Malawi Resilience and Disaster Risk Management Project

Abstract*

The development objective of Drought Recovery and Resilience Project for Malawi is to support the government of Malawi to meet the immediate food security and livelihoods restoration needs of the communities affected by drought and promote recovery and resilience in key affected sectors. This project has four components. 1) The first component, Improving Food Security and Sustainable Livelihoods, aims to improve agricultural productivity, enhance...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Support the recovery of livelihoods and infrastructure in flood and drought affected areas and strengthen capacity for flood and drought risk management

Key Details

Project Details

  • P161392

  • Closed

  • Arati Belle

  • Government of Malawi, Ministry of Finance, Economic Planning and Development

  • Malawi

  • September 23, 2016

  • (as of board presentation)

    November 8, 2016

  • January 18, 2017

  • US$ 104.00 million

  • Ministry of Irrigation and Water Development

  • Eastern and Southern Africa

  • 2017

  • US$ 104.00 million

  • B

  • May 6, 2024

  • January 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 104.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 104.00
IBRD + IDA Commitment 104.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 104.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 19, 2023 IDA-65680 Loan Disb 394,372.00
Sep 6, 2023 IDA-65680 Loan Disb 158,177.98
Sep 19, 2023 IDA-65680 Loan Disb 634,278.80
Aug 25, 2023 IDA-65680 Loan Disb 147,428.75
Aug 24, 2023 IDA-65680 Loan Disb 233,608.77
Sep 5, 2023 IDA-65680 Loan Disb 122,029.69
Jun 9, 2023 IDA-65680 Loan Disb 130,209.23
Nov 30, 2023 IDA-65680 Loan Disb 244,059.38
Oct 10, 2023 IDA-65680 Loan Disb 276,314.66
Nov 17, 2023 IDA-65680 Loan Disb 539,709.60
Apr 18, 2024 IDA-65680 Loan Disb 381,531.03
Aug 12, 2024 IDA-65680 Int Charges 7,845.74
Aug 12, 2024 IDA-65680 Int Charges 7,845.74
Aug 12, 2024 IDA-65680 Int Charges 140,991.34
Aug 12, 2024 IDA-65680 Int Charges 140,991.34
Oct 4, 2023 IDA-65680 Loan Disb 186,696.31
Dec 15, 2023 IDA-65680 Loan Disb 8,467,941.00
May 22, 2024 IDA-65680 Loan Disb 103,000.00
Feb 6, 2024 IDA-65680 Int Charges 831.23
Feb 6, 2024 IDA-65680 Int Charges 831.23
Feb 6, 2024 IDA-65680 Int Charges 102,282.04
Feb 6, 2024 IDA-65680 Int Charges 102,282.04
Jul 26, 2018 IDA-D1440 Loan Disb 356,328.00
May 10, 2018 IDA-D1440 Loan Disb 486,791.97
Sep 26, 2018 IDA-D1440 Loan Disb 897,114.80
Nov 2, 2018 IDA-D1440 Loan Disb 2,443,468.00
Mar 14, 2018 IDA-D1440 Loan Disb 163,938.31
Mar 21, 2019 IDA-D1440 Loan Disb 6,385,311.50
Apr 26, 2019 IDA-D1440 Loan Disb 3,907,904.00
Aug 9, 2022 IDA-65680 Int Charges 27,222.35
Aug 9, 2022 IDA-65680 Int Charges 27,222.35
Feb 10, 2022 IDA-65680 Int Charges 21,500.59
Feb 10, 2022 IDA-65680 Int Charges 21,500.59
Apr 19, 2023 IDA-65680 Loan Disb 255,383.27
Feb 2, 2023 IDA-65680 Int Charges 36,518.32
Feb 2, 2023 IDA-65680 Int Charges 36,518.32
Feb 1, 2023 IDA-65680 Int Charges 408.57
Feb 1, 2023 IDA-65680 Int Charges 408.57
Dec 12, 2022 IDA-65680 Loan Disb 333,827.16
Aug 2, 2023 IDA-65680 Int Charges 92,514.48
Aug 2, 2023 IDA-65680 Int Charges 92,514.48
Aug 2, 2023 IDA-65680 Int Charges 9,392.22
Aug 2, 2023 IDA-65680 Int Charges 9,392.22
Aug 1, 2023 IDA-65680 Loan Disb 630,694.56
Mar 31, 2023 IDA-65680 Loan Disb 140,165.23
May 31, 2022 IDA-65680 Loan Disb 3,404,926.00
Jul 8, 2022 IDA-65680 Loan Disb 381,372.28
Dec 15, 2021 IDA-65680 Loan Disb 408,860.80
Mar 14, 2022 IDA-65680 Loan Disb 220,086.39
Jan 4, 2023 IDA-65680 Loan Disb 14,252,739.00
Feb 1, 2022 IDA-65680 Int Charges 298.88
Feb 1, 2022 IDA-65680 Int Charges 298.88
Aug 9, 2022 IDA-65680 Int Charges 434.12
Aug 9, 2022 IDA-65680 Int Charges 434.12
Feb 11, 2021 IDA-65680 Loan Disb 5,857,968.00
Aug 6, 2021 IDA-65680 Int Charges 20,485.90
Aug 6, 2021 IDA-65680 Int Charges 20,485.90
