Skip to Main Navigation

Land Registration and Property Valuation Project

Abstract*

The development objective of the Land Registration and Property Valuation Project for Moldova is to improve the quality and transparency of the land administration and property valuation systems.The project consists of four components. 1) First Property Registration will support the first registration of public and private land in Moldova and strengthen the data quality for records already in the land register. This component will also organize mandatory...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the quality and transparency of the land administration and property valuation systems.

Key Details

Project Details

  • P161238

  • Active

  • Olivera Jordanovic

  • Republic of Moldova

  • Moldova

  • September 28, 2017

  • (as of board presentation)

    August 30, 2018

  • January 14, 2019

  • US$ 35.00 million

  • Public Institution Cadastre of Real Estate

  • Europe and Central Asia

  • 2019

  • US$ 28.11 million

  • B

  • Not Applicable

  • April 30, 2026

  • Yes

  • BANK APPROVED

  • April 15, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 28.11

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 28.11
IBRD + IDA Commitment 28.11
Lending Instrument
Grant Amount N/A
Total Project Cost** 35.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 24, 2022 IDA-63060 Loan Disb 396,880.00
Jan 15, 2022 IDA-63060 Int Charges 202.89
Jan 15, 2022 IDA-63060 Int Charges 4,240.32
Jan 15, 2022 IDA-63060 Int Charges 4,240.32
Jan 15, 2022 IDA-63060 Int Charges 3,019.25
Dec 2, 2022 IDA-63060 Loan Disb 526,875.00
Dec 21, 2021 IDA-63060 Loan Disb 45,140.00
Oct 13, 2022 IDA-63060 Loan Disb 437,625.00
Feb 28, 2020 IDA-63060 Loan Disb 54,114.96
Sep 5, 2019 IDA-63060 Loan Disb 82,920.00
Jan 15, 2020 IDA-63060 Int Charges 226.47
Jan 15, 2020 IDA-63060 Int Charges 226.47
Jan 15, 2020 IDA-63060 Int Charges 190.24
Mar 10, 2020 IDA-63060 Loan Disb 2,460.54
Jul 8, 2020 IDA-63060 Loan Disb 50,241.65
Sep 8, 2020 IDA-63060 Loan Disb 65,508.63
Nov 13, 2020 IDA-63060 Loan Disb 80,946.54
Dec 21, 2020 IDA-63060 Loan Disb 87,712.13
Jul 15, 2020 IDA-63060 Int Charges 496.36
Jul 15, 2020 IDA-63060 Int Charges 496.36
Jul 15, 2020 IDA-63060 Int Charges 403.25
Jan 15, 2021 IDA-63060 Int Charges 1,106.13
Jan 15, 2021 IDA-63060 Int Charges 1,106.13
Jan 15, 2021 IDA-63060 Int Charges 848.73
Jan 15, 2021 IDA-63060 Int Charges 14.50
Mar 10, 2021 IDA-63060 Loan Disb 59,786.56
Feb 8, 2021 IDA-63060 Loan Disb 55,004.91
Jul 13, 2021 IDA-63060 Loan Disb 190,530.62
Apr 30, 2021 IDA-63060 Loan Disb 12,080.00
May 11, 2021 IDA-63060 Loan Disb 77,047.18
Jun 2, 2021 IDA-63060 Loan Disb 121,745.00
Apr 9, 2021 IDA-63060 Loan Disb 56,848.77
Aug 30, 2018 IDA-63060 Loan Commitment 35,000,000.00
Jul 15, 2024 IDA-63060 Loan Repay 355,914.88
Jul 15, 2024 IDA-63060 Int Charges 37,954.92
Jul 15, 2024 IDA-63060 Int Charges 37,954.92
May 6, 2024 IDA-63060 Loan Disb 1,615,800.00
Jul 15, 2024 IDA-63060 Int Charges 31,882.12
Jul 15, 2024 IDA-63060 Loan Repay 69,837.04
Feb 2, 2023 IDA-63060 Loan Disb 879,920.00
May 5, 2023 IDA-63060 Loan Disb 1,102,500.00
Jan 15, 2023 IDA-63060 Int Charges 360.57
Jan 15, 2023 IDA-63060 Int Charges 11,609.84
Jan 15, 2023 IDA-63060 Int Charges 11,609.84
Jan 15, 2023 IDA-63060 Int Charges 8,861.18
Jul 7, 2023 IDA-63060 Loan Disb 1,089,300.00
Jul 15, 2023 IDA-63060 Int Charges 924.71
Jul 15, 2023 IDA-63060 Int Charges 19,810.77
Jul 15, 2023 IDA-63060 Int Charges 19,810.77
Jul 15, 2023 IDA-63060 Int Charges 16,296.99
Oct 4, 2023 IDA-63060 Loan Disb 1,575,600.00
Jan 15, 2024 IDA-63060 Int Charges 29,521.40
Jan 15, 2024 IDA-63060 Int Charges 29,521.40
Jan 15, 2024 IDA-63060 Int Charges 24,797.96
Jan 15, 2024 IDA-63060 Loan Repay 372,817.90
Jan 15, 2024 IDA-63060 Int Charges 335.65
Jan 15, 2024 IDA-63060 Loan Repay 54,319.36
Feb 16, 2024 IDA-63060 Loan Disb 1,616,700.00
Nov 18, 2021 IDA-63060 Loan Disb 226,880.00
Jul 15, 2021 IDA-63060 Int Charges 78.40
