Skip to Main Navigation

TV: Telecommunications and ICT Development Project

Abstract*

The development objective of Tuvalu Telecommunications and Information and communication technologies (ICT) Development project is to facilitate improved access to, and reduced cost of, internet services in Tuvalu. This project has three components. 1) The first component, Technical Assistance, aims to develop and implement ICT policy, new or amended legislation and reforms for the ICT sector, including strategies for Outer Islands and international...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to facilitate improved access to, and reduced cost of, internet services in Tuvalu.

Key Details

Project Details

  • P159395

  • Active

  • James Neumann

  • Tuvalu

  • Tuvalu

  • July 19, 2017

  • (as of board presentation)

    January 15, 2019

  • April 11, 2019

  • US$ 29.00 million

  • Ministry of Justice, Communications and Foreign Affairs,Tuvalu Telecommunication Corporation

  • East Asia and Pacific

  • 2019

  • US$ 29.00 million

  • B

  • February 25, 2024

  • December 1, 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 29.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 29.00
IBRD + IDA Commitment 29.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 29.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 6, 2024 IDA-D4030 Loan Disb 51,835.17
Apr 11, 2019 IDA-D4030 Loan Disb 409,425.00
Feb 17, 2021 IDA-D4030 Loan Disb 158,719.84
Jun 30, 2020 IDA-D4030 Loan Disb 14,682.96
Jun 30, 2020 IDA-D4030 Loan Disb 34,369.99
Jul 20, 2022 IDA-D4030 Loan Disb 48,024.92
Jun 28, 2024 IDA-D4030 Loan Disb -123,383.23
May 9, 2024 IDA-D4030 Loan Disb 297,805.60
May 16, 2024 IDA-D4030 Loan Disb 223,932.60
Jun 26, 2024 IDA-D4030 Loan Disb 126,381.34
Jun 26, 2024 IDA-D4030 Loan Disb 123,226.49
Feb 1, 2024 IDA-D4030 Loan Disb 90,264.97
Jul 25, 2024 IDA-D4030 Loan Disb 200,614.02
Aug 9, 2024 IDA-D4030 Loan Disb 74,451.40
Jan 2, 2024 IDA-D4030 Loan Disb 84,205.76
Nov 21, 2023 IDA-D4030 Loan Disb 88,713.73
Aug 13, 2024 IDA-D4030 Loan Disb 32,971.12
Oct 13, 2023 IDA-D4030 Loan Disb 168,411.52
Nov 8, 2023 IDA-D4030 Loan Disb 84,205.76
Aug 6, 2024 IDA-D4030 Loan Disb 163,284.30
Jun 24, 2024 IDA-D4030 Loan Disb -82,493.45
Jun 21, 2024 IDA-D4030 Loan Disb 82,044.31
Nov 7, 2019 IDA-D4030 Loan Disb 69,205.00
Jan 15, 2019 IDA-D4030 Loan Commitment 29,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-12-19
Procurement Moderately Satisfactory 2024-12-19
Financial Management Moderately Satisfactory 2024-12-19
Monitoring and Evaluation Moderately Satisfactory 2024-12-19
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-19
Project Management Moderately Satisfactory 2024-12-19

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with new or enhanced access to broadband internetValue2800.004500.006500.00
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Price of fixed internet service (US$/GB)Value26.006.333.50
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Persons identifying improved internet servicesValue0.000.003000.00
    DateAugust 17, 2018October 31, 2023June 30, 2024
    Comment
  • Price of mobile internet services (GB)Value14.006.333.50
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Persons reporting internet use once per weekValue0.004500.005000.00
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • People provided with new or enhanced access to broadband internet – FemaleValue1400.000.000.00
    Date
    Comment
  • of which femaleValue0.000.001500.00
    DateAugust 17, 2018October 31, 2023June 30, 2024
    Comment
  • of which femaleValue0.000.002500.00
    DateJune 1, 2023October 31, 2023December 1, 2025
    Comment
  • Broadband available on 8 inhabited Outer IslandsValueNoNoYes
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • ICT Policy formulated and adoptedValueNoYesYes
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Availability of fiber services in the deployment area (homes passed)Value0.000.0080.00
    DateJune 1, 2023October 31, 2023December 1, 2025
    Comment
  • Grievances responded and/or resolved within the stipulated service standardsValue0.00100.0075.00
    DateJune 1, 2023October 31, 2023December 1, 2025
    Comment
  • ICT regulatory framework developed and adopedValueNoNoYes
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Premises with a fiber connectionValue0.000.0020.00
    DateJune 1, 2023October 31, 2023December 1, 2025
    Comment
  • Demand-side analysis completedValueNoYesYes
    DateAugust 17, 2018October 31, 2023December 1, 2025
    Comment
  • In-service international bandwidth (Mbps)Value50.00850.001750.00
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • Number of people reached through digital literacy and skills programs (disaggregated by gender)Value0.000.00250.00
    DateJune 1, 2023October 31, 2023December 1, 2025
    Comment
  • Price of wholesale international internet bandwidthValue750.00280.00250.00
    DateOctober 1, 2018October 31, 2023December 1, 2025
    Comment
  • of which femaleValue0.000.00125.00
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment
  • Submarine cable contract negotiations completedValueNoNoYes
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment
  • Regulatory contract implemented between Govt and TTCValueNoNoYes
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment
  • Digital Tuvalu Office establishedValueNoNoYes
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment
  • Corporate governance and oversight of TTC improvedValueNoNoYes
    DateOctober 31, 2023October 31, 2023December 1, 2025
    Comment