Digitizing Implementation Monitoring and Public Procurement Project

Abstract*

The development objective of the Digitizing Implementation Monitoring and Public Procurement Project for Bangladesh is to improve public procurement performance and enhance capacity for implementation monitoring of development programs/projects. The project has four components that are summarized below. 1) The first component, Restructuring CPTU and Institutionalizing e-GP aims to restructure the CPTU in order to enhance its regulatory power and institutionalize...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve public procurement performance and enhance capacity for implementation monitoring of development programs/projects.

Key Details

Project Details

  • P160758

  • Closed

  • Nagaraju Duthaluri

  • People's Republic of Bangladesh

  • Bangladesh

  • March 2, 2017

  • (as of board presentation)

    July 28, 2017

  • October 8, 2017

  • US$ 60.00 million

  • Implementation Monitoring and Evaluation Division

  • South Asia

  • 2018

  • US$ 55.00 million

  • C

  • N/A

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • June 28, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrowing Agency 5.00
IDA Credit 55.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 55.00
IBRD + IDA Commitment 55.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 60.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 28, 2017 IDA-60770 Loan Commitment 55,000,000.00
Feb 5, 2021 IDA-68270 Loan Commitment 40,000,000.00
Dec 24, 2023 IDA-68270 Loan Cancel 12,763,181.00
Apr 28, 2024 IDA-60770 Loan Disb 641,913.60
Apr 28, 2024 IDA-60770 Loan Disb -641,913.60
Mar 1, 2024 IDA-68270 Int Charges 6.20
Mar 1, 2024 IDA-68270 Int Charges 6.20
Mar 1, 2024 IDA-60770 Loan Repay 38.42
Mar 1, 2024 IDA-60770 Loan Repay 774,154.00
Mar 1, 2024 IDA-60770 Int Charges 182,744.60
Mar 1, 2024 IDA-60770 Int Charges 182,744.60
Mar 1, 2024 IDA-68270 Int Charges 83,518.77
Mar 1, 2024 IDA-68270 Int Charges 83,518.77
Mar 1, 2024 IDA-68270 Int Charges 139,208.30
Sep 20, 2023 IDA-60770 Loan Disb 95,398.63
Sep 19, 2023 IDA-68270 Loan Disb 3,926,818.20
Sep 1, 2023 IDA-60770 Int Charges 814.48
Sep 1, 2023 IDA-60770 Int Charges 814.48
Sep 1, 2023 IDA-60770 Loan Repay 835,418.80
Sep 1, 2023 IDA-60770 Int Charges 185,564.64
Sep 1, 2023 IDA-60770 Int Charges 185,564.64
Sep 1, 2023 IDA-68270 Int Charges 59,486.91
Sep 1, 2023 IDA-68270 Int Charges 59,486.91
Sep 1, 2023 IDA-68270 Int Charges 99,144.89
Sep 1, 2023 IDA-68270 Int Charges 6,255.94
Oct 31, 2023 IDA-60770 Loan Disb 94,479.64
Oct 31, 2023 IDA-68270 Loan Disb 3,979,457.00
Dec 24, 2023 IDA-60770 Loan Cancel 3,767,218.50
Jan 31, 2023 IDA-60770 Loan Disb 631,300.00
Jan 30, 2023 IDA-68270 Loan Disb 3,541,700.00
Mar 22, 2023 IDA-60770 Loan Disb 492,156.88
Mar 1, 2023 IDA-68270 Int Charges 43,144.49
Mar 1, 2023 IDA-68270 Int Charges 65,633.43
Mar 1, 2023 IDA-68270 Int Charges 3,168.46
Mar 27, 2023 IDA-68270 Loan Disb 1,386,078.40
Mar 1, 2023 IDA-60770 Int Charges 3,186.11
Mar 1, 2023 IDA-60770 Int Charges 3,186.11
Mar 1, 2023 IDA-60770 Int Charges 178,448.48
Mar 1, 2023 IDA-60770 Int Charges 178,448.48
Mar 1, 2023 IDA-68270 Int Charges 43,144.49
Mar 1, 2022 IDA-60770 Int Charges 169,820.81
Mar 1, 2022 IDA-60770 Int Charges 169,820.81
Mar 1, 2022 IDA-68270 Int Charges 4,713.41
