Climate-Smart Agriculture and Water Management Project

Abstract*

The development objective of the Climate-Smart Agriculture and Water Management Project for Bangladesh is to enhance climate resilience and productivity of irrigated agriculture and fisheries in targeted schemes. The project comprises of four components. The first component is improved climate resilience of flood control, drainage and irrigation infrastructure systems. It consists of following sub-components: (i) flood control and drainage (FCD) and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To enhance climate resilience and productivity of irrigated agriculture and fisheries in targeted schemes

Key Details

Project Details

  • P161534

  • Active

  • Samina Yasmin

  • People's Republic of Bangladesh

  • Bangladesh

  • August 2, 2017

  • (as of board presentation)

    March 9, 2021

  • March 30, 2022

  • US$ 155.31 million

  • Department of Fisheries,Bangladesh Water Development Board,Department of Agricultural Extension

  • South Asia

  • 2021

  • US$ 120.00 million

  • B

  • Not Applicable

  • June 30, 2026

  • Yes

  • BANK APPROVED

  • January 4, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 35.31
IDA Credit 120.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 120.00
IBRD + IDA Commitment 120.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 155.31

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 1, 2024 IDA-68360 Int Charges 281.29
May 7, 2024 IDA-68360 Loan Disb 219,920.34
Jun 18, 2024 IDA-68360 Loan Disb 423,908.44
Jun 17, 2024 IDA-68360 Loan Disb 29,058.52
Jun 24, 2024 IDA-68360 Loan Disb 652,396.70
Jun 25, 2024 IDA-68360 Loan Disb 407,658.22
Jun 17, 2024 IDA-68360 Loan Disb 33,531.59
Mar 9, 2021 IDA-68360 Loan Commitment 120,000,000.00
Apr 22, 2022 IDA-68360 Fee Charges 300,000.00
Dec 28, 2022 IDA-68360 Loan Disb 505,050.50
Mar 30, 2022 IDA-68360 Loan Disb 342,670.60
Nov 1, 2023 IDA-68360 Int Charges 83,812.91
Nov 1, 2023 IDA-68360 Int Charges 147,952.14
Oct 3, 2023 IDA-68360 Loan Disb 452,529.62
Apr 15, 2024 IDA-68360 Loan Disb 270,493.66
May 15, 2024 IDA-68360 Loan Cancel 25,000,000.00
May 1, 2024 IDA-68360 Int Charges 7,578.87
May 1, 2024 IDA-68360 Int Charges 143,826.27
May 1, 2024 IDA-68360 Int Charges 161,540.55
Jan 12, 2023 IDA-68360 Loan Disb 500,000.00
Sep 11, 2023 IDA-68360 Loan Disb 36,731.04
Jul 19, 2023 IDA-68360 Loan Disb 54,968.47
Sep 28, 2023 IDA-68360 Loan Disb 416,632.44
Jul 6, 2023 IDA-68360 Loan Disb 1,415.09
Oct 18, 2023 IDA-68360 Loan Disb 850,495.06
Dec 21, 2023 IDA-68360 Loan Disb 315,507.30
Nov 1, 2022 IDA-68360 Int Charges 140,146.58
Nov 1, 2022 IDA-68360 Int Charges 6,668.37
Jan 24, 2023 IDA-68360 Loan Disb 1,000,000.00
May 1, 2023 IDA-68360 Int Charges 49,323.39
May 1, 2023 IDA-68360 Int Charges 146,875.69
May 21, 2024 IDA-68360 Loan Disb 168,741.27

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2024-12-23
Monitoring and Evaluation Moderately Unsatisfactory 2024-12-23
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-12-23
Financial Management Moderately Satisfactory 2024-12-23
Procurement Moderately Unsatisfactory 2024-12-23
Project Management Moderately Unsatisfactory 2024-12-23

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area under climate-resilient technologies and practices both under crop production and fisheriesValue0.000.0095000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Farmers adopting improved agricultural technologyValue0.000.00100000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Farmers adopting improved agricultural technology - FemaleValue0.000.0050000.00
    DateDecember 29, 2017June 30, 2023
    Comment
  • Farmers adopting improved agricultural technology - maleValue0.000.0050000.00
    DateDecember 29, 2017June 30, 2023
    Comment
  • Increase in productivity of selected agricultural commodities and fishery supported by the projectValue0.000.0018.60
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment
  • RiceValue0.000.007.50
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment
  • FisheriesValue0.000.0037.00
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment
  • VegetablesValue0.000.0010.00
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment
  • Number of direct project beneficiariesValue0.0011232.00170000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Percent of which are femaleValue0.0030.0050.00
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area provided with new/improved irrigation or drainage servicesValue0.000.00120000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Number of government staff trained through the projectValue0.000.00400.00
    DateFebruary 26, 2021December 19, 2023June 30, 2025
    Comment
  • Farmers reached with agricultural assets or servicesValue0.0011232.00150000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Area provided with new irrigation or drainage servicesValue0.000.005000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Percentage of whom are femaleValue0.000.0040.00
    DateFebruary 26, 2021December 19, 2023June 30, 2025
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.0075000.00
    DateNovember 8, 2017February 28, 2023
    Comment
  • Citizens and/or communities involved in making decisions on beneficiary selectionValueNoNoYes
    DateFebruary 26, 2021December 19, 2023June 30, 2025
    Comment
  • Percentage of farmers producing non-rice crops or engaging in other agricultural enterprisesValue50.0050.0080.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Area provided with improved irrigation or drainage servicesValue0.000.00115000.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Percent reduction in crop area damaged by floods in completed schemesValue0.000.0060.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Beneficiary satisfaction with projectValue0.000.0070.00
    DateFebruary 26, 2021December 19, 2023June 30, 2025
    Comment
  • Proportion of which are femaleValue0.000.0050.00
    DateNovember 8, 2017December 19, 2023February 28, 2023
    Comment
  • Percentage of WMOs with Annual Budgets and O&M plansValue20.0020.0080.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Ratio of farm-gate to wholesale pricesValue0.620.620.75
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment
  • Female beneficiary satisfactionValue0.000.0070.00
    DateFebruary 26, 2021December 19, 2023June 30, 2025
    Comment
  • Percentage of the planned routine O&M costs covered by WMOsValue30.0030.0090.00
    DateOctober 15, 2020December 19, 2023June 30, 2026
    Comment