Financier | Commitments |
---|---|
Local Govts. (Prov., District, City) of Borrowing Country | 20.55 |
IDA Credit | 80.00 |
Pharmaceutical Governance Fund | 3.00 |
National Government | 0.70 |
Integrating Donor-Financed Health Programs | 5.00 |
P161283
Closed
Anh Nguyen , Huong Dao
Ministry of Finance
December 21, 2017
(as of board presentation)
June 19, 2019
May 18, 2020
US$ 109.25 million
Ninh Thuan Department of Health,Hoa Binh Department of Health,Yen Bai Department of Health,Son La Department of Health,Ha Giang Department of Health,Hau Giang Department of Health,Ministry of Health,Tra Vinh Department of Health,Long An Department of Health,Quang Binh Department of Health,Quang Tri Provincial Project Management Unit for Civil Works,Bac Lieu Department of Health,Bac Kan Department of Health,Quang Ngai Department of Health
2019
US$ 88.00 million
B
November 29, 2023
December 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Local Govts. (Prov., District, City) of Borrowing Country | 20.55 |
IDA Credit | 80.00 |
Pharmaceutical Governance Fund | 3.00 |
National Government | 0.70 |
Integrating Donor-Financed Health Programs | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 80.00 |
IBRD + IDA Commitment | 80.00 |
Lending Instrument | |
---|---|
Grant Amount | 8.00 |
Total Project Cost** | 109.25 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2020 | IDA-64390 | Int Charges | 107,650.27 |
Jun 23, 2021 | IDA-64390 | Loan Disb | 950,000.00 |
May 1, 2021 | IDA-64390 | Int Charges | 4,411.55 |
May 18, 2021 | IDA-64390 | Int Charges | 98,275.08 |
Jun 1, 2021 | IDA-64390 | Loan Disb | 800,000.00 |
Jun 1, 2021 | IDA-64390 | Loan Disb | 997,600.00 |
Jun 25, 2021 | IDA-64390 | Loan Disb | 493,000.00 |
Oct 4, 2021 | IDA-64390 | Loan Disb | 997,827.00 |
May 1, 2022 | IDA-64390 | Int Charges | 3,106.12 |
May 1, 2022 | IDA-64390 | Int Charges | 81,146.10 |
May 1, 2022 | IDA-64390 | Int Charges | 720.19 |
Apr 21, 2022 | IDA-64390 | Loan Disb | 529,441.90 |
Apr 21, 2022 | IDA-64390 | Loan Disb | 606,032.00 |
Jun 21, 2022 | IDA-64390 | Loan Disb | 179,611.00 |
Jun 17, 2022 | IDA-64390 | Loan Disb | 602,987.00 |
Jun 29, 2022 | IDA-64390 | Loan Disb | 134,315.00 |
Dec 16, 2021 | IDA-64390 | Loan Disb | 309,481.00 |
Dec 7, 2021 | IDA-64390 | Loan Disb | 630,459.00 |
Apr 27, 2022 | IDA-64390 | Loan Disb | 999,900.00 |
Dec 6, 2021 | IDA-64390 | Loan Disb | 572,000.00 |
Nov 16, 2023 | IDA-64390 | Loan Disb | 663,722.00 |
Nov 16, 2023 | IDA-64390 | Loan Disb | 886,000.00 |
Nov 20, 2023 | IDA-64390 | Loan Disb | 450,000.00 |
Jan 9, 2024 | IDA-64390 | Loan Disb | 709,446.00 |
Jan 9, 2024 | IDA-64390 | Loan Disb | 997,000.00 |
Jan 11, 2024 | IDA-64390 | Loan Disb | 998,315.00 |
Jan 2, 2024 | IDA-64390 | Loan Disb | 396,418.53 |
Nov 27, 2023 | IDA-64390 | Loan Disb | 977,000.00 |
Nov 1, 2023 | IDA-64390 | Int Charges | 546.96 |
Nov 1, 2023 | IDA-64390 | Int Charges | 12,829.01 |
Nov 1, 2023 | IDA-64390 | Int Charges | 1,358,869.90 |
Oct 6, 2023 | IDA-64390 | Loan Disb | 955,916.00 |
Oct 6, 2023 | IDA-64390 | Loan Disb | 777,376.00 |
Jul 25, 2024 | IDA-64390 | Loan Disb | 911,627.00 |
Feb 3, 2023 | IDA-64390 | Loan Disb | 370,000.00 |
Jan 22, 2024 | IDA-64390 | Loan Disb | 45,448.00 |
May 1, 2024 | IDA-64390 | Int Charges | 686.66 |
May 15, 2024 | IDA-64390 | Loan Disb | 982,765.00 |
Nov 1, 2022 | IDA-64390 | Int Charges | 310,192.78 |
Nov 1, 2022 | IDA-64390 | Int Charges | 267.10 |
Jan 9, 2023 | IDA-64390 | Loan Disb | 430,000.00 |
Dec 22, 2022 | IDA-64390 | Loan Disb | 860,000.00 |
Jan 10, 2023 | IDA-64390 | Loan Disb | 799,816.00 |
Oct 13, 2022 | IDA-64390 | Loan Disb | 72,134.00 |
Dec 13, 2022 | IDA-64390 | Loan Disb | 460,000.00 |
May 1, 2024 | IDA-64390 | Int Charges | 17,386.52 |
May 1, 2024 | IDA-64390 | Int Charges | 1,887,599.40 |
Jan 25, 2024 | IDA-64390 | Loan Disb | 998,250.00 |
Jul 16, 2024 | IDA-64390 | Loan Disb | 566,788.00 |
Apr 24, 2024 | IDA-64390 | Loan Disb | 722,587.00 |
Jul 16, 2024 | IDA-64390 | Loan Disb | 70,000.00 |
