Power Sector Recovery Project - Additional Financing

Development Objective

The Project Development Objective (PDO) is to improve the technical and commercial performance of the national power utility.

Key Details

Project Details

  • P160771

  • Closed

  • Yussuf Uwamahoro

  • N/A

  • Guinea

  • January 2, 2018

  • (as of board presentation)

    March 16, 2018

  • N/A

  • US$ 25.00 million

  • B

  • August 15, 2024

  • March 31, 2022

  • No

  • BANK APPROVED

  • P146696

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 25.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 25.00
IBRD + IDA Commitment 25.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 25.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue1400000.001800000.001850000.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Bill collection rateValue77.0081.0096.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    CommentAdjusted based on EDG
  • Average daily hours of serviceValue12.0015.0018.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Electricity losses per yearValue42.0035.0023.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    CommentTarget revised from 27% to 23% and end date extended by a year.
  • Female beneficiariesValue52.0052.0052.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • People provided with new or improved electricity serviceValue0.000.00318000.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Average interruption frequency per year in the project areaValue942.00700.00350.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • People provided with new or improved electricity service - FemaleValue0.000.00165360.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Operator appointedValueNoYesYes
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Number of substations refurbishedValue0.000.0067.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Technical auditor appointedValueNoYesYes
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Distribution lines constructed or rehabilitated under the projectValue0.000.0096.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Distribution lines rehabilitated under the projectValue0.000.0096.00
    DateMay 21, 2014August 25, 2017December 31, 2020
    Comment
  • Number of transformers installedValue0.000.0024.00
    DateAugust 25, 2017August 25, 2017December 31, 2020
    Comment
  • Beneficiary satisfaction survey completed, publishedValueNoNoYes
    DateAugust 25, 2017August 25, 2017December 31, 2020
    Comment
  • Number of meters installed, of which large consumer smart metersValue0.000.0057887.00
    DateAugust 25, 2017August 25, 2017December 31, 2020
    Comment
  • People provided with access to electricity services under the project by household connections â?? rehabilitation and standardization of household connections in Kaloum Ratoma and MatotoValue0.000.00216150.00
    DateAugust 25, 2017August 25, 2017December 31, 2020
    Comment
  • People provided with access to electricity services under the project by household connections â?? Rehabilitation and extension of Distribution network in DixinnValue0.000.0074178.00
    DateAugust 25, 2017August 25, 2017December 31, 2020
    Comment
  • Average number of hours of training per staff per yearValue0.000.0017.00
    DateAugust 25, 2017August 25, 2017December 31, 2020
    CommentResult of EDG staff training including industrial attachment