Financier | Commitments |
---|---|
IDA Grant | 45.00 |
P160500
Closed
Francis Ovanda Mbele , Aguiratou Savadogo-Tinto, Papa Ndiaye
Government of Central African Republic
June 5, 2017
(as of board presentation)
June 30, 2017
April 10, 2018
US$ 53.40 million
Ministère des Travaux Publics et de l'Entretien Routier
2017
US$ 45.00 million
B
April 11, 2024
July 29, 2022
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 45.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 45.00 |
IBRD + IDA Commitment | 45.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 53.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 30, 2017 | IDA-D2230 | Loan Commitment | 45,000,000.00 |
Aug 21, 2019 | IDA-D2230 | Loan Disb | 29,953.41 |
Nov 29, 2022 | IDA-D2230 | Loan Disb | -1,277,001.50 |
Jan 12, 2023 | IDA-D2230 | Loan Cancel | 3,078,316.50 |
Nov 1, 2021 | IDA-D2230 | Loan Disb | 230,348.27 |
Jan 27, 2022 | IDA-D2230 | Loan Disb | 203,109.45 |
Jan 11, 2022 | IDA-D2230 | Loan Disb | 157,814.55 |
Jul 21, 2022 | IDA-D2230 | Loan Disb | -1,745,115.00 |
Jul 18, 2022 | IDA-D2230 | Loan Cancel | 15,085,943.00 |
Dec 21, 2020 | IDA-D2230 | Loan Disb | 279,114.53 |
Mar 23, 2021 | IDA-D2230 | Loan Disb | 41,734.97 |
Feb 4, 2021 | IDA-D2230 | Loan Disb | 42,508.53 |
Jul 28, 2021 | IDA-D2230 | Loan Disb | 113,863.88 |
May 28, 2021 | IDA-D2230 | Loan Disb | 178,993.52 |
Jun 17, 2020 | IDA-D2230 | Loan Disb | 22,914.87 |
Jun 17, 2020 | IDA-D2230 | Loan Disb | 134,501.12 |
Jun 25, 2020 | IDA-D2230 | Loan Disb | 213,354.30 |
Jun 25, 2020 | IDA-D2230 | Loan Disb | 248,368.92 |
Jul 17, 2020 | IDA-D2230 | Loan Disb | 567,570.00 |
Nov 5, 2020 | IDA-D2230 | Loan Disb | 4,397,241.50 |
Oct 28, 2020 | IDA-D2230 | Loan Disb | 142,841.10 |
Sep 14, 2020 | IDA-D2230 | Loan Disb | 38,219.03 |
Aug 21, 2019 | IDA-D2230 | Loan Disb | 8,265.80 |
Jul 24, 2019 | IDA-D2230 | Loan Disb | 165,655.66 |
Aug 21, 2019 | IDA-D2230 | Loan Disb | 631,338.94 |
Sep 26, 2019 | IDA-D2230 | Loan Disb | 30,727.98 |
Sep 26, 2019 | IDA-D2230 | Loan Disb | 34,081.16 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 162,488.19 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 166,908.61 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 146,699.95 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 88,501.29 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 126,446.28 |
Jul 8, 2019 | IDA-D2230 | Loan Disb | -4,397,240.50 |
Nov 21, 2019 | IDA-D2230 | Loan Disb | 90,692.97 |
Nov 21, 2019 | IDA-D2230 | Loan Disb | 40,793.27 |
Oct 30, 2019 | IDA-D2230 | Loan Disb | 132,416.69 |
Dec 27, 2019 | IDA-D2230 | Loan Disb | 4,397,241.50 |
Jun 18, 2018 | IDA-D2230 | Loan Disb | 8,794,482.00 |
Jul 5, 2018 | IDA-D2230 | Loan Disb | 2,509,062.80 |
Mar 29, 2019 | IDA-D2230 | Loan Disb | 410,373.78 |
Apr 18, 2019 | IDA-D2230 | Loan Disb | 8,794,482.00 |
Apr 9, 2019 | IDA-D2230 | Loan Disb | 236,210.84 |
Dec 1, 2022 | IDA-D2230 | Loan Disb | 11,099.12 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Unsatisfactory | 2022-03-11 |
Procurement | Moderately Satisfactory | 2022-03-11 |
Project Management | Moderately Satisfactory | 2022-03-11 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2022-03-11 |
Financial Management | Moderately Satisfactory | 2022-03-11 |
Monitoring and Evaluation | Moderately Satisfactory | 2022-03-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-22-2023 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-26-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Farmers in the project area with improved access to markets | Value | 0.00 | 36000.00 | 20000.00 |
Date | August 1, 2017 | July 29, 2022 | ||
Comment |
Proportion of improved project roads under routine maintenance | Value | 0.00 | 0.00 | 50.00 |
Date | August 1, 2017 | July 29, 2022 | July 26, 2022 | |
Comment |
Basic social services (markets, schools and health centers) with improved access in the project area | Value | 0.00 | 63.00 | 5.00 |
Date | August 1, 2017 | July 29, 2022 | ||
Comment |
Travel time between Ndele and Birao | Value | 10.00 | 9.00 | 7.00 |
Date | August 1, 2017 | July 29, 2022 | July 26, 2022 | |
Comment |
Passability of the road between Ndele and Birao | Value | 5.00 | 7.00 | 5.00 |
Date | August 1, 2017 | July 29, 2022 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 614.00 | 600.00 |
Date | August 1, 2017 | July 29, 2022 | July 26, 2022 | |
Comment |
Person-days of employment created through the Labor Intensive Public Works | Value | 0.00 | 58300.00 | 70000.00 |
Date | July 2, 2019 | July 29, 2022 | ||
Comment |
Share of person-days of employment created for women | Value | 0.00 | 0.00 | 33.00 |
Date | August 1, 2017 | April 4, 2018 | ||
Comment |
Community-based maintenance organizations that are operational | Value | 0.00 | 0.00 | 10.00 |
Date | July 2, 2019 | July 29, 2022 | ||
Comment |
Roads with improved road safety measures | Value | 0.00 | 614.00 | 600.00 |
Date | August 1, 2017 | July 29, 2022 | July 26, 2022 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 105000.00 | 25000.00 |
Date | August 1, 2017 | July 29, 2022 | ||
Comment |
Proportion of direct beneficiaries expressing positive reaction to the project | Value | 0.00 | 0.00 | 80.00 |
Date | August 1, 2017 | April 4, 2018 | ||
Comment |