Uganda Rural Electrification

Development Objective

The Project Development Objective is to increase access to electricity in rural areas of Uganda.

Key Details

Project Details

  • P159112

  • Active

  • Joseph Kapika

  • Republic of Uganda

  • Uganda

  • December 30, 2016

  • (as of board presentation)

    December 30, 2016

  • December 30, 2016

  • US$ 13.70 million

  • Ministry of Energy and Mineral Development (MEMD)

  • Eastern and Southern Africa

  • 2017

  • US$ 13.70 million

  • B

  • December 6, 2023

  • October 31, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Carbon Initiative for Development 13.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 13.70
Total Project Cost** 13.70

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-02-04
Financial Management Satisfactory 2025-02-04
Monitoring and Evaluation Satisfactory 2025-02-04
Overall Implementation Progress (IP) Satisfactory 2025-02-04
Procurement Satisfactory 2025-02-04
Project Management Satisfactory 2025-02-04

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.008789674.007600000.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Female beneficiariesValue50.0050.0050.00
    DateJanuary 1, 2015May 11, 2018December 31, 2020
    Comment
  • People provided with access to electricity by household connectionsValue0.00940678.00878333.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • People provided with access to electricity by hhold connections-GridValue0.00923791.00850000.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Ppl provided wth elec. by hhold conn.–Offgrid/minigrid–Only renewable sourcesValue0.0016887.0028333.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • CO2 emissions reduced/avoided as a result of the projectValue0.00127205.00120000.00
    DateMay 14, 2015December 7, 2023June 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total length of distribution lines constructed under the projectValue0.00268.001543.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Number of rural health centers with solar PV systems installedValue0.00329.00276.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Completion of the baseline survey report for ERT-3ValueNoYesYes
    DateFebruary 12, 2019December 7, 2023June 30, 2023
    Comment
  • Number of on-grid household connections made under the projectValue0.00163022.00150000.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Total installed capacity of solar PV systems installed at rural health centersValue0 kWp250 kWp250 kWp
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Increase in certified wiremen for household connectionsValue0.002751.001850.00
    DateFebruary 12, 2019December 7, 2023June 30, 2023
    Comment
  • Number of rural schools with solar PV systems installedValue0.0075.0089.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Total installed capacity of solar PV systems installed at rural schoolsValue0 kWp98 kWp114 kWp
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Total installed capacity of solar PV systems installed at rural water pumping stationsValue0 kWp458 kWp452 kWp
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Number of off-grid solar system connections made to households and enterprises under the projectValue0.003633.005000.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • National standards for Solar Home Systems adopted by UNBSValueNoYesYes
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • National standards for Pico PV Systems adopted by UNBSValueNoYesYes
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Number of rural water pumping stations with solar PV systems installed (number)Value0.0027.0026.00
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Amount of credit and guarantee extended to Participating Financial Institutions (cumulative)Value0 US$ million3.7 US$ million3.8 US$ million
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment
  • Amount of credit and guarantee extended to project beneficiaries by Participating Financial Institutions (cumulative US$ million equivalent)Value0US$ million0.8 US$ million1.3 US$ million
    DateJanuary 1, 2015December 7, 2023June 30, 2023
    Comment