Abstract*

The development objective of the Community Access and Urban Services Enhancement Project for Solomon Islands is to improve basic infrastructure and services for vulnerable urban populations in targeted urban centers of the recipient. The project comprises of four components. The first component, urban works and services, includes activities of engagement of community groups and contractors through community grants and contracts to build basic transport...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve basic infrastructure and services for vulnerable urban populations in targeted urban centers of the Recipient.

Key Details

Project Details

  • P161320

  • Closed

  • Ifeta Smajic

  • Solomon Islands Ministry of Finance and Treasury

  • Solomon Islands

  • January 28, 2018

  • (as of board presentation)

    April 2, 2018

  • July 17, 2018

  • US$ 15.00 million

  • Ministry of Infrastructure Development,Honiara City Council

  • East Asia and Pacific

  • 2018

  • US$ 15.00 million

  • B

  • May 9, 2024

  • October 31, 2024

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.00
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 15.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 4, 2020 IDA-D2920 Loan Disb 10,443.48
May 4, 2020 IDA-D2920 Loan Disb 8,448.00
Apr 6, 2020 IDA-D2920 Loan Disb 10,503.98
Apr 3, 2020 IDA-D2920 Loan Disb 401,074.84
Mar 3, 2020 IDA-D2920 Loan Disb 12,123.56
Dec 3, 2019 IDA-D2920 Loan Disb 12,163.80
Dec 19, 2019 IDA-D2920 Loan Disb 6,097.30
Mar 2, 2020 IDA-D2920 Loan Disb 10,202.51
Jan 23, 2020 IDA-D2920 Loan Disb 486,175.12
Apr 8, 2020 IDA-D2920 Loan Disb 9,869.20
Dec 27, 2019 IDA-D2920 Loan Disb 169,126.45
Dec 23, 2019 IDA-D2920 Loan Disb 7,321.84
Aug 3, 2020 IDA-D2920 Loan Disb 12,157.77
Aug 3, 2020 IDA-D2920 Loan Disb 8,189.67
Aug 19, 2020 IDA-D2920 Loan Disb 471,698.25
Sep 1, 2020 IDA-D2920 Loan Disb 9,081.60
Sep 2, 2020 IDA-D2920 Loan Disb 11,366.83
Jul 1, 2020 IDA-D2920 Loan Disb 8,870.40
Jun 19, 2020 IDA-D2920 Loan Disb 417,053.94
Sep 10, 2018 IDA-D2920 Loan Disb 10,503.98
Oct 24, 2018 IDA-D2920 Loan Disb 142,471.11
Feb 26, 2019 IDA-D2920 Loan Disb 25,478.42
Nov 6, 2018 IDA-D2920 Loan Disb 11,582.54
Nov 6, 2018 IDA-D2920 Loan Disb 12,857.90
Feb 19, 2019 IDA-D2920 Loan Disb 8,761.65
Feb 26, 2019 IDA-D2920 Loan Disb 152,594.58
Feb 27, 2019 IDA-D2920 Loan Disb 141,770.23
Dec 18, 2018 IDA-D2920 Loan Disb 71,168.88
Oct 9, 2018 IDA-D2920 Loan Disb 10,803.00
Dec 27, 2018 IDA-D2920 Loan Disb 5,071.01
Dec 27, 2018 IDA-D2920 Loan Disb 4,801.72
Dec 4, 2018 IDA-D2920 Loan Disb 11,952.60
Dec 4, 2018 IDA-D2920 Loan Disb 11,881.56
Dec 7, 2018 IDA-D2920 Loan Disb 177,535.90
Oct 9, 2018 IDA-D2920 Loan Disb 11,952.61
Sep 7, 2018 IDA-D2920 Loan Disb 12,857.91
Aug 10, 2018 IDA-D2920 Loan Disb 8,148.80
Aug 15, 2018 IDA-D2920 Loan Disb 252,400.02
Aug 2, 2021 IDA-D2920 Loan Disb 4,435.21
Nov 16, 2021 IDA-D2920 Loan Disb 264,321.53
Dec 3, 2021 IDA-D2920 Loan Disb 11,306.33
Jun 8, 2022 IDA-D2920 Loan Disb 7,509.52
Mar 2, 2022 IDA-D2920 Loan Disb 6,770.00
Aug 18, 2022 IDA-D2920 Loan Disb 147,654.90
Apr 4, 2022 IDA-D2920 Loan Disb 5,600.00
Apr 4, 2022 IDA-D2920 Loan Disb 11,366.83
Dec 8, 2021 IDA-D2920 Loan Disb 9,200.00
Mar 14, 2022 IDA-D2920 Loan Disb 263,689.97
Mar 22, 2022 IDA-D2920 Loan Disb 206,176.06
Feb 4, 2022 IDA-D2920 Loan Disb 10,180.41
Mar 1, 2022 IDA-D2920 Loan Disb 10,592.12
Jan 7, 2022 IDA-D2920 Loan Disb 485,355.28
Feb 3, 2022 IDA-D2920 Loan Disb 10,873.76
Jan 18, 2022 IDA-D2920 Loan Disb 10,180.41
Jan 4, 2022 IDA-D2920 Loan Disb 10,415.00
Jun 5, 2020 IDA-D2920 Loan Disb 10,503.97
Jun 5, 2020 IDA-D2920 Loan Disb 9,926.41
Jun 3, 2020 IDA-D2920 Loan Disb 439,703.97
Mar 2, 2021 IDA-D2920 Loan Disb 13,874.99
Sep 21, 2020 IDA-D2920 Loan Disb 478,283.03
Jul 6, 2020 IDA-D2920 Loan Disb 10,443.48
