Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
National Government | 40.00 |
P160661
Closed
Dong Kwak , Willem Van Der Muur
Republic of Indonesia
January 3, 2017
(as of board presentation)
July 18, 2018
November 15, 2018
US$ 240.00 million
Ministry of Agrarian Affairs and Spatial Planning / National Land Agency (ATR/BPN),Geospatial Information Agency; Badan Informasi Geospasial (BIG)
2019
US$ 200.00 million
A
April 3, 2024
October 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
National Government | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 240.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 3, 2019 | IBRD-88970 | Loan Disb | 140,000.00 |
Feb 6, 2024 | IBRD-88970 | Loan Disb | 10,000,000.00 |
Feb 1, 2019 | IBRD-88970 | Int Charges | 52,054.79 |
Jan 18, 2019 | IBRD-88970 | Fee Charges | 500,000.00 |
Feb 1, 2020 | IBRD-88970 | Int Charges | 246,010.33 |
Feb 1, 2020 | IBRD-88970 | Int Charges | 54,844.02 |
Mar 3, 2020 | IBRD-88970 | Loan Disb | 4,076,000.00 |
Dec 23, 2019 | IBRD-88970 | Loan Disb | 3,900,000.00 |
Aug 1, 2023 | IBRD-88970 | Int Charges | 88,936.63 |
Aug 1, 2023 | IBRD-88970 | Int Charges | 3,609,851.00 |
Aug 7, 2023 | IBRD-88970 | Loan Disb | 14,000,000.00 |
May 9, 2024 | IBRD-88970 | Loan Disb | 5,500,000.00 |
Jul 16, 2024 | IBRD-88970 | Loan Disb | 10,500,000.00 |
Feb 1, 2024 | IBRD-88970 | Int Charges | 30,747.51 |
Feb 1, 2024 | IBRD-88970 | Int Charges | 48,653.75 |
Feb 1, 2024 | IBRD-88970 | Int Charges | 5,193,485.50 |
Aug 1, 2024 | IBRD-88970 | Int Charges | 32,989.83 |
Aug 1, 2024 | IBRD-88970 | Int Charges | 20,888.03 |
Aug 1, 2024 | IBRD-88970 | Int Charges | 5,886,934.50 |
Feb 20, 2019 | IBRD-88970 | Loan Disb | 3,744,948.20 |
Aug 1, 2019 | IBRD-88970 | Int Charges | 243,789.84 |
Aug 1, 2019 | IBRD-88970 | Int Charges | 57,466.21 |
Feb 8, 2021 | IBRD-88970 | Loan Disb | 6,500,000.00 |
Feb 1, 2021 | IBRD-88970 | Int Charges | 211,469.40 |
Feb 1, 2021 | IBRD-88970 | Int Charges | 147,996.70 |
Feb 1, 2021 | IBRD-88970 | Int Charges | 2,458.33 |
Aug 1, 2020 | IBRD-88970 | Int Charges | 232,293.47 |
Aug 1, 2020 | IBRD-88970 | Int Charges | 132,101.88 |
Aug 6, 2020 | IBRD-88970 | Loan Disb | 11,000,000.00 |
Aug 1, 2020 | IBRD-88970 | Int Charges | 1,066.24 |
Aug 1, 2020 | IBRD-88970 | Int Charges | 10,980.44 |
Nov 10, 2020 | IBRD-88970 | Loan Disb | 7,000,000.00 |
Jun 3, 2020 | IBRD-88970 | Loan Disb | 6,100,000.00 |
Aug 1, 2021 | IBRD-88970 | Int Charges | 195,081.30 |
Jul 18, 2018 | IBRD-88970 | Loan Commitment | 200,000,000.00 |
Jul 9, 2021 | IBRD-88970 | Loan Disb | 3,400,000.00 |
Aug 19, 2021 | IBRD-88970 | Loan Disb | 13,150,000.00 |
Feb 1, 2021 | IBRD-88970 | Int Charges | 20,935.17 |
Feb 1, 2022 | IBRD-88970 | Int Charges | 535.61 |
Feb 1, 2022 | IBRD-88970 | Int Charges | 1,289.05 |
Mar 1, 2022 | IBRD-88970 | Loan Disb | 5,400,000.00 |
Aug 1, 2022 | IBRD-88970 | Int Charges | 157,706.30 |
Aug 1, 2022 | IBRD-88970 | Int Charges | 445,083.47 |
Feb 1, 2022 | IBRD-88970 | Int Charges | 177,245.80 |
Feb 1, 2022 | IBRD-88970 | Int Charges | 236,645.83 |
Apr 25, 2022 | IBRD-88970 | Loan Disb | 8,000,000.00 |
Jul 27, 2022 | IBRD-88970 | Loan Disb | 6,600,000.00 |
Aug 1, 2021 | IBRD-88970 | Int Charges | 178,265.06 |
Nov 29, 2021 | IBRD-88970 | Loan Disb | 4,700,000.00 |
May 10, 2023 | IBRD-88970 | Loan Disb | 17,000,000.00 |
Feb 1, 2023 | IBRD-88970 | Loan Disb | 17,500,000.00 |
Feb 1, 2023 | IBRD-88970 | Int Charges | 226.03 |
Feb 1, 2023 | IBRD-88970 | Int Charges | 87,972.22 |
Feb 1, 2023 | IBRD-88970 | Int Charges | 134,013.60 |
Feb 1, 2023 | IBRD-88970 | Int Charges | 2,076,227.20 |
Nov 9, 2022 | IBRD-88970 | Loan Disb | 21,800,000.00 |
Nov 3, 2023 | IBRD-88970 | Loan Disb | 16,000,000.00 |
Aug 1, 2023 | IBRD-88970 | Int Charges | 85,780.95 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2024-10-11 |
Progress towards achievement of PDO | Satisfactory | 2024-10-11 |
Financial Management | Satisfactory | 2024-10-11 |
Monitoring and Evaluation | Satisfactory | 2024-10-11 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2024-10-11 |
Procurement | Moderately Satisfactory | 2024-10-11 |
Project Management | Highly Satisfactory | 2024-10-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of project target area land parcels mapped in a parcel map. | Value | 57.17 | 66.07 | 67.26 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Area of country with publicly accessible ortho-rectified satellite imagery equivalent to map scale 1:5,000. | Value | 10.00 | 59.70 | 30.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of land parcels mapped in the project target areas. | Value | 42569.00 | 0.00 | 46732.00 |