Mar 1, 2022 IDA-68270 Int Charges 4,713.41
Mar 1, 2022 IDA-68270 Int Charges 7,855.69
Mar 1, 2022 IDA-60770 Int Charges 64.44
Mar 1, 2022 IDA-60770 Int Charges 64.44
Jul 19, 2022 IDA-68270 Loan Disb 1,723,060.50
Dec 30, 2021 IDA-60770 Loan Disb 596,246.00
Dec 30, 2021 IDA-60770 Loan Disb 418,298.38
Sep 1, 2022 IDA-60770 Int Charges 172,017.80
Sep 1, 2022 IDA-60770 Int Charges 172,017.80
Sep 1, 2022 IDA-68270 Int Charges 43.71
Sep 1, 2022 IDA-68270 Int Charges 43.71
Sep 1, 2022 IDA-68270 Int Charges 16,669.20
Sep 1, 2022 IDA-68270 Int Charges 16,669.20
Sep 1, 2022 IDA-68270 Int Charges 24,762.33
Sep 1, 2022 IDA-60770 Int Charges 590.77
Sep 1, 2022 IDA-60770 Int Charges 590.77
Sep 13, 2022 IDA-60770 Loan Disb 358,105.25
Sep 13, 2022 IDA-68270 Loan Disb 4,877,684.00
Jun 22, 2021 IDA-60770 Loan Disb 440,587.00
Sep 22, 2021 IDA-60770 Loan Disb 829,267.00
Sep 1, 2021 IDA-60770 Int Charges 132,645.03
Sep 1, 2021 IDA-60770 Int Charges 132,645.03
Sep 1, 2021 IDA-60770 Int Charges 271.98
Sep 1, 2021 IDA-60770 Int Charges 271.98
Nov 24, 2021 IDA-68270 Loan Disb 2,331,002.20
Sep 14, 2021 IDA-60770 Loan Disb 7,375,704.00
Mar 7, 2022 IDA-60770 Loan Disb 754,022.00
May 31, 2022 IDA-60770 Loan Disb 562,125.00
Mar 29, 2022 IDA-60770 Loan Disb 1,809,164.80
Mar 29, 2022 IDA-68270 Loan Disb 2,360,324.80
Jul 20, 2022 IDA-60770 Loan Disb 606,705.70
Mar 1, 2021 IDA-60770 Int Charges 106,912.77
Mar 1, 2021 IDA-60770 Int Charges 106,912.77
Mar 1, 2021 IDA-60770 Int Charges 2,850.45
Mar 1, 2021 IDA-60770 Int Charges 2,850.45
Dec 21, 2020 IDA-60770 Loan Disb 1,641,863.20
Apr 6, 2021 IDA-60770 Loan Disb 5,532,193.50
Jun 7, 2021 IDA-60770 Loan Disb 2,873,113.20
Feb 6, 2020 IDA-60770 Loan Disb 2,165,980.00
Apr 23, 2020 IDA-60770 Loan Disb 1,415,903.00
Apr 20, 2020 IDA-60770 Loan Disb 4,666,980.50
Sep 1, 2020 IDA-60770 Int Charges 764.00
Sep 1, 2020 IDA-60770 Int Charges 764.00
Sep 1, 2020 IDA-60770 Int Charges 82,930.51
Sep 1, 2020 IDA-60770 Int Charges 82,930.51
Sep 16, 2020 IDA-60770 Loan Disb 1,585,967.00
Sep 14, 2020 IDA-60770 Loan Disb 1,641,391.50
Apr 24, 2019 IDA-60770 Loan Disb 1,223,236.50
Apr 29, 2019 IDA-60770 Loan Disb 1,057,380.00
Sep 1, 2019 IDA-60770 Int Charges 50,217.89
Sep 1, 2019 IDA-60770 Int Charges 50,217.89
Sep 1, 2019 IDA-60770 Int Charges 88.90
Sep 1, 2019 IDA-60770 Int Charges 88.90
Mar 1, 2020 IDA-60770 Int Charges 726.09
Mar 1, 2020 IDA-60770 Int Charges 726.09
Mar 1, 2020 IDA-60770 Int Charges 55,868.66
Mar 1, 2020 IDA-60770 Int Charges 55,868.66
Nov 5, 2019 IDA-60770 Loan Disb 1,327,197.60
Mar 1, 2018 IDA-60770 Int Charges 4,776.99
Nov 28, 2017 IDA-60770 Loan Disb 2,453,987.80
Sep 1, 2018 IDA-60770 Int Charges 63.40
Jun 26, 2018 IDA-60770 Loan Disb 1,979,689.40
Mar 27, 2018 IDA-60770 Loan Disb 440,091.62
Mar 1, 2018 IDA-60770 Int Charges 4,776.99
Sep 1, 2018 IDA-60770 Int Charges 63.40
Sep 1, 2018 IDA-60770 Int Charges 13,117.84
Sep 1, 2018 IDA-60770 Int Charges 13,117.84
Oct 16, 2018 IDA-60770 Loan Disb 1,863,126.50
Dec 4, 2018 IDA-60770 Loan Disb 2,492,650.00
Oct 19, 2018 IDA-60770 Loan Disb -2,492,650.00
Oct 17, 2018 IDA-60770 Loan Disb 2,492,650.00
Nov 15, 2018 IDA-60770 Loan Disb 2,880,381.50
Mar 1, 2019 IDA-60770 Int Charges 48.72
Mar 1, 2019 IDA-60770 Int Charges 48.72
Mar 1, 2019 IDA-60770 Int Charges 34,101.24
Mar 1, 2019 IDA-60770 Int Charges 34,101.24

