Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 143.46 |
P159870
Closed
Qi Tian
People's Republic of China
October 25, 2016
(as of board presentation)
June 6, 2018
November 26, 2018
US$ 293.46 million
Zhejiang Provincial Construction Department
2018
US$ 150.00 million
B
March 20, 2024
December 31, 2024
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 143.46 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 293.46 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 1, 2021 | IBRD-88560 | Int Charges | 794.25 |
Jul 30, 2021 | IBRD-88560 | Loan Disb | 3,954,323.00 |
Apr 14, 2021 | IBRD-88560 | Loan Disb | 1,893,598.90 |
Jan 8, 2021 | IBRD-88560 | Loan Disb | 2,744,389.20 |
Dec 21, 2020 | IBRD-88560 | Loan Disb | 4,443,349.50 |
Jan 26, 2021 | IBRD-88560 | Loan Disb | 3,438,274.50 |
Sep 4, 2020 | IBRD-88560 | Loan Disb | 1,447,923.60 |
Nov 1, 2020 | IBRD-88560 | Int Charges | 8.92 |
Oct 15, 2020 | IBRD-88560 | Loan Disb | 1,899,960.60 |
May 1, 2022 | IBRD-88560 | Int Charges | 4,099.46 |
May 1, 2022 | IBRD-88560 | Int Charges | 116,592.62 |
May 1, 2022 | IBRD-88560 | Int Charges | 310,731.60 |
May 1, 2022 | IBRD-88560 | Int Charges | 1,131.41 |
Oct 14, 2021 | IBRD-88560 | Loan Disb | 3,068,009.20 |
Sep 24, 2021 | IBRD-88560 | Loan Disb | 2,893,716.80 |
Nov 1, 2021 | IBRD-88560 | Int Charges | 220.49 |
Nov 1, 2021 | IBRD-88560 | Int Charges | 798.90 |
Nov 1, 2021 | IBRD-88560 | Int Charges | 139,133.53 |
Nov 1, 2021 | IBRD-88560 | Int Charges | 225,508.40 |
Jan 9, 2019 | IBRD-88560 | Loan Disb | 15,000,000.00 |
Nov 1, 2019 | IBRD-88560 | Int Charges | 169,649.31 |
Nov 1, 2019 | IBRD-88560 | Int Charges | 276,042.10 |
Jun 6, 2018 | IBRD-88560 | Loan Commitment | 150,000,000.00 |
Jan 19, 2024 | IBRD-88560 | Loan Disb | 2,952,051.00 |
May 1, 2024 | IBRD-88560 | Int Charges | 34,194.69 |
May 1, 2024 | IBRD-88560 | Int Charges | 48,925.19 |
May 1, 2024 | IBRD-88560 | Int Charges | 3,743,849.20 |
May 1, 2024 | IBRD-88560 | Int Charges | 726.82 |
Mar 21, 2023 | IBRD-88560 | Loan Disb | 6,931,247.00 |
Jun 5, 2024 | IBRD-88560 | Loan Disb | 1,569,398.80 |
Oct 16, 2023 | IBRD-88560 | Loan Disb | 6,632,172.00 |
Nov 1, 2023 | IBRD-88560 | Int Charges | 1,946.45 |
Nov 1, 2023 | IBRD-88560 | Int Charges | 75,522.76 |
Nov 1, 2023 | IBRD-88560 | Int Charges | 81,235.91 |
Nov 1, 2023 | IBRD-88560 | Int Charges | 2,717,825.00 |
Nov 3, 2023 | IBRD-88560 | Loan Disb | 6,781,130.50 |
Dec 14, 2023 | IBRD-88560 | Loan Disb | 6,962,152.50 |
Jul 19, 2023 | IBRD-88560 | Loan Disb | 6,716,092.00 |
Feb 8, 2024 | IBRD-88560 | Loan Disb | 5,511,013.50 |
May 1, 2021 | IBRD-88560 | Int Charges | 147,671.16 |
May 1, 2021 | IBRD-88560 | Int Charges | 175,332.97 |
Jan 10, 2022 | IBRD-88560 | Loan Disb | 4,720,857.50 |
Feb 15, 2022 | IBRD-88560 | Loan Disb | 5,201,350.50 |
Apr 8, 2022 | IBRD-88560 | Loan Disb | 6,072,957.50 |
Dec 16, 2021 | IBRD-88560 | Loan Disb | 4,700,846.50 |
May 1, 2023 | IBRD-88560 | Int Charges | 95,860.92 |
May 1, 2023 | IBRD-88560 | Int Charges | 92,024.09 |
May 1, 2023 | IBRD-88560 | Int Charges | 1,966,457.60 |
May 1, 2023 | IBRD-88560 | Int Charges | 2,317.71 |
Sep 13, 2022 | IBRD-88560 | Loan Disb | 6,905,834.50 |
Nov 1, 2022 | IBRD-88560 | Int Charges | 956.70 |
Nov 1, 2022 | IBRD-88560 | Int Charges | 3,388.83 |
Nov 1, 2022 | IBRD-88560 | Int Charges | 101,913.59 |
Nov 1, 2022 | IBRD-88560 | Int Charges | 1,097,602.10 |
Aug 19, 2019 | IBRD-88560 | Loan Disb | 29,738.73 |
May 1, 2019 | IBRD-88560 | Int Charges | 197,681.52 |
May 1, 2019 | IBRD-88560 | Int Charges | 178,196.25 |
Nov 26, 2018 | IBRD-88560 | Loan Disb | 375,000.00 |
Nov 26, 2018 | IBRD-88560 | Fee Charges | 375,000.00 |
Nov 1, 2020 | IBRD-88560 | Int Charges | 166,312.12 |
Nov 1, 2020 | IBRD-88560 | Int Charges | 147,200.38 |