Date | August 1, 2018 | July 31, 2021 | ||
Comment |
Number of core government agencies using accessible ortho-rectified satellite imagery equivalent to map scale 1:5,000 for their activities. | Value | 1.00 | 0.00 | 5.00 |
Date | August 1, 2018 | July 31, 2022 | ||
Comment |
Direct project beneficiaries (landholders, concessionaires, government agencies, community members) in the project target areas with their land parcels mapped. | Value | 0.00 | 26510.02 | 16652.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Share of districts in the project areas with forest boundaries reconstructed from an MoEF enactment or demarcated for an enactment by MoEF. | Value | 1.00 | 27.14 | 15.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of project target area land rights registered to the land register. | Value | 57.17 | 59.57 | 62.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Share of target areas with available and accessible geospatial data (1:5000 map). | Value | 56.47 | 78.15 | 91.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of regencies targeted by public awareness campaign on land. | Value | 0.00 | 140.00 | 74.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
CORS network coverage of project target areas in Kalimantan | Value | 15.00 | 0.00 | 62.00 |
Date | August 1, 2018 | July 31, 2022 | ||
Comment |
Share of registered land rights belonging to female either alone or through joint ownership in the project target area. | Value | 36.00 | 41.21 | 40.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of regencies targeted by environmental and social vulnerability mapping. | Value | 0.00 | 75.00 | 74.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of regencies with a completed environmental and social risk assessment | Value | 0.00 | 0.00 | 60.00 |
Date | August 1, 2018 | July 31, 2022 | ||
Comment |
Number of land rights registered in the Land Register in the project target areas. | Value | 42569.00 | 0.00 | 46164.00 |
Date | August 1, 2018 | July 31, 2022 | ||
Comment |
Number of ATR/BPN offices in target areas with upgraded archives and technical infrastructure. | Value | 0.00 | 130.00 | 70.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Participatory parcel map publicly accessible via NSDI and INA-Geoportal. | Value | No | No | Yes |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of analytical studies prepared by the project. | Value | 0.00 | 9.00 | 10.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of ATR/BPN offices operating eLand system. | Value | 0.00 | 140.00 | 74.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
NSDI Data Centre and INA-Geoportal solutions modernized. | Value | No | No | Yes |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Grievances responded and/or resolved within the stipulated service standards for response times. | Value | 0.00 | 100.00 | 100.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Regulations analyzed and advised upon. | Value | 0.00 | 5.00 | 5.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Coverage of project target provinces with adequate and accessible DEM/DSM and ground control points. | Value | 46.75 | 100.00 | 100.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Availability of electronic land administration and geospatial services. | Value | 12.00 | 24.00 | 21.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of people trained by the project. | Value | 0.00 | 2507.00 | 2000.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Number of electronic requests processed annually by the ATR/BPN. | Value | 10000.00 | 6288887.00 | 100000.00 |
Date | August 1, 2018 | August 31, 2023 | July 31, 2022 | |
Comment |
Reduced emissions from deforestation in demarcated Forest Areas (tCO2e). | Value | 0.00 | 0.00 | 0.00 |
Date | August 1, 2018 | August 31, 2023 | ||
Comment |
Number of non-government beneficiaries received training. | Value | 0.00 | 0.00 | 10000.00 |
Date | August 1, 2018 | July 31, 2022 | ||
Comment |
Reduced emissions from deforestation in demarcated Forest Areas compared to areas without clarity on Forest Area boundaries (tCO2e). | Value | 0.00 | 0.00 | 0.00 |
Date | August 1, 2018 | August 31, 2023 | ||
Comment |
Number of women trained by the project | Value | 0.00 | 2357.00 | 600.00 |
Date | ||||
Comment |