Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 4.20 |
Gender Trust Funds | 0.55 |
IDA Credit | 3.83 |
Borrower/Recipient | 1.00 |
Clean Technology Fund | 8.57 |
Canada Clean Energy and Forest Climate Facility Trust Fund | 3.71 |
P161316
Active
Neha Mukhi
Saint Lucia
May 30, 2017
(as of board presentation)
July 28, 2021
July 29, 2022
US$ 21.86 million
Ministry of Infrastructure, Port, Transport, Physical Development and Urban Renewal (MIPTPDUR)
2022
US$ 20.86 million
B
May 10, 2024
December 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 4.20 |
Gender Trust Funds | 0.55 |
IDA Credit | 3.83 |
Borrower/Recipient | 1.00 |
Clean Technology Fund | 8.57 |
Canada Clean Energy and Forest Climate Facility Trust Fund | 3.71 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 3.83 |
IBRD + IDA Commitment | 3.83 |
Lending Instrument | |
---|---|
Grant Amount | 17.03 |
Total Project Cost** | 21.86 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 6, 2023 | IDA-69710 | Loan Disb | 246,999.94 |
Jul 28, 2021 | IDA-69710 | Loan Commitment | 3,830,000.00 |
Sep 18, 2023 | IDA-69710 | Int Charges | 2,981.28 |
Nov 9, 2023 | IDA-69710 | Loan Disb | 320,966.97 |
Mar 15, 2024 | IDA-69710 | Int Charges | 5,902.99 |
Mar 15, 2024 | IDA-69710 | Int Charges | 5,902.99 |
Feb 22, 2024 | IDA-69710 | Loan Disb | 384,848.00 |
Jan 22, 2024 | IDA-69710 | Loan Disb | 132,726.31 |
Aug 10, 2022 | IDA-69710 | Loan Disb | 290,000.00 |
Mar 24, 2023 | IDA-69710 | Int Charges | 437.02 |
Mar 24, 2023 | IDA-69710 | Int Charges | 437.02 |
Mar 24, 2023 | IDA-69710 | Int Charges | 2,247.50 |
Mar 24, 2023 | IDA-69710 | Int Charges | 2,247.50 |
Jul 28, 2021 | TF-B6751 | Loan Commitment | 3,710,000.00 |
Sep 18, 2023 | IDA-69710 | Int Charges | 2,981.28 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2025-02-28 |
Monitoring and Evaluation | Satisfactory | 2025-02-28 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-28 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-02-28 |
Financial Management | Moderately Satisfactory | 2025-02-28 |
Overall Safeguards Rating | Satisfactory | 2025-02-28 |
Procurement | Moderately Satisfactory | 2025-02-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Determination made by GoSL whether to pursue delineation drilling | Value | No | No | Yes |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Legal and regulatory framework for clean energy investments in Saint Lucia finalized with Government | Value | 0.00 | 20.00 | 100.00 |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Exploration Management Consultant (EMC) hired | Value | No | Yes | Yes |
Date | May 7, 2021 | June 29, 2023 | June 29, 2022 | |
Comment |
Number of draft laws prepared and presented to Parliament | Value | 0.00 | 0.00 | 2.00 |
Date | April 26, 2018 | March 26, 2024 | April 25, 2024 | |
Comment |
Drilling Program design finalized | Value | 0.00 | 90.00 | 100.00 |
Date | May 13, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Number of energy sector regulations finalized | Value | 0.00 | 0.00 | 4.00 |
Date | April 8, 2021 | March 26, 2024 | July 31, 2025 | |
Comment |
Drilling Contractor hired | Value | No | No | Yes |
Date | May 7, 2021 | March 26, 2024 | December 30, 2022 | |
Comment |
Citizens reporting satisfaction with consultation process | Value | 0.00 | 96.00 | 90.00 |
Date | February 28, 2019 | March 26, 2024 | February 28, 2024 | |
Comment |
Project safeguard documentation updated based on final design, consulted and disclosed | Value | 0.00 | 0.00 | 100.00 |
Date | May 13, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Share of women who participated in consultations | Value | 0.00 | 32.00 | 50.00 |
Date | July 18, 2018 | March 26, 2024 | June 30, 2025 | |
Comment |
Progress in land acquisition | Value | 0.00 | 0.00 | 100.00 |
Date | May 10, 2021 | March 26, 2024 | December 30, 2022 | |
Comment |
Changes to project activities as a result of citizen feedback | Value | 0.00 | 0.00 | 5.00 |
Date | July 18, 2018 | March 26, 2024 | June 30, 2025 | |
Comment |
Progress in infrastructure civil works required for the drilling program | Value | 0.00 | 0.00 | 100.00 |
Date | May 10, 2021 | March 26, 2024 | March 29, 2024 | |
Comment |
Percent of registered project related grievances responded to within stipulated service standards for response times | Value | 0.00 | 100.00 | 90.00 |
Date | July 13, 2018 | March 26, 2024 | February 28, 2024 | |
Comment |
Geothermal exploration wells drilled and tested | Value | 0.00 | 0.00 | 3.00 |
Date | July 3, 2017 | March 26, 2024 | June 30, 2024 | |
Comment |
Market sounding conducted related to the future commercial development of geothermal resources | Value | No | No | Yes |
Date | May 10, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Drilling Report provided to the GoSL | Value | No | No | Yes |
Date | May 11, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Number of capacity enhancement activities (trainings, workshops, etc.) completed | Value | 0.00 | 7.00 | 5.00 |
Date | July 31, 2018 | March 26, 2024 | April 30, 2024 | |
Comment |
Resource Capacity Report finalized | Value | No | No | Yes |
Date | May 18, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Scholarships provided for female students to pursue electrical or mechanical engineering degrees | Value | 0.00 | 17.00 | 16.00 |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Interim Feasibility Study provided to the GoSL | Value | No | No | Yes |
Date | May 11, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Apprenticeships provided for female students in STEM field | Value | 0.00 | 3.00 | 20.00 |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Female beneficiaries successfully employed in technical positions within the first year of completing scholarship and apprenticeship programs | Value | 0.00 | 20.00 | 60.00 |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Geothermal resource potential for power generation confirmed through exploration drilling | Value | 0.00 | 0.00 | 30.00 |
Date | February 28, 2019 | March 26, 2024 | July 28, 2025 | |
Comment |
Female employees in the GoSL Electrical Inspectorate (MoIPEL) | Value | 15.00 | 20.00 | 30.00 |
Date | May 7, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Expected annual CO2 emissions reductions | Value | 0.00 | 0.00 | 76941.00 |
Date | April 8, 2021 | March 26, 2024 | July 31, 2025 | |
Comment |
Number of studies conducted on direct use / productive uses for geothermal resources | Value | 0.00 | 0.00 | 2.00 |
Date | April 15, 2021 | March 26, 2024 | July 31, 2025 | |
Comment |
Volume of indirect financing catalyzed by CTF financing | Value | 0.00 | 0.00 | 151500000.00 |
Date | November 25, 2018 | March 26, 2024 | June 30, 2024 | |
Comment |
Female participation on direct use / productive use outreach events | Value | 0.00 | 0.00 | 50.00 |
Date | April 15, 2021 | March 26, 2024 | July 31, 2025 | |
Comment |
Jobs created | Value | 0.00 | 8.00 | 90.00 |
Date | May 18, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Permanent positions | Value | 0.00 | 2.00 | 32.00 |
Date | June 14, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |
Jobs held by women | Value | 0.00 | 3.00 | 22.00 |
Date | June 14, 2021 | March 26, 2024 | June 30, 2025 | |
Comment |