Financier | Commitments |
---|---|
IDA Credit | 32.00 |
IDA Grant | 25.00 |
P160230
Active
Constantin Rusu , Christopher Tullis
Kyrgyz Republic
June 30, 2017
(as of board presentation)
March 20, 2018
February 20, 2019
US$ 50.00 million
Ministry of Digital Development
2018
US$ 57.00 million
B
April 17, 2024
July 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 32.00 |
IDA Grant | 25.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 57.00 |
IBRD + IDA Commitment | 57.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 12, 2019 | IDA-D2790 | Loan Disb | 320,799.70 |
Mar 20, 2018 | IDA-D2790 | Loan Commitment | 25,000,000.00 |
Mar 22, 2019 | IDA-D2790 | Loan Disb | 200,000.02 |
May 30, 2023 | IDA-D2790 | Loan Disb | 541,819.44 |
Jun 27, 2023 | IDA-D2790 | Loan Disb | 338,543.00 |
Jul 12, 2023 | IDA-D2790 | Loan Disb | 329,224.12 |
Aug 24, 2023 | IDA-D2790 | Loan Disb | 2,054,106.60 |
Apr 27, 2023 | IDA-D2790 | Loan Disb | 2,394,763.00 |
Feb 24, 2023 | IDA-D2790 | Loan Disb | 475,837.62 |
Oct 19, 2022 | IDA-D2790 | Loan Disb | 519,233.10 |
Dec 27, 2022 | IDA-D2790 | Loan Disb | 546,978.70 |
Aug 30, 2022 | IDA-D2790 | Loan Disb | 510,711.70 |
Jul 12, 2022 | IDA-D2790 | Loan Disb | 297,996.28 |
Jul 12, 2022 | IDA-D2790 | Loan Disb | 330,752.60 |
May 29, 2024 | IDA-D2790 | Loan Disb | 201,490.40 |
May 9, 2024 | IDA-D2790 | Loan Disb | 1,618,791.60 |
Mar 11, 2024 | IDA-D2790 | Loan Disb | 2,496,480.20 |
Mar 27, 2024 | IDA-D2790 | Loan Disb | 208,065.66 |
Jun 26, 2024 | IDA-D2790 | Loan Disb | 331,970.72 |
Dec 13, 2023 | IDA-D2790 | Loan Disb | 2,093,106.00 |
Dec 22, 2023 | IDA-D2790 | Loan Disb | 428,894.03 |
Jul 26, 2024 | IDA-62000 | Loan Disb | 2,269,338.80 |
Jul 26, 2024 | IDA-62000 | Loan Disb | 3,110,416.00 |
Mar 20, 2018 | IDA-62000 | Loan Commitment | 25,000,000.00 |
Jan 12, 2024 | IDA-74790 | Loan Commitment | 7,000,000.00 |
Oct 30, 2020 | IDA-D2790 | Loan Disb | 209,907.90 |
Jul 23, 2019 | IDA-D2790 | Loan Disb | 800,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2025-01-09 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-09 |
Procurement | Moderately Satisfactory | 2025-01-09 |
Project Management | Satisfactory | 2025-01-09 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-09 |
Monitoring and Evaluation | Satisfactory | 2025-01-09 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to the Internet | Value | 3140000.00 | 2960000.00 | 337000.00 |
Date | May 3, 2023 | January 4, 2023 | ||
Comment |
Private sector investments committed through the project (US$) | Value | 0.00 | 0.00 | 5000000.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
G-Cloud operational and ready to host digital government services | Value | No | No | |
Date | May 3, 2023 | May 3, 2023 | ||
Comment |
Internet penetration (%) | Value | 47.00 | 34.50 | 40.00 |
Date | December 31, 2017 | December 31, 2017 | ||
Comment |
International Internet bandwidth per capita (kilobits per second per person) | Value | 60.00 | 50.00 | 30.00 |
Date | May 3, 2023 | January 4, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of fiber-optic network | Value | 36530.00 | 31246.00 | 16281.00 |
Date | May 3, 2023 | April 11, 2022 | ||
Comment |
Number of government agencies using the G-Cloud shared infrastructure | Value | 0.00 | 0.00 | 5.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
Number of cross-border fiber-optic links | Value | 37.00 | 31.00 | 7.00 |
Date | May 3, 2023 | April 11, 2022 | ||
Comment |
People trained under the project | Value | 0.00 | 259.00 | 500.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 200000.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
Of which female (%) | Value | 0.00 | 0.00 | 50.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
of which female | Value | 0.00 | 0.00 | 35.00 |
Date | December 31, 2017 | December 31, 2017 | ||
Comment |
Partnerships formed under the project | Value | 0.00 | 6.00 | 10.00 |
Date | December 31, 2017 | April 11, 2022 | ||
Comment |
Social facilities provided with Internet access | Value | 2453.00 | 2453.00 | 0.00 |
Date | May 3, 2023 | May 3, 2023 | ||
Comment |
Digital Code developed and adopted by the Cabinet of Ministers of the Kyrgyz Republic and the Jogorku Kenesh (Parliament) of the Kyrgyz Republic (Yes/No) | Value | No | No | |
Date | May 3, 2023 | May 3, 2023 | ||
Comment |
Number of information systems migrated to G-Cloud | Value | 0.00 | 0.00 | 0.00 |
Date | May 3, 2023 | May 3, 2023 | ||
Comment |
Number of services provided by G-Cloud | Value | 0.00 | 0.00 | 0.00 |
Date | May 3, 2023 | May 3, 2023 | ||
Comment |