Sep 22, 2021 IDA-65680 Loan Disb 183,219.78
Oct 13, 2023 IDA-D1440 Loan Disb 356,842.25
May 28, 2020 IDA-D1440 Loan Disb 245,693.88
Aug 6, 2020 IDA-D1440 Loan Disb 109,636.89
Aug 6, 2020 IDA-D1440 Loan Disb 199,115.86
Jan 27, 2021 IDA-D1440 Loan Disb 2,393,688.00
Sep 21, 2020 IDA-D1440 Loan Disb 4,241,656.00
Jul 24, 2020 IDA-D1440 Loan Disb 207,414.30
Sep 8, 2020 IDA-D1440 Loan Disb 219,721.89
Jul 16, 2019 IDA-D1440 Loan Disb 535,264.40
Sep 30, 2019 IDA-D1440 Loan Disb 262,199.06
Sep 30, 2019 IDA-D1440 Loan Disb 275,479.47
May 20, 2019 IDA-D1440 Loan Disb 10,335,958.00
Apr 16, 2019 IDA-D1440 Loan Disb 190,649.98
Apr 8, 2020 IDA-D1440 Loan Disb 292,932.34
Sep 8, 2020 IDA-D1440 Loan Disb 183,031.40
Aug 31, 2020 IDA-D1440 Loan Disb 125,665.01
Aug 28, 2020 IDA-D1440 Loan Disb 125,168.11
Jun 24, 2020 IDA-D1440 Loan Disb 155,017.42
Mar 21, 2018 IDA-D1440 Loan Disb 2,093,143.00
Feb 6, 2018 IDA-D1440 Loan Disb 86,365.80
Feb 6, 2018 IDA-D1440 Loan Disb 73,723.50
Mar 22, 2018 IDA-D1440 Loan Disb 784,770.60
Aug 2, 2018 IDA-D1440 Loan Disb 276,800.00
Aug 30, 2018 IDA-D1440 Loan Disb 265,670.38
May 3, 2017 IDA-D1440 Loan Disb 2,642,674.00
Apr 12, 2017 IDA-D1440 Loan Disb 38,200,000.00
Apr 6, 2017 IDA-D1440 Loan Disb 6,746,309.50
Jul 12, 2017 IDA-D1440 Loan Disb 734,848.80
Feb 23, 2017 IDA-D1440 Loan Disb 4,300,000.00
Aug 21, 2017 IDA-D1440 Loan Disb 8,556,717.00
Jan 24, 2018 IDA-D1440 Loan Disb 140,402.75
Dec 21, 2018 IDA-D1440 Loan Disb 159,380.19
Nov 27, 2018 IDA-D1440 Loan Disb 216,569.98
Aug 29, 2018 IDA-D1440 Loan Disb 164,740.00
Jul 10, 2018 IDA-D1440 Loan Disb 2,227,916.00
Dec 15, 2021 IDA-D5780 Loan Disb 136,286.94
May 31, 2022 IDA-D5780 Loan Disb 582,575.00
Dec 2, 2021 IDA-D5780 Loan Disb 358,017.70
Oct 29, 2021 IDA-D5780 Loan Disb 145,011.89
Feb 10, 2021 IDA-D5780 Loan Disb 2,136,464.80
Dec 14, 2023 IDA-D5780 Loan Disb 2,822,657.00
Dec 22, 2023 IDA-D5780 Loan Disb 189,172.60
Dec 26, 2023 IDA-D5780 Loan Disb 267,351.25
Jun 8, 2023 IDA-D5780 Loan Disb 137,919.06
Jun 8, 2023 IDA-D5780 Loan Disb 93,100.00
May 23, 2023 IDA-D5780 Loan Disb 124,651.39
Jul 28, 2023 IDA-D5780 Loan Disb 175,021.73
Jul 28, 2023 IDA-D5780 Loan Disb 133,350.00
Aug 1, 2023 IDA-D5780 Loan Disb 187,340.75
Aug 1, 2023 IDA-D5780 Loan Disb 398,283.88
Mar 9, 2023 IDA-D5780 Loan Disb 98,462.51
Mar 9, 2023 IDA-D5780 Loan Disb 105,307.49
Feb 16, 2023 IDA-D5780 Loan Disb 80,288.88
Nov 28, 2022 IDA-D5780 Loan Disb 66,272.96
Dec 23, 2022 IDA-D5780 Loan Disb 67,824.74
Jan 3, 2023 IDA-D5780 Loan Disb 4,750,925.00
Dec 30, 2022 IDA-D5780 Loan Disb 251,993.23
Jun 20, 2024 IDA-D5780 Loan Disb 114,900.00
Jun 4, 2024 IDA-D5780 Loan Disb 187,052.06
Mar 26, 2024 IDA-D5780 Loan Disb 202,441.86
Apr 3, 2024 IDA-D5780 Loan Disb 114,900.00
Aug 15, 2024 IDA-D5780 Loan Disb 135,241.88
Aug 5, 2024 IDA-D5780 Loan Disb 278,923.60
Aug 5, 2024 IDA-D5780 Loan Disb 201,993.89
Aug 5, 2024 IDA-D5780 Loan Disb 120,066.75
Jan 9, 2024 IDA-D5780 Loan Disb 308,221.12
Jan 11, 2024 IDA-D5780 Loan Disb 106,175.00
Aug 16, 2024 IDA-D5780 Loan Disb 337,277.00
Aug 16, 2024 IDA-D5780 Loan Disb 3,453,250.00
Nov 8, 2016 IDA-D1440 Loan Commitment 104,000,000.00
Mar 24, 2020 IDA-65680 Loan Commitment 60,000,000.00
Mar 24, 2020 IDA-D5780 Loan Commitment 20,000,000.00
Feb 21, 2024 IDA-65680 Loan Disb 162,706.25
Jan 25, 2024 IDA-65680 Loan Disb 220,319.70
Jan 25, 2024 IDA-65680 Loan Disb 226,268.38
Aug 19, 2024 IDA-65680 Loan Disb 13,635,641.00
Jun 20, 2024 IDA-65680 Loan Disb 186,887.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-03-05
Financial Management Satisfactory 2024-03-05
Monitoring and Evaluation Moderately Satisfactory 2024-03-05
Overall Implementation Progress (IP) Moderately Satisfactory 2024-03-05
Progress towards achievement of PDO Moderately Satisfactory 2024-03-05
Procurement Moderately Satisfactory 2024-03-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of farming households benefitting from restored and enhanced irrigation schemesValue0.005689.007400.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Number of government departments utilizing project generated data and knowledge products for DRM decision makingValue0.0020.007.00
