Financier | Commitments |
---|---|
IDA Grant | 15.00 |
P161320
Closed
Ifeta Smajic
Solomon Islands Ministry of Finance and Treasury
January 28, 2018
(as of board presentation)
April 2, 2018
July 17, 2018
US$ 15.00 million
Ministry of Infrastructure Development,Honiara City Council
2018
US$ 15.00 million
B
May 9, 2024
October 31, 2024
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 4, 2020 | IDA-D2920 | Loan Disb | 10,443.48 |
May 4, 2020 | IDA-D2920 | Loan Disb | 8,448.00 |
Apr 6, 2020 | IDA-D2920 | Loan Disb | 10,503.98 |
Apr 3, 2020 | IDA-D2920 | Loan Disb | 401,074.84 |
Mar 3, 2020 | IDA-D2920 | Loan Disb | 12,123.56 |
Dec 3, 2019 | IDA-D2920 | Loan Disb | 12,163.80 |
Dec 19, 2019 | IDA-D2920 | Loan Disb | 6,097.30 |
Mar 2, 2020 | IDA-D2920 | Loan Disb | 10,202.51 |
Jan 23, 2020 | IDA-D2920 | Loan Disb | 486,175.12 |
Apr 8, 2020 | IDA-D2920 | Loan Disb | 9,869.20 |
Dec 27, 2019 | IDA-D2920 | Loan Disb | 169,126.45 |
Dec 23, 2019 | IDA-D2920 | Loan Disb | 7,321.84 |
Aug 3, 2020 | IDA-D2920 | Loan Disb | 12,157.77 |
Aug 3, 2020 | IDA-D2920 | Loan Disb | 8,189.67 |
Aug 19, 2020 | IDA-D2920 | Loan Disb | 471,698.25 |
Sep 1, 2020 | IDA-D2920 | Loan Disb | 9,081.60 |
Sep 2, 2020 | IDA-D2920 | Loan Disb | 11,366.83 |
Jul 1, 2020 | IDA-D2920 | Loan Disb | 8,870.40 |
Jun 19, 2020 | IDA-D2920 | Loan Disb | 417,053.94 |
Sep 10, 2018 | IDA-D2920 | Loan Disb | 10,503.98 |
Oct 24, 2018 | IDA-D2920 | Loan Disb | 142,471.11 |
Feb 26, 2019 | IDA-D2920 | Loan Disb | 25,478.42 |
Nov 6, 2018 | IDA-D2920 | Loan Disb | 11,582.54 |
Nov 6, 2018 | IDA-D2920 | Loan Disb | 12,857.90 |
Feb 19, 2019 | IDA-D2920 | Loan Disb | 8,761.65 |
Feb 26, 2019 | IDA-D2920 | Loan Disb | 152,594.58 |
Feb 27, 2019 | IDA-D2920 | Loan Disb | 141,770.23 |
Dec 18, 2018 | IDA-D2920 | Loan Disb | 71,168.88 |
Oct 9, 2018 | IDA-D2920 | Loan Disb | 10,803.00 |
Dec 27, 2018 | IDA-D2920 | Loan Disb | 5,071.01 |
Dec 27, 2018 | IDA-D2920 | Loan Disb | 4,801.72 |
Dec 4, 2018 | IDA-D2920 | Loan Disb | 11,952.60 |
Dec 4, 2018 | IDA-D2920 | Loan Disb | 11,881.56 |
Dec 7, 2018 | IDA-D2920 | Loan Disb | 177,535.90 |
Oct 9, 2018 | IDA-D2920 | Loan Disb | 11,952.61 |
Sep 7, 2018 | IDA-D2920 | Loan Disb | 12,857.91 |
Aug 10, 2018 | IDA-D2920 | Loan Disb | 8,148.80 |
Aug 15, 2018 | IDA-D2920 | Loan Disb | 252,400.02 |
Aug 2, 2021 | IDA-D2920 | Loan Disb | 4,435.21 |
Nov 16, 2021 | IDA-D2920 | Loan Disb | 264,321.53 |
Dec 3, 2021 | IDA-D2920 | Loan Disb | 11,306.33 |
Jun 8, 2022 | IDA-D2920 | Loan Disb | 7,509.52 |
Mar 2, 2022 | IDA-D2920 | Loan Disb | 6,770.00 |
Aug 18, 2022 | IDA-D2920 | Loan Disb | 147,654.90 |
Apr 4, 2022 | IDA-D2920 | Loan Disb | 5,600.00 |
Apr 4, 2022 | IDA-D2920 | Loan Disb | 11,366.83 |
Dec 8, 2021 | IDA-D2920 | Loan Disb | 9,200.00 |
Mar 14, 2022 | IDA-D2920 | Loan Disb | 263,689.97 |
Mar 22, 2022 | IDA-D2920 | Loan Disb | 206,176.06 |
Feb 4, 2022 | IDA-D2920 | Loan Disb | 10,180.41 |
Mar 1, 2022 | IDA-D2920 | Loan Disb | 10,592.12 |
Jan 7, 2022 | IDA-D2920 | Loan Disb | 485,355.28 |
Feb 3, 2022 | IDA-D2920 | Loan Disb | 10,873.76 |