Nov 1, 2020 | IBRD-88560 | Int Charges | 0.86 |
Nov 18, 2020 | IBRD-88560 | Loan Disb | 3,265,552.00 |
Jun 17, 2020 | IBRD-88560 | Loan Disb | 1,989,399.50 |
May 1, 2020 | IBRD-88560 | Int Charges | 167,454.44 |
May 1, 2020 | IBRD-88560 | Int Charges | 219,105.03 |
Apr 30, 2020 | IBRD-88560 | Loan Disb | 125,334.93 |
Jan 10, 2020 | IBRD-88560 | Loan Disb | 30,151.94 |
May 1, 2021 | IBRD-88560 | Int Charges | 4,664.39 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Highly Satisfactory | 2024-12-16 |
Procurement | Satisfactory | 2024-12-16 |
Financial Management | Moderately Satisfactory | 2024-12-16 |
Monitoring and Evaluation | Satisfactory | 2024-12-16 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-16 |
Project Management | Satisfactory | 2024-12-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Nitrogen load reduction achieved under the project | Value | 0.00 | 23.90 | 25.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
People provided with access to improved water sources | Value | 0.00 | 203172.00 | 279044.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Phosphorus load reduction achieved under the project | Value | 0.00 | 28.90 | 30.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Decrease of soil erosion | Value | 0.00 | 20.20 | 20.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in pesticide consumption in project areas | Value | 0.00 | 88.70 | 92.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Length of river bank rehabilitated | Value | 0.00 | 208.62 | 204.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Number of research and study programs (by topic) conducted | Value | 0.00 | 5.00 | 8.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Reduction of phosphorus consumption in project areas | Value | 0.00 | 1294.00 | 1380.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Number of overflow weir dams upgraded and rehabilitated | Value | 15.00 | 86.00 | 85.00 |
Date | June 30, 2019 | October 31, 2023 | June 30, 2024 | |
Comment |
Number of workshops organized | Value | 0.00 | 5.00 | 5.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Reduction of nitrogen consumption in project areas | Value | 0.00 | 3152.50 | 3080.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Increase in delivery capacity of safe water supply | Value | 0.00 | 53334.00 | 127400.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Project staff and beneficiaries trained (person days) | Value | 0.00 | 21409.00 | 19300.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Areas of degraded monoculture plantations converted to mixed stands with multiple species | Value | 0.00 | 10035.00 | 11140.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
New piped household water connections under the project | Value | 0.00 | 58049.00 | 92667.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Number of beneficiaries trained --Female (person days) | Value | 0.00 | 7230.00 | 5790.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Areas of denuded forests fully planted with multiple tree and shrub species | Value | 0.00 | 2403.00 | 2260.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Number of project management staff trained (person days) | Value | 0.00 | 0.00 | 2100.00 |
Date | July 1, 2018 | June 30, 2024 | ||
Comment |
Number of tree species introduced by the project to diversify forest ecosystems | Value | 9.00 | 58.00 | 40.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Project monitoring system established and put into operation | Value | No | Yes | Yes |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |
Decrease of pest incidence in project areas | Value | 30.00 | 5.43 | 10.00 |
Date | July 1, 2018 | October 31, 2023 | June 30, 2024 | |
Comment |