Financier | Commitments |
---|---|
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan | 19.00 |
P160445
Closed
Kiran Afzal
FATA Secretariat,Government of Khyber Pakhtunkhwa,Economic Affairs Division
February 15, 2017
(as of board presentation)
March 28, 2017
N/A
US$ 19.00 million
Small and Medium Enterprise Development Authority (SMEDA)
2017
US$ 19.00 million
B
Not Applicable
June 30, 2022
Yes
BANK APPROVED
July 29, 2022
Financier | Commitments |
---|---|
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan | 19.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 19.00 |
Total Project Cost** | 19.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SME beneficiaries of the MGs, of which at least 5 percent are owned/managed by women entrepreneurs. | Value | 0.00 | 1601.00 | 2500.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | Original end-target of 850 surpassed. 32 of the total MGs were given to women entrepreneurs. | Indicator value increased. The increased target for women beneficiaries is an aspirational target. Indicator name being revised toensure consistency in the PMIs. |
Number of direct jobs created by the enterprises supported through the Project. | Value | 0.00 | 8843.00 | 13500.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | A baseline for jobs was not established at the initiation of the Project activities in 2011. | Original project end-target of 8,000 direct and indirect jobs was surpassed. Of these jobs, 126 jobs were created for women. | Target enhanced. The indicator title has been revised to remove the mention of âindirectâ jobs. |
Percentage of the matching grants beneficiaries operational and productive at the completion of the Project. | Value | 0.00 | 0.00 | 75.00 |
Date | October 11, 2011 | November 15, 2015 | June 30, 2020 | |
Comment | Indicator name revised to remove the target value from its title. |
Investment attracted from the Diaspora and private enterprises. | Value | 0.00 | 0.00 | 10.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | Value of this indicator is in US$ millions. | ERKF was unable to fully realize the investments promised by the diaspora for KP. GoKP is pursuing a few pipeline contracts, so theAF will monitor progress on this. | This will also include the private investment generated by MGs provided to the SMEs. The indicator name has thus been revised. |
Investment facilitation authorities established in FATA and KP. | Value | 0.00 | 100.00 | 100.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | Target fully achieved by the project. | The indicator title has been revised as the authorities continue changing the names of the investment authorities. |
Number of direct jobs created for women through the matching grants. | Value | 0.00 | 126.00 | 315.00 |
Date | October 11, 2011 | December 16, 2011 | June 30, 2020 | |
Comment |
Number of private enterprises using the Tourism Management Systems developed by the project. | Value | 0.00 | 0.00 | 50.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | This is a new indicator linked to Component 4 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SME Rehabilitation Support provided through the MGs. | Value | 0.00 | 1447.00 | 2200.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | The original target of 600 was surpassed. Indicator name revised to remove the target value. | Indicator value increased to reflect the scope of the AF. |
SME beneficiaries of the up-gradation MGs. | Value | 0.00 | 194.00 | 300.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | The original indicator value of 250 partially achieved. Indicator title revised to remove the target value from its title. | Original indicator value being enhanced to reflect the scope of the AF |
Number of SMEs/clusters that have used the Business Development Services (BDS). | Value | 0.00 | 800.00 | 1000.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | Target surpassed. | The indicator value is being enhanced. |
Diaspora Outreach program implemented: At least 7 to 10 outreach activities/events successfully organized | Value | 0.00 | 5.00 | 7.00 |
Date | October 11, 2011 | November 30, 2016 | March 31, 2017 | |
Comment | This is linked to Component 2, which will not disburse under AF. | Partially achieved. | It will not be monitored during the AF implementation. |
Re-connect Pakistan (web tools for Diaspora) operational | Value | 0.00 | 6200.00 | 10000.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2016 | |
Comment | This is measured by the number of hits on the website. | This was partially achieved. |
PPD mechanism established in KP/FATA; defining economic growth and employment generation policy reforms; proposals for implementation submitted | Value | 0.00 | 0.00 | 6.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2016 | |
Comment | Unachieved. | Not relevant to AF activities. |
Machinery pools/common facility supported by the Project. | Value | 0.00 | 2.00 | 6.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | Original target value of 11 was partially achieved. | Indicator value revised downwards to 6. |
Recommended regulatory/institutional reforms introduced/notified by Industries Department for private sector development in KP | Value | 0.00 | 2.00 | 5.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2016 | |
Comment | Partially achieved. | Not directly relevant to the activities of AF. |
Number of individuals (including women) that received training in the tourism sector. | Value | 0.00 | 0.00 | 200.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | This is a new target linked to the Component 4. |
Officials of the IEs and relevant departments of KP and FATA receive training in technical areas, including (i) trade and commerce,(ii) tourism, and (iii) PPPs. | Value | 0.00 | 25.00 | 100.00 |
Date | October 31, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | The original grant supported training of the 25 officials of KP, FATA, and SMEDA. |
Number of scalable investment projects and activities identified in the competitive sectors of KP and FATA. | Value | 0.00 | 2.00 | 6.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | GoKP has already conducted two feasibility studies under CIPK: (i) Dates Processing Plant (KP): and (ii) Fruits and VegetablesDehydration Unit | This is a new indicator linked to Component 4. |
SME owners satisfied with the processing of the MGs under the AF. | Value | 0.00 | 0.00 | 80.00 |
Date | October 11, 2011 | November 30, 2016 | June 30, 2020 | |
Comment | This is a new indicator for measuring citizen engagement. It is directly linked to the AF grant processing steps. | This will be measured annually and at the end of the AF. |
Number of individuals (including women) in FATA that received training in the pine nut value chains. | Value | 0.00 | 0.00 | 100.00 |
Date | October 11, 2011 | March 30, 2017 | June 30, 2020 | |
Comment | This indicator is linked to Component 4. |