Jan 18, 2022 | IDA-D2920 | Loan Disb | 10,180.41 |
Jan 4, 2022 | IDA-D2920 | Loan Disb | 10,415.00 |
Jun 5, 2020 | IDA-D2920 | Loan Disb | 10,503.97 |
Jun 5, 2020 | IDA-D2920 | Loan Disb | 9,926.41 |
Jun 3, 2020 | IDA-D2920 | Loan Disb | 439,703.97 |
Mar 2, 2021 | IDA-D2920 | Loan Disb | 13,874.99 |
Sep 21, 2020 | IDA-D2920 | Loan Disb | 478,283.03 |
Jul 6, 2020 | IDA-D2920 | Loan Disb | 10,443.48 |
Oct 1, 2020 | IDA-D2920 | Loan Disb | 11,306.33 |
Oct 1, 2020 | IDA-D2920 | Loan Disb | 9,715.20 |
Nov 16, 2020 | IDA-D2920 | Loan Disb | 557,054.44 |
Nov 2, 2020 | IDA-D2920 | Loan Disb | 11,366.83 |
Nov 2, 2020 | IDA-D2920 | Loan Disb | 10,560.00 |
Mar 16, 2021 | IDA-D2920 | Loan Disb | 467,073.25 |
Dec 21, 2020 | IDA-D2920 | Loan Disb | 11,366.83 |
Dec 21, 2020 | IDA-D2920 | Loan Disb | 6,336.00 |
Dec 21, 2020 | IDA-D2920 | Loan Disb | 352,283.62 |
Feb 2, 2021 | IDA-D2920 | Loan Disb | 11,366.84 |
Feb 2, 2021 | IDA-D2920 | Loan Disb | 9,292.79 |
Feb 11, 2021 | IDA-D2920 | Loan Disb | 424,054.60 |
Mar 1, 2021 | IDA-D2920 | Loan Disb | 6,969.60 |
Mar 1, 2021 | IDA-D2920 | Loan Disb | 11,185.33 |
Apr 7, 2021 | IDA-D2920 | Loan Disb | 11,366.83 |
Jun 14, 2021 | IDA-D2920 | Loan Disb | 235,583.05 |
May 3, 2021 | IDA-D2920 | Loan Disb | 11,306.33 |
Jun 3, 2021 | IDA-D2920 | Loan Disb | 11,015.01 |
Jun 3, 2021 | IDA-D2920 | Loan Disb | 4,012.81 |
May 3, 2021 | IDA-D2920 | Loan Disb | 3,590.40 |
May 3, 2021 | IDA-D2920 | Loan Disb | 11,675.10 |
Jul 1, 2021 | IDA-D2920 | Loan Disb | 11,306.33 |
Jul 1, 2021 | IDA-D2920 | Loan Disb | 9,200.00 |
Jul 1, 2021 | IDA-D2920 | Loan Disb | 4,224.00 |
Jul 14, 2021 | IDA-D2920 | Loan Disb | 315,443.50 |
May 19, 2021 | IDA-D2920 | Loan Disb | 543,554.20 |
Apr 6, 2021 | IDA-D2920 | Loan Disb | 3,379.20 |
Jul 21, 2021 | IDA-D2920 | Loan Disb | 548,454.00 |
Dec 1, 2020 | IDA-D2920 | Loan Disb | 9,503.99 |
Dec 1, 2020 | IDA-D2920 | Loan Disb | 11,306.33 |
Mar 5, 2021 | IDA-D2920 | Loan Disb | 506,000.00 |
Nov 8, 2021 | IDA-D2920 | Loan Disb | 5,718.11 |
Aug 13, 2021 | IDA-D2920 | Loan Disb | 356,262.00 |
Aug 10, 2021 | IDA-D2920 | Loan Disb | 6,081.11 |
Nov 4, 2021 | IDA-D2920 | Loan Disb | 10,890.00 |
May 3, 2019 | IDA-D2920 | Loan Disb | 10,443.48 |
Feb 19, 2019 | IDA-D2920 | Loan Disb | 5,161.20 |
May 13, 2019 | IDA-D2920 | Loan Disb | 397,140.34 |
Mar 8, 2019 | IDA-D2920 | Loan Disb | 9,603.44 |
Jul 2, 2019 | IDA-D2920 | Loan Disb | 9,603.44 |
Jul 2, 2019 | IDA-D2920 | Loan Disb | 11,831.59 |
Feb 27, 2020 | IDA-D2920 | Loan Disb | 413,152.44 |
Feb 4, 2020 | IDA-D2920 | Loan Disb | 6,580.21 |
Feb 26, 2019 | IDA-D2920 | Loan Disb | 40.83 |
Sep 3, 2019 | IDA-D2920 | Loan Disb | 12,857.90 |
Sep 30, 2019 | IDA-D2920 | Loan Disb | 9,542.94 |
Oct 24, 2019 | IDA-D2920 | Loan Disb | 481,329.66 |
Nov 1, 2019 | IDA-D2920 | Loan Disb | 12,857.89 |
Sep 11, 2019 | IDA-D2920 | Loan Disb | 10,503.98 |
Oct 2, 2019 | IDA-D2920 | Loan Disb | 11,530.20 |
Aug 30, 2019 | IDA-D2920 | Loan Disb | 566,883.25 |
Aug 2, 2019 | IDA-D2920 | Loan Disb | 5,516.84 |
