Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 310.00 |
Borrower/Recipient | 7.00 |
P160005
Active
Elad Shenfeld , Udage Arachchige Dissanayake
Democratic Socialist Republic of Sri Lanka
November 8, 2018
(as of board presentation)
June 25, 2019
October 12, 2021
US$ 92.00 million
Ministry of Irrigation
2019
US$ 310.00 million
A
April 2, 2024
December 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 310.00 |
Borrower/Recipient | 7.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 310.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 310.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 92.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 17, 2021 | IBRD-89960 | Loan Cancel | 218,000,000.00 |
Jun 25, 2019 | IBRD-89960 | Loan Commitment | 310,000,000.00 |
Mar 15, 2022 | IBRD-89960 | Int Charges | 74,798.83 |
Mar 15, 2022 | IBRD-89960 | Int Charges | 1,160.99 |
Oct 12, 2021 | IBRD-89960 | Loan Disb | 230,000.00 |
Oct 12, 2021 | IBRD-89960 | Fee Charges | 230,000.00 |
Mar 15, 2023 | IBRD-89960 | Int Charges | 923.64 |
Mar 15, 2023 | IBRD-89960 | Int Charges | 113,050.61 |
Mar 15, 2023 | IBRD-89960 | Int Charges | 21,657.97 |
Sep 15, 2022 | IBRD-89960 | Int Charges | 114,983.97 |
Sep 15, 2022 | IBRD-89960 | Int Charges | 8,504.44 |
Oct 19, 2023 | IBRD-89960 | Loan Disb | 1,060,988.00 |
May 25, 2023 | IBRD-89960 | Loan Disb | 2,791,276.50 |
Sep 15, 2023 | IBRD-89960 | Int Charges | 309.37 |
Sep 15, 2023 | IBRD-89960 | Int Charges | 112,764.00 |
Sep 15, 2023 | IBRD-89960 | Int Charges | 78,080.74 |
Mar 15, 2024 | IBRD-89960 | Int Charges | 1,601.95 |
Mar 15, 2024 | IBRD-89960 | Int Charges | 108,999.20 |
Mar 15, 2024 | IBRD-89960 | Int Charges | 151,425.55 |
Apr 1, 2024 | IBRD-89960 | Loan Disb | 1,155,509.90 |
Mar 30, 2022 | IBRD-89960 | Loan Disb | 580,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Unsatisfactory | 2024-12-23 |
Procurement | Moderately Unsatisfactory | 2024-12-23 |
Project Management | Moderately Unsatisfactory | 2024-12-23 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2024-12-23 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-23 |
Financial Management | Satisfactory | 2024-12-23 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1. People who can take action to protect their lives, livelihood and property based on early warnings | Value | 15000.00 | 15000.00 | 3500000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
3. People benefiting from new Salinity Barrier (Number) | Value | 0.00 | 0.00 | 1000000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
PrDO Outcome 1: People who can take action to protect their lives, livelihood and property based on early warnings | Value | 15000.00 | 15000.00 | 3500000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2030 | |
Comment |
PrDO Outcome 2: People benefiting from multi-purpose water infrastructure for flood and climate resilience in Kelani River Basin (Number) | Value | 0.00 | 0.00 | 1800000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2030 | |
Comment |
Females who can take action to protect their lives, livelihood and property based on early warnings | Value | 7650.00 | 7650.00 | 1785000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
2. Improved performance of risk-based warning | Value | 10.00 | 10.00 | 66.00 |
Date | February 1, 2019 | December 15, 2023 | September 30, 2024 | |
Comment |
PrDO Outcome 3: Reduction in average annual flood damages in Kelani River Basin | Value | 0.00 | 0.00 | 78000000.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2030 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1. National hydromet data portal established | Value | No | No | Yes |
Date | December 31, 2021 | May 30, 2023 | December 31, 2026 | |
Comment |
Number of community members benefitting from irrigation and storm-water irrigation improvement activities | Value | 0.00 | 207500.00 | 25000.00 |
Date | January 31, 2023 | March 15, 2024 | December 31, 2024 | |
Comment |
Length of irrigation and storm-water infrastructure improved | Value | 0.00 | 58.50 | 15.00 |
Date | February 28, 2023 | March 15, 2024 | December 31, 2024 | |
Comment |
8. Ambatale Salinity Barrier constructed | Value | 0.00 | 0.00 | 100.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
3. Government professionals trained for flood forecasting and early warning | Value | 0.00 | 40.00 | 50.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
9. Detailed designs and studies for the construction of one upstream reservoir in Kelani river basin | Value | 0.00 | 0.00 | 2.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2025 | |
Comment |
4. National flood forecasting center established | Value | No | No | Yes |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
5. Disaster analytics and information center established | Value | No | No | Yes |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
6. Disaster and emergency preparedness plans developed by Grama Niladhari Divisions (GND, lowest level government administration) in Kelani Basin | Value | 0.00 | 0.00 | 10.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |
12. Grievances addressed | Value | 0.00 | 0.00 | 100.00 |
Date | December 31, 2021 | December 15, 2023 | December 31, 2026 | |
Comment |