May 1, 2024 | IDA-64390 | Int Charges | 31,770.79 |
Jun 28, 2024 | IDA-64390 | Loan Disb | 999,215.00 |
Apr 8, 2024 | IDA-64390 | Loan Disb | 939,962.00 |
Nov 1, 2023 | IDA-64390 | Int Charges | 48,507.53 |
Aug 6, 2024 | IDA-64390 | Loan Disb | 988,286.00 |
Apr 23, 2024 | IDA-64390 | Loan Disb | 986,000.00 |
May 1, 2023 | IDA-64390 | Int Charges | 61,025.39 |
Jul 6, 2023 | IDA-64390 | Loan Disb | 820,000.00 |
Jul 6, 2023 | IDA-64390 | Loan Disb | 914,428.00 |
May 23, 2023 | IDA-64390 | Loan Disb | 1,000,000.00 |
Jun 7, 2023 | IDA-64390 | Loan Disb | 300,000.00 |
Oct 4, 2021 | IDA-64390 | Loan Disb | 897,841.00 |
Oct 22, 2021 | IDA-64390 | Loan Disb | 324,039.00 |
Oct 12, 2021 | IDA-64390 | Loan Disb | 843,560.00 |
Sep 2, 2021 | IDA-64390 | Loan Disb | 420,000.00 |
Apr 20, 2022 | IDA-64390 | Loan Disb | 998,000.00 |
May 4, 2022 | IDA-64390 | Loan Disb | 999,000.00 |
May 1, 2022 | IDA-64390 | Int Charges | 83,400.42 |
Jun 19, 2019 | IDA-64390 | Loan Commitment | 80,000,000.00 |
Jun 22, 2022 | IDA-64390 | Loan Disb | 592,000.00 |
Dec 22, 2021 | IDA-64390 | Loan Disb | 458.30 |
Apr 18, 2022 | IDA-64390 | Loan Disb | 974,000.00 |
Aug 23, 2022 | IDA-64390 | Loan Disb | 430,346.00 |
Aug 5, 2022 | IDA-64390 | Loan Disb | 350,000.00 |
Dec 23, 2022 | IDA-64390 | Loan Disb | 531,278.00 |
Dec 27, 2022 | IDA-64390 | Loan Disb | 955,509.10 |
Dec 30, 2022 | IDA-64390 | Loan Disb | 255,328.00 |
Dec 30, 2022 | IDA-64390 | Loan Disb | 281,804.00 |
Dec 30, 2022 | IDA-64390 | Loan Disb | 440,000.00 |
Sep 27, 2022 | IDA-64390 | Loan Disb | 337,861.22 |
Nov 14, 2022 | IDA-64390 | Loan Disb | 450,000.00 |
Oct 18, 2022 | IDA-64390 | Loan Disb | 971,000.00 |
Nov 1, 2022 | IDA-64390 | Int Charges | 1,130.21 |
Nov 30, 2021 | IDA-64390 | Loan Disb | 899,000.00 |
Nov 12, 2021 | IDA-64390 | Loan Disb | 359,394.00 |
Apr 25, 2023 | IDA-64390 | Loan Disb | 892,000.00 |
Mar 6, 2023 | IDA-64390 | Loan Disb | 990,000.00 |
Nov 1, 2022 | IDA-64390 | Int Charges | 74,521.32 |
May 1, 2023 | IDA-64390 | Int Charges | 373.17 |
May 1, 2023 | IDA-64390 | Int Charges | 4,091.48 |
May 1, 2023 | IDA-64390 | Int Charges | 919,648.40 |
Apr 11, 2023 | IDA-64390 | Loan Disb | 953,226.00 |
May 9, 2023 | IDA-64390 | Loan Disb | 600,277.00 |
May 16, 2023 | IDA-64390 | Loan Disb | 220,000.00 |
Dec 30, 2020 | IDA-64390 | Loan Disb | 165,500.00 |
Dec 15, 2020 | IDA-64390 | Fee Charges | 200,000.00 |
Dec 23, 2020 | IDA-64390 | Loan Disb | 450,000.00 |
Dec 28, 2020 | IDA-64390 | Loan Disb | 258,833.00 |
Dec 28, 2020 | IDA-64390 | Loan Disb | 65,992.00 |
Aug 15, 2024 | IDA-64390 | Loan Disb | 519,496.00 |
Jan 11, 2023 | IDA-64390 | Loan Disb | 402,461.00 |
Jan 11, 2023 | IDA-64390 | Loan Disb | 371,830.00 |
Jul 13, 2023 | IDA-64390 | Loan Disb | 840,000.00 |
Sep 1, 2023 | IDA-64390 | Loan Disb | 659,283.00 |
Jul 27, 2023 | IDA-64390 | Loan Disb | 750,000.00 |
Aug 22, 2023 | IDA-64390 | Loan Disb | 691,276.00 |
Aug 22, 2023 | IDA-64390 | Loan Disb | 45,420.18 |
Aug 18, 2023 | IDA-64390 | Loan Disb | 978,000.00 |
Nov 1, 2021 | IDA-64390 | Int Charges | 95,673.16 |
Aug 31, 2022 | IDA-64390 | Loan Disb | 629,804.00 |
Dec 28, 2021 | IDA-64390 | Loan Disb | 170,241.00 |
Jan 28, 2022 | IDA-64390 | Loan Disb | 600,000.00 |
Dec 23, 2021 | IDA-64390 | Loan Disb | 643,000.00 |
Jun 23, 2023 | IDA-64390 | Loan Disb | 742,993.00 |
Oct 17, 2023 | IDA-64390 | Loan Disb | 998,000.00 |
Dec 8, 2023 | IDA-64390 | Loan Disb | 603,000.00 |
Dec 13, 2023 | IDA-64390 | Loan Disb | 707,919.00 |
Dec 22, 2023 | IDA-64390 | Loan Disb | 533,467.00 |
Dec 26, 2023 | IDA-64390 | Loan Disb | 255,558.00 |
Dec 26, 2023 | IDA-64390 | Loan Disb | 584,000.00 |
Jul 27, 2021 | IDA-64390 | Loan Disb | 107,945.00 |
Dec 13, 2021 | IDA-64390 | Loan Disb | 748,900.00 |
Dec 15, 2021 | IDA-64390 | Loan Disb | 619,628.00 |
Dec 13, 2022 | IDA-64390 | Loan Disb | 997,752.00 |
Oct 31, 2022 | IDA-64390 | Loan Disb | 901,938.00 |
Oct 3, 2022 | IDA-64390 | Loan Disb | 923,867.00 |
May 2, 2023 | IDA-64390 | Loan Disb | 326,642.00 |
