak hour) | Value | 30.00 | 36.00 | 15.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Average weekday number of people (women) using public transport service in Da Nang (including inter-provincial routes) | Value | 12000.00 | 17029.00 | 70000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Average weekday number of people (men) using public transport service in Da Nang (including inter-provincial routes) | Value | 10000.00 | 14359.00 | 62000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Travel time (in minutes) from highway 14B to DT602 (by car, on week days during peak hours) | Value | 0.00 | 22.00 | 14.00 |
Date | December 31, 2015 | December 31, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to Improved Sanitation under the project | Value | 0.00 | 80827.00 | 500000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Volume(mass) of BOD pollution load removed by treatment plant under the project | Value | 0.00 | 320.00 | 4000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of high quality buses procured and in BRT service | Value | 0.00 | 0.00 | 66.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Roads constructed, non-rural | Value | 0.00 | 7.30 | 27.30 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of people (men) provided with access to improved sanitation service under the project | Value | 0.00 | 39148.00 | 245000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Number of people (women) provided with access to improved sanitation service under the project | Value | 0.00 | 41679.00 | 255000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Length of drains constructed/upgraded under the project | Value | 0.00 | 25000.00 | 60000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
Volume of wastewater treated by WWTPs supported under the project. | Value | 0.00 | 12000000.00 | 20000000.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |
No. of household provided with connection to separate sewers system | Value | 0.00 | 0.00 | 10000.00 |
Date | December 31, 2015 | December 31, 2018 | ||
Comment |
Share of citizens (from women/vulnerable/ marginalized groups) who participated in consultations (%) | Value | 0.00 | 70.00 | 70.00 |
Date | January 1, 2013 | December 31, 2015 | December 31, 2018 | |
Comment |