Oct 1, 2020 IDA-D2920 Loan Disb 11,306.33
Oct 1, 2020 IDA-D2920 Loan Disb 9,715.20
Nov 16, 2020 IDA-D2920 Loan Disb 557,054.44
Nov 2, 2020 IDA-D2920 Loan Disb 11,366.83
Nov 2, 2020 IDA-D2920 Loan Disb 10,560.00
Mar 16, 2021 IDA-D2920 Loan Disb 467,073.25
Dec 21, 2020 IDA-D2920 Loan Disb 11,366.83
Dec 21, 2020 IDA-D2920 Loan Disb 6,336.00
Dec 21, 2020 IDA-D2920 Loan Disb 352,283.62
Feb 2, 2021 IDA-D2920 Loan Disb 11,366.84
Feb 2, 2021 IDA-D2920 Loan Disb 9,292.79
Feb 11, 2021 IDA-D2920 Loan Disb 424,054.60
Mar 1, 2021 IDA-D2920 Loan Disb 6,969.60
Mar 1, 2021 IDA-D2920 Loan Disb 11,185.33
Apr 7, 2021 IDA-D2920 Loan Disb 11,366.83
Jun 14, 2021 IDA-D2920 Loan Disb 235,583.05
May 3, 2021 IDA-D2920 Loan Disb 11,306.33
Jun 3, 2021 IDA-D2920 Loan Disb 11,015.01
Jun 3, 2021 IDA-D2920 Loan Disb 4,012.81
May 3, 2021 IDA-D2920 Loan Disb 3,590.40
May 3, 2021 IDA-D2920 Loan Disb 11,675.10
Jul 1, 2021 IDA-D2920 Loan Disb 11,306.33
Jul 1, 2021 IDA-D2920 Loan Disb 9,200.00
Jul 1, 2021 IDA-D2920 Loan Disb 4,224.00
Jul 14, 2021 IDA-D2920 Loan Disb 315,443.50
May 19, 2021 IDA-D2920 Loan Disb 543,554.20
Apr 6, 2021 IDA-D2920 Loan Disb 3,379.20
Jul 21, 2021 IDA-D2920 Loan Disb 548,454.00
Dec 1, 2020 IDA-D2920 Loan Disb 9,503.99
Dec 1, 2020 IDA-D2920 Loan Disb 11,306.33
Mar 5, 2021 IDA-D2920 Loan Disb 506,000.00
Nov 8, 2021 IDA-D2920 Loan Disb 5,718.11
Aug 13, 2021 IDA-D2920 Loan Disb 356,262.00
Aug 10, 2021 IDA-D2920 Loan Disb 6,081.11
Nov 4, 2021 IDA-D2920 Loan Disb 10,890.00
May 3, 2019 IDA-D2920 Loan Disb 10,443.48
Feb 19, 2019 IDA-D2920 Loan Disb 5,161.20
May 13, 2019 IDA-D2920 Loan Disb 397,140.34
Mar 8, 2019 IDA-D2920 Loan Disb 9,603.44
Jul 2, 2019 IDA-D2920 Loan Disb 9,603.44
Jul 2, 2019 IDA-D2920 Loan Disb 11,831.59
Feb 27, 2020 IDA-D2920 Loan Disb 413,152.44
Feb 4, 2020 IDA-D2920 Loan Disb 6,580.21
Feb 26, 2019 IDA-D2920 Loan Disb 40.83
Sep 3, 2019 IDA-D2920 Loan Disb 12,857.90
Sep 30, 2019 IDA-D2920 Loan Disb 9,542.94
Oct 24, 2019 IDA-D2920 Loan Disb 481,329.66
Nov 1, 2019 IDA-D2920 Loan Disb 12,857.89
Sep 11, 2019 IDA-D2920 Loan Disb 10,503.98
Oct 2, 2019 IDA-D2920 Loan Disb 11,530.20
Aug 30, 2019 IDA-D2920 Loan Disb 566,883.25
Aug 2, 2019 IDA-D2920 Loan Disb 5,516.84
Aug 2, 2019 IDA-D2920 Loan Disb 10,503.99
Apr 2, 2018 IDA-D2920 Loan Commitment 15,000,000.00
Oct 4, 2023 IDA-D2920 Loan Disb 139,681.20
Apr 9, 2024 IDA-D2920 Loan Disb 50,444.98
Sep 7, 2021 IDA-D2920 Loan Disb 11,314.99
Oct 1, 2021 IDA-D2920 Loan Disb 11,350.01
Oct 1, 2021 IDA-D2920 Loan Disb 4,745.66
Sep 21, 2021 IDA-D2920 Loan Disb 292,875.97
Jun 1, 2021 IDA-D2920 Loan Disb 11,366.84
Apr 7, 2021 IDA-D2920 Loan Disb 11,615.00
Jun 7, 2022 IDA-D2920 Loan Disb 9,755.00
May 5, 2022 IDA-D2920 Loan Disb 10,515.38
May 6, 2022 IDA-D2920 Loan Disb 7,440.00
Nov 10, 2021 IDA-D2920 Loan Disb 285,559.12
Sep 14, 2021 IDA-D2920 Loan Disb 4,745.66
Aug 2, 2021 IDA-D2920 Loan Disb 9,199.99
Aug 23, 2018 IDA-D2920 Loan Disb 3,899.45
Jan 24, 2019 IDA-D2920 Loan Disb 168,244.78
Dec 3, 2019 IDA-D2920 Loan Disb 10,443.48
Jun 21, 2019 IDA-D2920 Loan Disb 555,471.80
Mar 14, 2019 IDA-D2920 Loan Disb 190,934.64
Mar 14, 2019 IDA-D2920 Loan Disb 498,000.00
Jun 19, 2019 IDA-D2920 Loan Disb 75,581.99
Apr 16, 2019 IDA-D2920 Loan Disb 9,425.41
Apr 16, 2019 IDA-D2920 Loan Disb 12,435.51
Jun 14, 2019 IDA-D2920 Loan Disb 12,435.50
Jun 14, 2019 IDA-D2920 Loan Disb 4,200.20
Feb 26, 2019 IDA-D2920 Loan Disb 244.55
Mar 4, 2019 IDA-D2920 Loan Disb 11,409.21
May 3, 2019 IDA-D2920 Loan Disb 5,920.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Highly Satisfactory 2024-10-31
Financial Management Moderately Satisfactory 2024-10-31
Monitoring and Evaluation Satisfactory 2024-10-31
Procurement Satisfactory 2024-10-31
Project Management Satisfactory 2024-10-31
Overall Implementation Progress (IP) Satisfactory 2024-10-31

