Financier | Commitments |
---|---|
IDA Credit | 22.32 |
IDA Grant | 47.68 |
P160519
Closed
Ivan Drabek
N/A
September 22, 2016
(as of board presentation)
November 8, 2016
N/A
US$ 70.00 million
N/A
2017
US$ 70.00 million
B
January 17, 2024
June 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 22.32 |
IDA Grant | 47.68 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 70.00 |
IBRD + IDA Commitment | 70.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 70.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries of Safety Nets Programs - (Unconditional) Social Cash Transfers (number) (Number, Core Breakdown) | Value | 0 | 21,568 | 21,000 |
Date | October 18, 2013 | March 15, 2016 | June 30, 2018 | |
Comment |
Number of direct beneficiaries of PWP - emergency response | Value | 0.00 | 0.00 | 902000.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number of direct beneficiaries of Social Cash Transfers (SCT) | Value | 0.00 | 21000.00 | 123711.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number of direct beneficiaries of PWP - regular beneficiaires | Value | 0 | 985,635 (53% female) | 985,635 (of which 50% female) |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Indicator was incorrectly entered in the Bankâs system as a breakdown indicator |
Percentage of households with asset value above critical threshold | Value | 33% livelihood and skills development, 25% PWP, 4. | 33% livelihood and skills development, 25% PWP, 4. | no set target |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment is under way, results are due by end-2016 |
Establishment of an integrated and functional national safety net delivery systems | Value | 0 | 2 | 35 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | 2 districts with integrated and functional safety net delivery system | 35 districts with integrated and functional safety net delivery system |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of COMSIP and other livelihood groups formed and strengthened | Value | 4457.00 | 5241.00 | 6697.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Number of groups formed under COMSIP only so far |
Number of people trained on skill development activities | Value | 0.00 | 2201.00 | 0.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | No set target, as it will depend on group demands for skills development activities, i.e. product value addition. |
Number of Local Authorities with operational MIS | Value | 0 | 2 | 35 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number of Local Authorities with operational M&E system | Value | 0 | 2 | 35 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number of extension workers trained and supported with equipment | Value | 0.00 | 1116.00 | 1350.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of households having at least three meals per day | Value | 21.20 | 0.00 | 70.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment is under way, results are due by end-2016 |
Percentage of participants paid within the agreed time frame (two weeks for PWP and within a month for SCT) | Value | 50 for STC, 54 for PWP | 100 for STC, assessment under way for PWP | 100 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of beneficiaries receiving full entitlement (PWP, SCT) | Value | 0 | 100 | 100 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of beneficiaries staying in the program for a minimum of three years (PWP, SCT) | Value | 0.00 | 0.00 | 80.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of subprojects selected and implemented following participatory community-based planning approaches | Value | 0.00 | 100.00 | 100.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of subprojects or investment for which arrangement for community engagement and or operation and maintenance are established | Value | 0.00 | 30.00 | 70.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of households reporting that asset depletion is prevented as a result of transfers (SCT, PWP) | Value | 0.00 | 0.00 | 40.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment is under way, results are due by end-2016 |
Number of Local Authorities with community safety net plans developed in a participatory approach | Value | 0.00 | 28.00 | 35.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number and type of productive community assets completed (re-forestation, road construction and maintenance, irrigation) | Value | 0 | 4,069 hectares re-afforested, 5,050 roads construc | no set targets |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | These are demand-driven interventions based on community priorities |
Percentage of subprojects screened for ESMF | Value | 0.00 | 80.00 | 100.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of subprojects for which safeguard mitigation plans are developed and are being implemented | Value | 0.00 | 80.00 | 100.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Number of Local Authorities implementing harmonized targeting instruments to select beneficiaries | Value | 0.00 | 2.00 | 35.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | End target based on the assumption that all Local Authorities will have targeting systems for PW. |
Number of groups/cooperatives accessing grants for investments | Value | 0.00 | 95.00 | 400.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of households that report improved access to social services | Value | 0 | No set target | |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment is under way, results are due by end-2016 | These are demand-driven interventions based on community priorities. |
Percentage increase in household productive assets by type | Value | 0.00 | 0.00 | 25.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment is under way, results are due by end-2016 |
Number of Local Authorities with operational harmonized targeting mechanism | Value | 0.00 | 2.00 | 35.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment |
Percentage of beneficiaries who are aware of project information and project supported investments | Value | 0.00 | 0.00 | 100.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment under way, result will be known by end-2016 |
Percentage of grievances registered related to delivery of project benefits that are actually addressed | Value | 0.00 | 0.00 | 100.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Assessment under way, result will be known by end-2016 |
% of people reporting improvement in the natural resource and environment and its benefit to communities as a result of PW activities (Percentage, Custom) | Value | 0.00 | 0.00 | 60.00 |
Date | October 18, 2013 | March 15, 2016 | June 30, 2018 | |
Comment | Unit of measure for this indicator was incorrectly entered in the Bankâs system as âAmount USDâ |
Percentage of households that report improved access to and use of small scale irrigation | Value | 5 | no set target | |
Date | September 30, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Based on MASAF III achievements | Assessment is under way, results are due by end-2016 | These are demand-driven interventions based on community priorities |
Percentage of people engaging in diversified income-generation activities (off-farm and on-farm) | Value | 63.00 | 0.00 | 80.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | 63% is for old groups, 0 for new groups | Assessment is under way, results will be known by end-2016 | 80% for old groups, 50% for new groups |
Percentage increase in household level savings | Value | 84 (old groups) 0 (new groups) | 100.00 (old groups) 70 (new groups) | |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Baseline for old groups based on COMSIP groups only for the period 2009-2013 | Assessment is under way, results are due by end-2016 |
% of beneficiaries that feel project investments/ PWP investments reflected their needs (Percentage, Core) | Value | 0.00 | 0.00 | 80.00 |
Date | October 18, 2013 | March 15, 2016 | June 30, 2018 | |
Comment | Indicator was incorrectly entered in the Bankâs system as a breakdown indicator |
Percentage of beneficiaries who feel project investments/PWP reflected their needs | Value | 74.10 | 0.00 | 80.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | Based on MASAF III Beneficiary Assessment |
Percentage of people reporting improvement in the natural resource and environment and its benefit to communities as a result of public works activities | Value | 0.00 | 0.00 | 60.00 |
Date | September 1, 2014 | September 28, 2015 | December 31, 2019 | |
Comment |
Number of people trained on livelihood development activities | Value | 0.00 | 22000.00 | 0.00 |
Date | September 1, 2014 | September 28, 2016 | December 31, 2019 | |
Comment | No set target, it will be based on the number of groups formed and related training needs |