Nov 1, 2021 | IDA-64390 | Int Charges | 23,527.98 |
Oct 19, 2021 | IDA-64390 | Loan Disb | 520,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-12-09 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-09 |
Project Management | Satisfactory | 2024-12-09 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-09 |
Procurement | Satisfactory | 2024-12-09 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-09 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of CHS in the project provinces meeting national standards/benchmarks for structural quality | Value | 40.60 | 58.00 | 67.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of NCD cases screened or being managed at the CHS level in project provinces | Value | 429563.00 | 828234.00 | 802782.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of hypertension cases being managed at CHS level | Value | 168544.00 | 305301.00 | 419391.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of diabetes cases being managed at CHS level | Value | 43582.00 | 67719.00 | 76063.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of eligible women screened for cervical cancer at the CHS level | Value | 217437.00 | 455214.00 | 307328.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Percentage of project provinces maintaining a full immunization rate above 90% | Value | 92.30 | 38.00 | 100.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Population utilization rate of CHS in the project provinces | Value | 0.62 | 0.44 | 0.67 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of CHS built (new) or renovated with project support | Value | 0.00 | 263.00 | 461.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of CHS in the project provinces with the basic package of equipment needed to manage the tracer conditions (provided by theproject) | Value | 0.00 | 440.00 | 1100.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of districts in project provinces piloting at least one innovation | Value | 0.00 | 4.00 | 26.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of new CHS built | Value | 0.00 | 68.00 | 129.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services | Value | 10696722.00 | 10920490.00 | 11076722.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of CHS renovated | Value | 0.00 | 224.00 | 332.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement) | Value | 5214436.00 | 5291385.00 | 5291856.00 |
Date | ||||
Comment |
Number of children immunized | Value | 190221.00 | 152478.00 | 210221.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of health professionals at CHS level who have received in-service training (through the project) on the management of the tracer conditions. | Value | 0.00 | 6193.00 | 7000.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of women and children who have received basic nutrition services | Value | 6493338.00 | 6395849.00 | 6725838.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of CHS in the project provinces authorized by the provincial DOH and provincial VSS to manage at least one of the new NCD tracer conditions (hypertension or diabetes) in the project provinces | Value | 1764.00 | 1692.00 | 1699.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of deliveries attended by skilled health personnel | Value | 160452.00 | 127752.00 | 190452.00 |
Date | December 31, 2019 | October 31, 2023 | November 30, 2024 | |
Comment |
Percentage of CHS using quality monitoring and management practices (in the form of a quality scorecard) | Value | 0.00 | 39.00 | 25.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
The number of Provincial Project Management Units, who perform satisfactorily, based on the evaluation score | Value | 0.00 | 10.00 | 10.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |
Number of community people were publicly consulted before project interventions | Value | 0.00 | 6590.00 | 4500.00 |
Date | December 31, 2019 | October 31, 2023 | December 31, 2024 | |
Comment |