Skip to Main Navigation

Maritime Investment in Climate Resilient Operations

Abstract*

The development objective of the Maritime Investment in Climate Resilient Operations Project for Tuvalu is to improve the climate resilience of Nanumaga harbor and Funafuti port, and in the event of an eligible crisis or emergency, to provide an immediate response to the eligible crisis or emergency.It has four components. First component, sectoral and spatial planning tools finances spatial planning and risk-based tools for infrastructure investments...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the climate resilience of Nanumaga harbor and Funafuti port, and in the event of an Eligible Crisis or Emergency, to provide an immediate response to the Eligible Crisis or Emergency.

Key Details

Project Details

  • P161540

  • Closed

  • Satoshi Ogita

  • Ministry of Finance

  • Tuvalu

  • September 25, 2017

  • (as of board presentation)

    December 18, 2018

  • April 9, 2019

  • US$ 22.50 million

  • Ministry Of Public Works, Infrastructure, Environment, Labour, Meteorology, and Disaster

  • East Asia and Pacific

  • 2019

  • US$ 0.00 million

  • B

  • N/A

  • January 31, 2025

  • Yes

  • BANK APPROVED

  • April 17, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** 22.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 14, 2024 IDA-D4100 Loan Disb 246,840.02
Dec 20, 2023 IDA-D4100 Loan Disb 208,826.97
Jul 5, 2024 IDA-D4100 Loan Disb 36,796.49
Apr 9, 2019 IDA-D4100 Loan Disb 376,600.00
Jul 26, 2019 IDA-D4100 Loan Disb 209,460.00
Feb 7, 2020 IDA-D4100 Loan Disb 108,713.03
Feb 18, 2020 IDA-D4100 Loan Disb 149,173.20
Jul 13, 2020 IDA-D4100 Loan Disb 494,073.50
Sep 11, 2020 IDA-D4100 Loan Disb 201,607.12
Jun 21, 2021 IDA-D4100 Loan Disb 468,132.88
Jun 21, 2021 IDA-D4100 Loan Disb 1,576,992.10
Apr 23, 2021 IDA-D4100 Loan Disb 236,492.10
Mar 15, 2022 IDA-D4100 Loan Disb 176,200.45
May 5, 2022 IDA-D4100 Loan Disb 101,623.08
Sep 2, 2022 IDA-D4100 Loan Disb 126,063.44
Aug 13, 2021 IDA-D4100 Loan Cancel 13,109,830.00
Feb 10, 2022 IDA-D4100 Loan Disb 58,136.62
Mar 29, 2023 IDA-D4100 Loan Disb 112,036.71
Jun 5, 2020 IDA-D6460 Loan Commitment 2,500,000.00
Dec 18, 2018 IDA-D4100 Loan Commitment 20,000,000.00
May 28, 2024 IDA-D6460 Loan Disb 642,575.94
May 28, 2024 IDA-D6460 Loan Disb 669,332.44
Mar 12, 2024 IDA-D6460 Loan Disb 474,031.22
Jun 14, 2024 IDA-D6460 Loan Disb 524,408.50
Dec 1, 2022 IDA-D4100 Loan Disb 76,864.07
Aug 30, 2024 IDA-D4100 Loan Disb 6,340.72
Mar 12, 2024 IDA-D4100 Loan Disb 2,270,512.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-06-28
Financial Management Moderately Unsatisfactory 2024-06-28
Project Management Moderately Unsatisfactory 2024-06-28
Progress towards achievement of PDO Moderately Satisfactory 2024-06-28
Monitoring and Evaluation Moderately Satisfactory 2024-06-28
Overall Implementation Progress (IP) Moderately Satisfactory 2024-06-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Climate resilient investments on Funafuti constructed and operationalValue0.000.00100.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Improved operations at Funafuti portValue0.000.0050000.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Preliminary Design of climate resilient investments on selected outer islands completedValue0.0066.00100.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Successful implementation of SEA/SH Strategy Action PlanValueNoNoYes
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Funafuti port paved with climate resilient design standardsValue0.000.006000.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.000.00100.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Open Contracting used to publicize procurement data and updated on a monthly basisValueNoYesYes
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Number of individuals attending GBV, VAC and/or trafficking through trainingsValue0.000.0030.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Energy efficiency improvements at Funafuti PortValue0.000.0012.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Grievances responded and/or resolved within the stipulated service standardsValue0.000.0075.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • Unqualified audit with the time specified under the Legal AgreementValueNoYesYes
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • GIS database used to inform disaster preparedness and responseValueGIS database not establishedGIS database not establishedGIS database used to inform disaster preparedness
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • CERC-related procurement packages completed on time as per the procurement planValue0.00100.00100.00
    DateApril 30, 2020November 13, 2023April 30, 2024
    Comment
  • Percentage of project workers who complete induction on the Code of ConductValue0.000.0060.00
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • People with enhanced access to transportation servicesValue0.000.006000.00
    DateDecember 18, 2018August 11, 2023January 31, 2024
    Comment
  • Project-supported organization(s) publishing periodic reports on GRM and how issues were resolved [including resolution rates]ValueNoYesYes
    DateJanuary 31, 2019April 25, 2023January 31, 2024
    Comment
  • People with enhanced access to transportation services – IWT/ FerriesValue0.000.006000.00
    DateDecember 18, 2018August 11, 2023January 31, 2024
    Comment