Aug 2, 2019 | IDA-D2920 | Loan Disb | 10,503.99 |
Apr 2, 2018 | IDA-D2920 | Loan Commitment | 15,000,000.00 |
Oct 4, 2023 | IDA-D2920 | Loan Disb | 139,681.20 |
Apr 9, 2024 | IDA-D2920 | Loan Disb | 50,444.98 |
Sep 7, 2021 | IDA-D2920 | Loan Disb | 11,314.99 |
Oct 1, 2021 | IDA-D2920 | Loan Disb | 11,350.01 |
Oct 1, 2021 | IDA-D2920 | Loan Disb | 4,745.66 |
Sep 21, 2021 | IDA-D2920 | Loan Disb | 292,875.97 |
Jun 1, 2021 | IDA-D2920 | Loan Disb | 11,366.84 |
Apr 7, 2021 | IDA-D2920 | Loan Disb | 11,615.00 |
Jun 7, 2022 | IDA-D2920 | Loan Disb | 9,755.00 |
May 5, 2022 | IDA-D2920 | Loan Disb | 10,515.38 |
May 6, 2022 | IDA-D2920 | Loan Disb | 7,440.00 |
Nov 10, 2021 | IDA-D2920 | Loan Disb | 285,559.12 |
Sep 14, 2021 | IDA-D2920 | Loan Disb | 4,745.66 |
Aug 2, 2021 | IDA-D2920 | Loan Disb | 9,199.99 |
Aug 23, 2018 | IDA-D2920 | Loan Disb | 3,899.45 |
Jan 24, 2019 | IDA-D2920 | Loan Disb | 168,244.78 |
Dec 3, 2019 | IDA-D2920 | Loan Disb | 10,443.48 |
Jun 21, 2019 | IDA-D2920 | Loan Disb | 555,471.80 |
Mar 14, 2019 | IDA-D2920 | Loan Disb | 190,934.64 |
Mar 14, 2019 | IDA-D2920 | Loan Disb | 498,000.00 |
Jun 19, 2019 | IDA-D2920 | Loan Disb | 75,581.99 |
Apr 16, 2019 | IDA-D2920 | Loan Disb | 9,425.41 |
Apr 16, 2019 | IDA-D2920 | Loan Disb | 12,435.51 |
Jun 14, 2019 | IDA-D2920 | Loan Disb | 12,435.50 |
Jun 14, 2019 | IDA-D2920 | Loan Disb | 4,200.20 |
Feb 26, 2019 | IDA-D2920 | Loan Disb | 244.55 |
Mar 4, 2019 | IDA-D2920 | Loan Disb | 11,409.21 |
May 3, 2019 | IDA-D2920 | Loan Disb | 5,920.50 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Highly Satisfactory | 2024-10-31 |
Financial Management | Moderately Satisfactory | 2024-10-31 |
Monitoring and Evaluation | Satisfactory | 2024-10-31 |
Procurement | Satisfactory | 2024-10-31 |
Project Management | Satisfactory | 2024-10-31 |
Overall Implementation Progress (IP) | Satisfactory | 2024-10-31 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Households in project areas benefiting from improved access to infrastructure, services or markets | Value | 0.00 | 18100.00 | 18000.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Individuals from project areas reporting improved access to infrastructure, services or markets | Value | 0.00 | 82.80 | 75.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Youth (aged between 16 and 29 years) from project areas reporting improved access to infrastructure, services or markets | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Women from project areas reporting improved access to infrastructure, services or markets | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Beneficiaries of job-focused interventions | Value | 0.00 | 8345.00 | 8400.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Beneficiaries of job-focused interventions - Female | Value | 0.00 | 0.00 | 4200.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Youth that are engaged in works or training activities | Value | 0.00 | 4256.00 | 4200.