Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 10.00 |
P161234
Closed
Martin Maxwell Norman , Aguiratou Savadogo-Tinto, Michael Weber
N/A
January 18, 2018
(as of board presentation)
March 29, 2018
N/A
US$ 60.00 million
N/A
2018
US$ 50.00 million
A
Not Applicable
November 30, 2020
Yes
BANK APPROVED
July 13, 2023
Financier | Commitments |
---|---|
IDA Credit | 50.00 |
Borrower/Recipient | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 60.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Volume of cereal production (cereal and cereal crops, vegetable cultures, bananas, in the â??zone de concentrationâ??) | Value | 157867.00 | 160300.00 | 220000.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
of which percentage of female | Value | 0.00 | 0.00 | 28.00 |
Date | May 27, 2011 | November 30, 2018 | ||
Comment |
of which percentage of youth | Value | 0.00 | 0.00 | 28.00 |
Date | May 27, 2011 | November 30, 2018 | ||
Comment |
Value of investment flows | Value | 0.00 | 24700000.00 | 32000000.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Number of jobs created in the Project Area | Value | 0.00 | 25020.00 | 33000.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of proposals financed by the matching grants and cash grants fund | Value | 0.00 | 821.00 | 1600.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Beneficiaries satisfied with the matching grants and cash grants program (%) | Value | 0.00 | 65.30 | 80.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Operational water user associations created and/or strengthened | Value | 0.00 | 0.00 | 26.00 |
Date | June 23, 2017 | December 15, 2017 | November 30, 2018 | |
Comment |
Length of roads constructed (both paved and unpaved - km) | Value | 0.00 | 0.00 | 150.00 |
Date | May 31, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Changes to the matching grants / cash transfers activity as a result of consultations | Value | No | No | Yes |
Date | May 30, 2018 | December 15, 2017 | November 30, 2018 | |
Comment |
Beneficiaries satisfied with the roads constructed in the Project Area (%) | Value | 0.00 | 0.00 | 80.00 |
Date | May 30, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 30.00 |
Date | May 30, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Number of technical and feasibility studies for the establishment of the industrial park | Value | 0.00 | 0.00 | 2.00 |
Date | May 30, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Number of agribusiness firms having signed an agreement committing to invest in an area of at least 5ha | Value | 0.00 | 0.00 | 20.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Number of enterprises established | Value | 3.00 | 167.00 | 200.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Number of private service providers operating in Bagre | Value | 0.00 | 89.00 | 110.00 |
Date | May 27, 2011 | December 15, 2017 | November 30, 2018 | |
Comment |
Hectares of land allocated with land title or under a lease | Value | 0.00 | 0.00 | 300.00 |
Date | May 31, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Area provided with irrigation and drainage services (ha) | Value | 3380.00 | 3380.00 | 5574.00 |
Date | May 31, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |
Area of irrigated land in production with Project support | Value | 1880.00 | 1880.00 | 3380.00 |
Date | May 31, 2016 | December 15, 2017 | November 30, 2018 | |
Comment |