Skip to Main Navigation

Republic of Azerbaijan: NSDS, Including Detailed Institution, Human and ICT Capacity Building Plans for 2017-2022

Development Objective

The objective of the grant is to support the State Statistical Committee of the Republic of Azerbaijan in the preparation of: (i) a new long-term National Strategy for the Development of Statistics for 2018-2030 (NSDS); (ii) supplemental mid-term (2018-2022) action plans; and (iii) capacity building of the SSC staff in order to make them ready for implementation of these action plans.

Key Details

Project Details

  • P161307

  • Closed

  • Cesar Cancho

  • State Statistical Committee of the Republic of Azerbaijan

  • Azerbaijan

  • August 8, 2016

  • (as of board presentation)

    February 20, 2017

  • July 21, 2017

  • US$ 0.25 million

  • State Statistical Committee of the Republic of Azerbaijan

  • Europe and Central Asia

  • 2017

  • US$ 0.25 million

  • N/A

  • Not Applicable

  • December 31, 2019

  • BANK APPROVED

  • October 5, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Trust Fund for Statistical Capacity Building 0.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.25
Total Project Cost** 0.25

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2018-04-13
Overall Implementation Progress (IP) Moderately Satisfactory 2018-04-13
Overall Satisfactory 2018-04-13

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-23-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Completion of the new NSDS covering 2018-2030.Valuethere is no NSDScompletedcompleted
    DateFebruary 28, 2017June 29, 2018December 31, 2019
    Comment
  • Three costed out action plans (for 2018-2022) with timetables prepared and accpeted by the SSCValuethere are no action planscompleted7 multi-annual action plans
    DateFebruary 28, 2017June 29, 2018December 31, 2019
    Comment
  • Improve capacity of key SSC staff in implementation of specific action plans.Valuenot startedcompletedcompleted
    DateFebruary 28, 2017June 29, 2018December 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Due to a simple project desing and short implemenation period, no intermediate indicators are neededValuen/an/an/a
    DateNovember 11, 2017June 29, 2018November 10, 2017
    Comment