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Households in project areas benefiting from improved access to infrastructure, services or marketsValue0.0018100.0018000.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Individuals from project areas reporting improved access to infrastructure, services or marketsValue0.0082.8075.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Youth (aged between 16 and 29 years) from project areas reporting improved access to infrastructure, services or marketsValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Women from project areas reporting improved access to infrastructure, services or marketsValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Beneficiaries of job-focused interventionsValue0.008345.008400.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Beneficiaries of job-focused interventions - FemaleValue0.000.004200.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Youth that are engaged in works or training activitiesValue0.004256.004200.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Beneficiaries from poor communities ranked as “highest priority” in the vulnerability indexValue0.0059.7150.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Beneficiaries reporting that project investments reflected their needsValue0.0096.7070.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Community access infrastructure constructedValue0.00209.00212.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Cumulative length of roads restored and maintained annually (km X years) (Kilometers)Value0.0099.5783.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Individuals trained under the ISDTValue0.008857.008400.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Grievances resolved within three monthsValue0.00100.00100.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Community members reporting that the infrastructure improved pedestrian safetyValue0.0095.0080.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Financial progress of road restoration and maintenance (USD) (Number)Value0.002818355.003200000.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Of which youthValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Number of labor days generated (under Components 1 & 2)Value0.00360187.00370000.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Length of roads improved to climate resilient standards (Kilometers)Value0.0017.8814.10
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Of which womenValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Cumulative expenditure on spot improvement works (USD) (Number)Value0.002111590.002200000.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Trainees that are assessed as successfully completing the trainingValue0.0093.0080.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Of which youthValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Trainees that expressed satisfaction with knowledge and skills received from ISDTValue0.0093.0080.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Of which womenValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Volume of waste collectedValue0.0064138.0078000.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • New bank accounts opened or reactivated as result of the projectValue0.001571.002700.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • New bank accounts opened or reactivated as result of the project by womenValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment
  • Trainees that accessed post training support services (Number)Value0.006074.002500.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Participants who acquire Level-I literacy skillsValue0.00840.00850.00
    DateApril 30, 2018March 31, 2024October 31, 2024
    Comment
  • Women who acquire Level-I literacy skillsValue0.000.0050.00
    DateApril 30, 2018May 21, 2018March 1, 2022
    Comment