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Beneficiaries from poor communities ranked as “highest priority” in the vulnerability index | Value | 0.00 | 59.71 | 50.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Beneficiaries reporting that project investments reflected their needs | Value | 0.00 | 96.70 | 70.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Community access infrastructure constructed | Value | 0.00 | 209.00 | 212.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Cumulative length of roads restored and maintained annually (km X years) (Kilometers) | Value | 0.00 | 99.57 | 83.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Individuals trained under the ISDT | Value | 0.00 | 8857.00 | 8400.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Grievances resolved within three months | Value | 0.00 | 100.00 | 100.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Community members reporting that the infrastructure improved pedestrian safety | Value | 0.00 | 95.00 | 80.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Financial progress of road restoration and maintenance (USD) (Number) | Value | 0.00 | 2818355.00 | 3200000.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Of which youth | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Number of labor days generated (under Components 1 & 2) | Value | 0.00 | 360187.00 | 370000.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Length of roads improved to climate resilient standards (Kilometers) | Value | 0.00 | 17.88 | 14.10 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Of which women | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Cumulative expenditure on spot improvement works (USD) (Number) | Value | 0.00 | 2111590.00 | 2200000.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Trainees that are assessed as successfully completing the training | Value | 0.00 | 93.00 | 80.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Of which youth | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Trainees that expressed satisfaction with knowledge and skills received from ISDT | Value | 0.00 | 93.00 | 80.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Of which women | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Volume of waste collected | Value | 0.00 | 64138.00 | 78000.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
New bank accounts opened or reactivated as result of the project | Value | 0.00 | 1571.00 | 2700.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
New bank accounts opened or reactivated as result of the project by women | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |
Trainees that accessed post training support services (Number) | Value | 0.00 | 6074.00 | 2500.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Participants who acquire Level-I literacy skills | Value | 0.00 | 840.00 | 850.00 |
Date | April 30, 2018 | March 31, 2024 | October 31, 2024 | |
Comment |
Women who acquire Level-I literacy skills | Value | 0.00 | 0.00 | 50.00 |
Date | April 30, 2018 | May 21, 2018 | March 1, 2022 | |
Comment |