Financier | Commitments |
---|---|
IDA Grant | 17.50 |
P160739
Active
Lan Nguyen
Republic of Maldives
October 11, 2016
(as of board presentation)
June 23, 2017
September 13, 2017
US$ 17.50 million
Ministry of Environment
2017
US$ 17.50 million
A
April 1, 2024
November 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 17.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 17.50 |
IBRD + IDA Commitment | 17.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 17.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 23, 2017 | IDA-D1990 | Loan Commitment | 17,500,000.00 |
May 20, 2021 | IDA-D1990 | Loan Disb | 860,275.00 |
May 20, 2021 | IDA-D1990 | Loan Disb | 3,004,153.00 |
Dec 29, 2022 | IDA-D1990 | Loan Disb | 800,000.00 |
Jun 13, 2023 | IDA-D1990 | Loan Disb | 800,000.00 |
Apr 2, 2019 | IDA-D1990 | Loan Disb | 3,667,134.00 |
Jun 17, 2024 | IDA-D1990 | Loan Disb | 1,500,000.00 |
Jun 11, 2024 | IDA-D1990 | Loan Disb | 400,000.00 |
Apr 26, 2024 | IDA-D1990 | Loan Disb | 1,000,000.00 |
Jan 16, 2018 | IDA-D1990 | Loan Disb | 1,517,025.00 |
Aug 17, 2018 | IDA-D1990 | Loan Disb | 34,000.00 |
Nov 27, 2023 | IDA-D1990 | Loan Disb | 1,303,168.80 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-06-20 |
Financial Management | Satisfactory | 2024-06-20 |
Overall Safeguards Rating | Moderately Satisfactory | 2024-06-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-06-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-06-20 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-06-20 |
Project Management | Moderately Satisfactory | 2024-06-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-06-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Regional Waste Management Center (RWMC) operational | Value | 0.00 | 12.00 | 12.00 |
Date | June 30, 2017 | November 9, 2023 | December 31, 2024 | |
Comment |
Number of IWMCs treating organic waste in selected zones | Value | 5.00 | 28.00 | 19.00 |
Date | April 4, 2019 | March 21, 2023 | December 31, 2024 | |
Comment |
Number of IWMCs in Zone 2, storing, treating/processing ‘other’ waste (not included in organics) and transporting to a RWMC or another end-user. | Value | 0.00 | 24.00 | 45.00 |
Date | June 30, 2017 | March 21, 2023 | December 31, 2024 | |
Comment |
Share of target beneficiaries (disaggregated by gender) with rating "satisfied" or above with application of the solid waste management approach (user fees, environmental benefits, reliability) | Value | 22.00 | 26.00 | 50.00 |
Date | June 20, 2019 | February 21, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Update the National Solid Waste Management Policy and Strategy, and develop underlying regulations, laws and implementation plans anagement Strategy | Value | No updated waste strategy and policy, no regulatio | The government strategy for the phaseout of single | Adoption of new waste management Law and National |
Date | June 30, 2017 | November 9, 2023 | December 31, 2024 | |
Comment |
Island Waste and Resource Management Centers Established | Value | 22.00 | 57.00 | 64.00 |
Date | June 30, 2017 | February 21, 2023 | December 31, 2024 | |
Comment |
The number of national institutional staff trained under the project and remaining on the job at least one year after the training. | Value | 0.00 | 48.00 | 50.00 |
Date | September 29, 2017 | November 9, 2023 | December 31, 2024 | |
Comment |
Number of approved Island and Atoll Waste Management Plans | Value | 0.00 | 54.00 | 77.00 |
Date | June 30, 2017 | March 21, 2023 | December 31, 2024 | |
Comment |
Establishment of a system for monitoring operational compliance of licensed waste facilities by the Utility Regulatory Authority (URA). | Value | The URA has not yet approved any operating license | The URA has developed, tested, and shared a random | URA commences operational compliance monitoring wi |
Date | January 15, 2021 | August 1, 2023 | December 29, 2023 | |
Comment |
Number of resorts in zone 2 sending residual waste to Vandhoo | Value | 0.00 | 2.00 | 10.00 |
Date | August 31, 2020 | November 9, 2023 | December 31, 2024 | |
Comment |
Establishment of a system for monitoring environmental compliance by the EPA for pollution caused due to improper waste handling and management | Value | Electronic remote supervision monitoring forms for | The EPA has piloted and prepared its first inspect | EPA publicly discloses the results of environmenta |
Date | January 14, 2022 | November 9, 2023 | December 31, 2024 | |
Comment |
Establish Vandhoo as a stand-alone WAMCO budget centre along with a system for financial monitoring starting from July 1, 2022 | Value | There is no separation of accounts for Vandhoo wit | Agreements were reached on a system and process to | - First bi-annual audit (July-Dec 2022) and contin |
Date | January 14, 2022 | November 9, 2023 | December 31, 2024 | |
Comment |