Financier | Commitments |
---|---|
Trust Fund for Statistical Capacity Building | 1.50 |
P159189
Closed
Aboudrahyme Savadogo , Aly Sanoh
Ministry of Planning, Economy and International Cooperation
March 29, 2016
(as of board presentation)
October 5, 2016
February 15, 2017
US$ 1.50 million
INSEED
2017
US$ 1.50 million
C
Not Applicable
June 30, 2019
BANK APPROVED
November 30, 2020
Financier | Commitments |
---|---|
Trust Fund for Statistical Capacity Building | 1.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.50 |
Total Project Cost** | 1.50 |
Name | Review | Date |
---|---|---|
Overall | Moderable | 2018-02-23 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2018-02-23 |
Progress towards achievement of PDO | Satisfactory | 2018-02-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-09-2020 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Survey preparation is completed according to international standards with regards to quality and timeliness. | Value | No | Yes | Yes |
Date | July 1, 2016 | December 1, 2017 | June 30, 2019 | |
Comment |
Relevant socioeconomic statistics and anonymized microdata are released within 12 months of the completion of fieldwork. | Value | No | Yes | No |
Date | July 1, 2016 | March 1, 2018 | November 1, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Finalization and testing of Computer Assisted Personal Interviewing (CAPI) data entry system | Value | No | Yes | Yes |
Date | July 1, 2016 | March 1, 2017 | June 28, 2019 | |
Comment |
Generation of key consumption statistics | Value | No | Yes | Yes |
Date | July 1, 2016 | November 30, 2017 | July 1, 2019 | |
Comment |
Number of regional workshops hosted by WAEMU with participation of INSEED staff | Value | 2.00 | 6.00 | 6.00 |
Date | July 1, 2016 | December 1, 2017 | December 2, 2019 | |
Comment |
Non-standard unit survey conducted | Value | No | Yes | Yes |
Date | July 1, 2016 | March 1, 2017 | June 28, 2019 | |
Comment |
Survey enumerator training completed | Value | No | Yes | Yes |
Date | July 1, 2016 | December 1, 2016 | May 22, 2019 | |
Comment |
Statistical abstract is published within 12 months of completion of field work and contains gender disaggregated analysis where relevant | Value | No | Yes | No |
Date | July 1, 2016 | March 1, 2018 | August 20, 2019 | |
Comment |