Renewable Energy Sector Development Project

Abstract*

The development objective of the Renewable Energy Sector Development Project for Saint Lucia is to inform the Government of Saint Lucia on the viability of its geothermal resource for power generation and strengthen the enabling environment to scale-up clean energy investments with the private sector. The project comprises of two components. The first component, geothermal exploration drilling program will finance following sub-components: (i) exploration...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective is to inform the Government of Saint Lucia on the viability of its geothermal resource for power generation and strengthen the enabling environment to scale-up clean energy investments with the private sector.

Key Details

Project Details

  • P161316

  • Active

  • Neha Mukhi

  • Saint Lucia

  • St. Lucia

  • May 30, 2017

  • (as of board presentation)

    July 28, 2021

  • July 29, 2022

  • US$ 21.86 million

  • Ministry of Infrastructure, Port, Transport, Physical Development and Urban Renewal (MIPTPDUR)

  • Latin America and Caribbean

  • 2022

  • US$ 20.86 million

  • B

  • May 10, 2024

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Free-standing Single Purpose Trust Fund 4.20
Gender Trust Funds 0.55
IDA Credit 3.83
Borrower/Recipient 1.00
Clean Technology Fund 8.57
Canada Clean Energy and Forest Climate Facility Trust Fund 3.71

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 3.83
IBRD + IDA Commitment 3.83
Lending Instrument
Grant Amount 17.03
Total Project Cost** 21.86

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 6, 2023 IDA-69710 Loan Disb 246,999.94
Jul 28, 2021 IDA-69710 Loan Commitment 3,830,000.00
Sep 18, 2023 IDA-69710 Int Charges 2,981.28
Nov 9, 2023 IDA-69710 Loan Disb 320,966.97
Mar 15, 2024 IDA-69710 Int Charges 5,902.99
Mar 15, 2024 IDA-69710 Int Charges 5,902.99
Feb 22, 2024 IDA-69710 Loan Disb 384,848.00
Jan 22, 2024 IDA-69710 Loan Disb 132,726.31
Aug 10, 2022 IDA-69710 Loan Disb 290,000.00
Mar 24, 2023 IDA-69710 Int Charges 437.02
Mar 24, 2023 IDA-69710 Int Charges 437.02
Mar 24, 2023 IDA-69710 Int Charges 2,247.50
Mar 24, 2023 IDA-69710 Int Charges 2,247.50
Jul 28, 2021 TF-B6751 Loan Commitment 3,710,000.00
Sep 18, 2023 IDA-69710 Int Charges 2,981.28

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2025-02-28
Monitoring and Evaluation Satisfactory 2025-02-28
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-28
Progress towards achievement of PDO Moderately Satisfactory 2025-02-28
Financial Management Moderately Satisfactory 2025-02-28
Overall Safeguards Rating Satisfactory 2025-02-28
Procurement Moderately Satisfactory 2025-02-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Determination made by GoSL whether to pursue delineation drillingValueNoNoYes
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment
  • Legal and regulatory framework for clean energy investments in Saint Lucia finalized with GovernmentValue0.0020.00100.00
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Exploration Management Consultant (EMC) hiredValueNoYesYes
    DateMay 7, 2021June 29, 2023June 29, 2022
    Comment
  • Number of draft laws prepared and presented to ParliamentValue0.000.002.00
    DateApril 26, 2018March 26, 2024April 25, 2024
    Comment
  • Drilling Program design finalizedValue0.0090.00100.00
    DateMay 13, 2021March 26, 2024June 30, 2025
    Comment
  • Number of energy sector regulations finalizedValue0.000.004.00
    DateApril 8, 2021March 26, 2024July 31, 2025
    Comment
  • Drilling Contractor hiredValueNoNoYes
    DateMay 7, 2021March 26, 2024December 30, 2022
    Comment
  • Citizens reporting satisfaction with consultation processValue0.0096.0090.00
    DateFebruary 28, 2019March 26, 2024February 28, 2024
    Comment
  • Project safeguard documentation updated based on final design, consulted and disclosedValue0.000.00100.00
    DateMay 13, 2021March 26, 2024June 30, 2025
    Comment
  • Share of women who participated in consultationsValue0.0032.0050.00
    DateJuly 18, 2018March 26, 2024June 30, 2025
    Comment
  • Progress in land acquisitionValue0.000.00100.00
    DateMay 10, 2021March 26, 2024December 30, 2022
    Comment
  • Changes to project activities as a result of citizen feedbackValue0.000.005.00
    DateJuly 18, 2018March 26, 2024June 30, 2025
    Comment
  • Progress in infrastructure civil works required for the drilling programValue0.000.00100.00
    DateMay 10, 2021March 26, 2024March 29, 2024
    Comment
  • Percent of registered project related grievances responded to within stipulated service standards for response timesValue0.00100.0090.00
    DateJuly 13, 2018March 26, 2024February 28, 2024
    Comment
  • Geothermal exploration wells drilled and testedValue0.000.003.00
    DateJuly 3, 2017March 26, 2024June 30, 2024
    Comment
  • Market sounding conducted related to the future commercial development of geothermal resourcesValueNoNoYes
    DateMay 10, 2021March 26, 2024June 30, 2025
    Comment
  • Drilling Report provided to the GoSLValueNoNoYes
    DateMay 11, 2021March 26, 2024June 30, 2025
    Comment
  • Number of capacity enhancement activities (trainings, workshops, etc.) completedValue0.007.005.00
    DateJuly 31, 2018March 26, 2024April 30, 2024
    Comment
  • Resource Capacity Report finalizedValueNoNoYes
    DateMay 18, 2021March 26, 2024June 30, 2025
    Comment
  • Scholarships provided for female students to pursue electrical or mechanical engineering degreesValue0.0017.0016.00
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment
  • Interim Feasibility Study provided to the GoSLValueNoNoYes
    DateMay 11, 2021March 26, 2024June 30, 2025
    Comment
  • Apprenticeships provided for female students in STEM fieldValue0.003.0020.00
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment
  • Female beneficiaries successfully employed in technical positions within the first year of completing scholarship and apprenticeship programsValue0.0020.0060.00
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment
  • Geothermal resource potential for power generation confirmed through exploration drillingValue0.000.0030.00
    DateFebruary 28, 2019March 26, 2024July 28, 2025
    Comment
  • Female employees in the GoSL Electrical Inspectorate (MoIPEL)Value15.0020.0030.00
    DateMay 7, 2021March 26, 2024June 30, 2025
    Comment
  • Expected annual CO2 emissions reductionsValue0.000.0076941.00
    DateApril 8, 2021March 26, 2024July 31, 2025
    Comment
  • Number of studies conducted on direct use / productive uses for geothermal resourcesValue0.000.002.00
    DateApril 15, 2021March 26, 2024July 31, 2025
    Comment
  • Volume of indirect financing catalyzed by CTF financingValue0.000.00151500000.00
    DateNovember 25, 2018March 26, 2024June 30, 2024
    Comment
  • Female participation on direct use / productive use outreach eventsValue0.000.0050.00
    DateApril 15, 2021March 26, 2024July 31, 2025
    Comment
  • Jobs createdValue0.008.0090.00
    DateMay 18, 2021March 26, 2024June 30, 2025
    Comment
  • Permanent positionsValue0.002.0032.00
    DateJune 14, 2021March 26, 2024June 30, 2025
    Comment
  • Jobs held by womenValue0.003.0022.00
    DateJune 14, 2021March 26, 2024June 30, 2025
    Comment