Jul 15, 2021 IDA-63060 Int Charges 2,303.27
Jul 15, 2021 IDA-63060 Int Charges 2,303.27
Jul 15, 2021 IDA-63060 Int Charges 1,725.39
Oct 14, 2021 IDA-63060 Loan Disb 169,050.77
Apr 26, 2022 IDA-63060 Loan Cancel 6,894,073.50
Apr 26, 2022 IDA-63060 Loan Disb 267,250.00
Jun 16, 2022 IDA-63060 Loan Disb 312,180.00
Jan 26, 2022 IDA-63060 Loan Disb 248,138.00
Jul 15, 2022 IDA-63060 Int Charges 476.60
Jul 15, 2022 IDA-63060 Int Charges 6,495.39
Jul 15, 2022 IDA-63060 Int Charges 6,495.39
Jul 15, 2022 IDA-63060 Int Charges 5,120.65
Mar 21, 2022 IDA-63060 Loan Disb 220,900.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2025-03-12
Project Management Moderately Unsatisfactory 2025-03-12
Monitoring and Evaluation Moderately Unsatisfactory 2025-03-12
Financial Management Satisfactory 2025-03-12
Procurement Satisfactory 2025-03-12
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-03-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of land in Moldova recorded in cadastre (private/public)Value84.0088.0493.50
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Land administration system information easily and widely accessibleValueLimited availabilityData available online and/or offlineData available online and/or offline
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Information on property values and property valuation methodologies easily and widely accessibleValueLimited availabilityAvailableData available online and/or offline
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of private land in Moldova recorded in cadastreValue85.0091.0095.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of private land in Moldova recorded in cadastreValue85.0091.0095.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of public land in Moldova recorded in cadastreValue7.0012.8952.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of urban residential and commercial properties revaluedValue0.000.0095.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of urban residential properties revaluedValue0.000.0095.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of urban commercial properties revaluedValue0.000.0095.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of customers satisfied with Cadastru servicesValue0.0085.0070.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment
  • Percentage of customers satisfied with Cadastru services - femaleValue0.0083.0070.00
    DateJanuary 1, 2019January 30, 2024June 28, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Cadastru ICT system to report gender-disaggregated property ownership data for policy and decision makingValueNoYesYes
    DateJanuary 1, 2019January 30, 2024January 1, 2024
    Comment
  • Percentage of land parcels with known errors for which the quality of data was improvedValue0.0013.2847.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment
  • Number of private land parcels registeredValue4700000.004898536.005100000.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment
  • Percentage of rural residential properties valued for the first timeValue0.000.0050.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment
  • Number of datasets in compliance with INSPIRE standardsValue0.000.003.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment
  • Percentage of local public authorities trained in supporting first property registrationValue0.0029.4030.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment
  • National valuation standards developedValueNoNoYes
    DateJanuary 1, 2019January 30, 2024January 1, 2024
    Comment
  • Percentage of Digital Archive completeValue25.0080.0085.00
    DateJanuary 1, 2019January 30, 2024January 1, 2024
    Comment
  • Number of private land parcels registered in women's namesValue2.16 million land parcelsNo target; indicator to be monitored
    DateJanuary 1, 2019January 1, 2024
    Comment
  • Number of public land parcels delineatedValue25000.0031226.00125000.00
    DateJanuary 1, 2019January 30, 2024June 30, 2024
    Comment