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-01-24
Monitoring and Evaluation Satisfactory 2024-01-24
Project Management Satisfactory 2024-01-24
Counterpart Funding Satisfactory 2024-01-24
Progress towards achievement of PDO Moderately Satisfactory 2024-01-24
Procurement Satisfactory 2024-01-24
Overall Implementation Progress (IP) Moderately Satisfactory 2024-01-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2024
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-06-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • NSPSOs procurement lead time reduced in NCB using e-GP system (invitation to contract award)Value100.0054.0090.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • NSPSOs invite bids in National Competitive Bidding (NCB) through e-GP systemValue2.0096.0015.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • Selected sub-districts engage citizen monitoring in contract implementatiionValue4.0048.005.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • SPSOs’ projects implementation monitored on-line by IMEDValue0.00100.000.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • SPSOs conduct contract management using e-GP systemValue0.0012.000.00
    DateSeptember 30, 2020December 12, 2023
    Comment
  • Invitation of International Competitive Bidding (ICB) through e-GP systemValue0.0057.000.00
    DateSeptember 30, 2020December 12, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Draft bill establishing the proposed Authority and amending the PPA 2006 placed in ParliamentValueNoYesNo
    DateMarch 31, 2017August 22, 2023
    Comment
  • Procuring entities of NSPSOs have at least one trained/certified procurement professionalValue5.0075.0010.00
    DateMarch 31, 2017April 20, 2023
    Comment
  • IMED’s on-line project implementation monitoring module developedValueNoYesNo
    DateMarch 31, 2017April 20, 2023
    Comment
  • Government approved organogram with staffing of the proposed AuthorityValueNoNoNo
    DateMarch 31, 2017December 12, 2023
    Comment
  • Core procurement unit operationalized in each of the selected public sector organizations (SPSOs);Value0.0087.005.00
    DateMarch 31, 2017April 20, 2023
    Comment
  • e-contract magement module in e-GP system updatedValueNoYesYes
    DateMarch 31, 2017April 20, 2023
    Comment
  • Authority's officials in place compared with the staffing planValue0.000.000.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • Procurement professionalization/accreditation certificates issuedValue0.001079.000.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • e-GP system generated procurement performance reports of SPSOs published in CPTU/ Authority's websiteValue0.00100.0010.00
    DateMarch 31, 2017April 20, 2023
    Comment
  • Develop sustainable procurement policy and implementation roadmapValueNoYesNo
    DateSeptember 30, 2020October 23, 2023
    Comment
  • Open contracting module developed and made functionalValueNoYesNo
    DateMarch 31, 2017April 20, 2023
    Comment
  • e-GP module for international procurement under development partner funded projects developedValueNoYesNo
    DateSeptember 30, 2020April 20, 2023
    Comment
  • Citizen portal developed and made functionalValueNoYesNo
    DateMarch 31, 2017April 20, 2023
    Comment
  • e-GP modules for direct procurement and framework agreement developedValueNoYesNo
    DateSeptember 30, 2020April 20, 2023
    Comment
  • Develop mechanism to identify and track procurement performance of the women-led/owned enterprisesValueNoYesNo
    DateSeptember 30, 2020April 20, 2023
    Comment
  • Strengthen country’s emergency procurement and contract management frameworkValueNoNoNo
    DateSeptember 30, 2020December 12, 2023
    Comment
  • Disposal policy drafted and issuedValueNoNoNo
    DateMarch 31, 2017December 12, 2023
    Comment
  • Officials trained in reference to the training planValue0.0080.0010.00
    DateMarch 31, 2017April 20, 2023
    Comment
  • Female officials level of participation in trainingValue0.0024.925.00
    DateMarch 31, 2017December 12, 2023
    Comment
  • Officials trained on contract managementValue0.002617.000.00
    DateSeptember 30, 2020April 20, 2023
    Comment