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Number of functional local DRM authorities in Project affected areas established or strengthenedValue0.004.0017.00
    DateJanuary 24, 2020June 22, 2023January 31, 2025
    Comment
  • Number of female farming households benefiting from restored and enhanced irrigation schemesValue0.002706.003200.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Number of people with access to improved water supply as a result of the projectValue0.00452897.00850000.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Number of people in areas with reduced flood risk to project interventionsValue0.0024625.00400000.00
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Increased quality and reliability of forecasts and warnings produced by the hydro-met systemValueNoNoYes
    DateAugust 17, 2023August 17, 2023January 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of grievances registered and addressed within 45 daysValue0.00100.0080.00
    DateJanuary 20, 2020August 17, 2023January 31, 2025
    Comment
  • Number of water supply schemes rehabilitated and upgradedValue0.005.007.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Area provided with new/ rehabilitated irrigation facilitiesValue0.001831.002100.00
    DateNovember 8, 2016August 17, 2023January 31, 2025
    Comment
  • Number of beneficiaries from emergency response and recoveryValue0.00879697.00880000.00
    DateNovember 8, 2016August 17, 2023January 31, 2025
    Comment
  • Number of operational rural boreholes constructed under the ProjectValue0.00725.00815.00
    DateJanuary 20, 2020August 17, 2023January 31, 2025
    Comment
  • Cumulative crop production from land irrigated under the projectValue0.000.002760.00
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Adopted flood risk management plans for Blantyre and Shire River BasinValueNoNoYes
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Number of farmers trained in sustainable land and irrigation water managementValue0.00643.004900.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Number of female farmers trainedValue0.00375.002000.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Operational Decision Support System UpdatedValueNoNoYes
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Number of hotspot micro catchments with Catchment Management Committees and plansValue35.0059.0075.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • National Comprehensive Risk Assessment and risk atlas developedValueNoNoYes
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Hectares of catchments conserved and restoredValue0.000.002000.00
    DateNovember 8, 2016June 22, 2023January 31, 2025
    Comment
  • Number of DRM plans in affected districts developed and informed by available knowledge and data productsValue3.004.0017.00
    DateJuly 19, 2021August 17, 2023January 31, 2025
    Comment
  • Proportion of women in WUA committees (decision-making position)Value0.000.0040.00
    DateJanuary 24, 2020August 17, 2023January 31, 2025
    Comment
  •  National Emergency Operation Centre (NEOC) designed/approved with finalized bidding documents and safeguard instrumentsValueNoNoYes
    DateJanuary 20, 2020June 22, 2023January 31, 2025
    Comment
  • Area covered by installed small-scale solar power drip and medium-scale solar pumpsValue0.00342.40700.00
    DateNovember 8, 2016August 17, 2023January 31, 2025
    Comment
  • Number of small earth dams rehabilitatedValue0.0012.0023.00
    DateNovember 8, 2016August 17, 2023January 31, 2025
    Comment
  • Improved drainage system for flood control - (Length of drainage structures constructed)Value0.000.006.00
    DateAugust 17, 2023August 17, 2023January 31, 2025
    Comment