Bangladesh Municipal Water Supply and Sanitation Project

Abstract*

The development objective of Municipal Water Supply and Sanitation Project for Bangladesh is to increase access to improved water supply and sanitation services in selected municipalities, and strengthen the municipalities’ institutional capacities for delivering water and sanitation services. This project has five components. 1) The first component, Sector Support and Capacity Strengthening, comprises three subcomponents as follows: (i) Strengthening...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to increase access to improved water supply and sanitation services in selected municipalities, and strengthen the municipalities’ institutional capacities for delivering water and sanitation services.

Key Details

Project Details

  • P161227

  • Active

  • Arif Ahamed , Aroha Bahuguna

  • People's Republic of Bangladesh

  • Bangladesh

  • September 9, 2018

  • (as of board presentation)

    July 11, 2019

  • February 24, 2020

  • US$ 209.53 million

  • Department of Public Health Engineering

  • South Asia

  • 2020

  • US$ 200.00 million

  • B

  • March 10, 2024

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.00
Asian Infrastructure Investment Bank 100.00
Borrowing Agency 9.53

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 100.00
Total Project Cost** 209.53

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 24, 2020 IDA-64370 Loan Disb 1,518,650.40
Nov 15, 2020 IDA-64370 Int Charges 16,090.95
Nov 15, 2020 IDA-64370 Int Charges 16,090.95
Nov 15, 2020 IDA-64370 Int Charges 26,694.75
Nov 15, 2020 IDA-64370 Int Charges 4,576.76
Nov 15, 2020 IDA-64370 Int Charges 4,576.76
Nov 15, 2020 IDA-64370 Int Charges 7,627.93
May 15, 2021 IDA-64370 Int Charges 125.09
May 15, 2021 IDA-64370 Int Charges 28,660.60
May 15, 2021 IDA-64370 Int Charges 28,660.60
May 15, 2021 IDA-64370 Int Charges 38,155.29
Mar 23, 2021 IDA-64370 Loan Disb 3,134,487.50
Jun 7, 2021 IDA-64370 Loan Disb 1,002,425.40
Sep 13, 2021 IDA-64370 Loan Disb 1,990,610.40
Jul 11, 2019 IDA-64370 Loan Commitment 100,000,000.00
May 15, 2024 IDA-64370 Int Charges 303,715.80
May 15, 2024 IDA-64370 Int Charges 2,528.98
May 15, 2024 IDA-64370 Int Charges 183,755.44
May 15, 2024 IDA-64370 Int Charges 183,755.44
Jun 6, 2024 IDA-64370 Loan Disb 2,255,319.20
Feb 28, 2023 IDA-64370 Loan Disb 7,289,604.00
Jun 5, 2023 IDA-64370 Loan Disb 1,590,909.10
Aug 31, 2023 IDA-64370 Loan Disb 968,036.50
May 15, 2023 IDA-64370 Int Charges 6,693.82
May 15, 2023 IDA-64370 Int Charges 143,333.20
May 15, 2023 IDA-64370 Int Charges 143,333.20
May 15, 2023 IDA-64370 Int Charges 235,580.73
Nov 15, 2023 IDA-64370 Int Charges 164,009.92
Nov 15, 2023 IDA-64370 Int Charges 164,009.92
Nov 15, 2023 IDA-64370 Int Charges 270,815.10
Nov 15, 2023 IDA-64370 Int Charges 3,267.76
Dec 12, 2023 IDA-64370 Loan Disb 4,807,256.00
Jun 12, 2023 IDA-64370 Loan Cancel 10,582,591.00
Apr 29, 2024 IDA-64370 Loan Disb 6,263,636.50
Nov 8, 2021 IDA-64370 Loan Disb 3,957,993.00
Nov 15, 2021 IDA-64370 Int Charges 9,386.72
Nov 15, 2021 IDA-64370 Int Charges 42,830.84
Nov 15, 2021 IDA-64370 Int Charges 42,830.84
Nov 15, 2021 IDA-64370 Int Charges 71,384.69
Jun 16, 2022 IDA-64370 Loan Disb 5,749,387.50
Nov 15, 2022 IDA-64370 Int Charges 93,319.17
Nov 15, 2022 IDA-64370 Int Charges 159,941.61
Nov 15, 2022 IDA-64370 Int Charges 6,582.25
Nov 15, 2022 IDA-64370 Int Charges 6,582.25
Feb 26, 2020 IDA-64370 Loan Disb 1,005,072.70
Mar 23, 2020 IDA-64370 Loan Disb 2,501,471.50
Sep 3, 2020 IDA-64370 Loan Disb 1,514,053.00
May 15, 2022 IDA-64370 Int Charges 297.27
May 15, 2022 IDA-64370 Int Charges 297.27
May 15, 2022 IDA-64370 Int Charges 67,346.89
May 15, 2022 IDA-64370 Int Charges 67,346.89
May 15, 2022 IDA-64370 Int Charges 112,740.28
Mar 2, 2022 IDA-64370 Loan Disb 5,916,279.00
Nov 8, 2022 IDA-64370 Loan Disb 5,876,288.50
Sep 12, 2022 IDA-64370 Loan Disb 1,500,000.00
Nov 15, 2022 IDA-64370 Int Charges 93,319.17

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-12-15
Project Management Satisfactory 2024-12-15
Financial Management Moderately Satisfactory 2024-12-15
Progress towards achievement of PDO Moderately Satisfactory 2024-12-15
Procurement Satisfactory 2024-12-15
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to improved water sourcesValue0.0052257.00600000.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.00300000.00
    DateAugust 28, 2018December 31, 2023
    Comment
  • People provided with access to improved sanitation servicesValue600000.00611223.00680000.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • People provided with access to improved sanitation services - Female (RMS requirement)Value300000.000.00340000.00
    DateOctober 30, 2018December 31, 2023
    Comment
  • Number of municipalities scoring 50% and above in Performance Assessment ScorecardValue0.0030.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with operational water supply systemsValue0.003.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Participating municipalities with at least 80% cost recovery on operations and maintenanceValue0.000.0024.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with developed and approved sanitation action plansValue0.0018.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities maintaining Grievance Redressal Mechanism (GRM)Value0.0030.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with at least 50% improved toiletsValue0.005.0025.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities maintaining at least 30% attendance level of female members in Town Level Coordination CommitteesValue0.0028.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities supplying at least 11 hours per day of water to customersValue0.000.0020.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities maintaining separate WSS bank accountsValue0.0030.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with Public Toilets being operated by Private Operators/SHGsValue0.000.0020.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Percentage of beneficiaries expressing satisfaction over service provision (gender disaggregated)Value0.000.0055.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities supplying water of quality in compliance with Bangladesh standardsValue0.003.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with operational service contracts for emptyingValue0.000.0015.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities that have public toilets managed by women run Self-Help GroupsValue0.000.0010.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities that implement drainage improvements to manage storm water and wastewaterValue0.0030.0030.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment
  • Number of municipalities with women employed in various roles in Water and Sanitation service deliveryValue0.004.009.00
    DateJuly 11, 2019October 20, 2023December 31, 2024
    Comment