AP Integrated Irrigation & Agriculture Transformation Project

Abstract*

The development objective of Andhra Pradesh Integrated Irrigation and Agriculture Transformation Project for India is to enhance agricultural productivity, profitability and climate resilience of smallholder farmers in selected districts of Andhra Pradesh. This project has four components. 1) The first component, Improving Irrigated Agriculture Efficiency, aims to enhance the water security of individual farms so as to reduce the risks associated...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to enhance agricultural productivity, profitability and climate resilience of smallholder farmers in selected districts of Andhra Pradesh.

Key Details

Project Details

  • P160463

  • Active

  • Nora Kaoues , Cheikh Dia

  • Republic of India

  • India

  • May 3, 2017

  • (as of board presentation)

    October 23, 2018

  • December 27, 2018

  • US$ 238.08 million

  • Government of Andhra Pradesh

  • South Asia

  • 2019

  • US$ 172.20 million

  • B

  • November 24, 2023

  • October 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 172.20
Borrower/Recipient 73.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 172.20
IDA Commitment N/A
IBRD + IDA Commitment 172.20
Lending Instrument
Grant Amount N/A
Total Project Cost** 238.08

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 23, 2018 IBRD-89100 Loan Commitment 172,200,000.00
Dec 27, 2018 IBRD-89100 Fee Charges 430,500.00
Dec 15, 2023 IBRD-89100 Int Charges 180,204.23
Dec 15, 2023 IBRD-89100 Int Charges 899,509.70
Jun 15, 2023 IBRD-89100 Int Charges 36,374.32
Jun 15, 2023 IBRD-89100 Int Charges 179,219.52
Jun 15, 2023 IBRD-89100 Int Charges 786,360.44
Jun 15, 2024 IBRD-89100 Int Charges 179,757.62
Jun 15, 2024 IBRD-89100 Int Charges 5,652.95
Jun 15, 2024 IBRD-89100 Int Charges 952,984.06
May 7, 2024 IBRD-89100 Loan Cancel 109,560,000.00
Jun 15, 2020 IBRD-89100 Int Charges 387,318.20
Dec 15, 2019 IBRD-89100 Int Charges 450,907.72
Dec 15, 2019 IBRD-89100 Int Charges 180,204.23
Dec 15, 2020 IBRD-89100 Int Charges 179,711.88
Dec 15, 2020 IBRD-89100 Int Charges 174,871.27
Jun 15, 2020 IBRD-89100 Int Charges 179,757.62
Jun 15, 2021 IBRD-89100 Int Charges 179,173.78
Jun 15, 2021 IBRD-89100 Int Charges 150,918.56
Dec 15, 2021 IBRD-89100 Int Charges 180,204.23
Dec 15, 2021 IBRD-89100 Int Charges 141,631.27
Jun 15, 2022 IBRD-89100 Int Charges 179,219.52
Jun 15, 2022 IBRD-89100 Int Charges 162,417.16
Dec 15, 2022 IBRD-89100 Int Charges 180,204.23
Dec 15, 2022 IBRD-89100 Int Charges 541,808.50
Jun 15, 2019 IBRD-89100 Int Charges 172,949.73
Jun 15, 2019 IBRD-89100 Int Charges 271,541.47
Mar 15, 2019 IBRD-89100 Loan Disb 28,000,000.00
Dec 27, 2018 IBRD-89100 Loan Disb 430,500.00
Dec 15, 2023 IBRD-89100 Int Charges 15,119.37

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2025-02-05
Procurement Moderately Satisfactory 2025-02-05
Project Management Satisfactory 2025-02-05
Financial Management Moderately Unsatisfactory 2025-02-05
Monitoring and Evaluation Moderately Unsatisfactory 2025-02-05
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-02-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Productivity of specific crops increasedValue0.000.000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Farmers reached with agricultural assets or servicesValue0.0036088.00200000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Farmer's income increasedValueINR 15,722.0075,412.00INR 19,653.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Water Productivity Increased (Kg/m3)Value(as given for each crop)as given for each crop in baseline value(as given for each crop)
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • a. PaddyValue5.005.005.10
    Date
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.0050000.00
    DateMarch 19, 2018September 30, 2025
    Comment
  • a. Paddy (Surface water)Value0.33 kg/m30.33 kg/m30.42 kg/m3
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • b. GroundnutValue1.141.141.14
    Date
    Comment
  • b. Paddy (Surface + Groundwater)Value0.37 kg/m30.37 kg/m30.38 kg/m3
    Date
    Comment
  • c. ChilliValue2.372.372.40
    Date
    Comment
  • c. Groundnut (Surface + Groundwater)Value0.28 kg/m30.28 kg/m30.28 kg/m3
    Date
    Comment
  • d. Chilli (Surface + Groundwater)Value0.30 kg/m30.30 kg/m30.30 kg/m3
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area increased/decreased in the Tank Command under Paddy, Pulses, Oil seeds and VegetablesValue0.000.000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Satisfaction rate related to WUAs performanceValue17.0055.1070.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Number of Farmers Having Access to Infrastructural Facilities CreatedValue0.000.000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Beneficiary (of which 50 percent women) satisfaction rate with quality of services provided by the projectValue0.0064.0280.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.000.0090000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • a. PaddyValue95908.0077635.2875908.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • a. Storage StructuresValue0.002246.006000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • b. Red GramValue2052.002052.005552.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • b. Low Energy cool ChambersValue0.001825.005000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Area provided with new irrigation or drainage servicesValue0.000.0090000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Number of FPO activities financed through business plansValue0.0022.00100.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • c. GroundnutValue4982.001031.508482.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Area provided with improved irrigation or drainage servicesValue46000.0058904.0090000.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Number of women represented in WUA and FPOValue0.0028.7130.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • d. ChilliValue627.0028565.554777.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Area under fishery increased (Ha EWSA) at Full Tank LevelValue33.0033.0041.00
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment
  • Increment in Fish Productivity in short seasonal tanksValue0.360.360.53
    DateMarch 19, 2018November 24, 2023October 31, 2025
    Comment