Financier | Commitments |
---|---|
IDA Grant | 28.00 |
P161591
Closed
Gbetoho Boko
Central African Republic
April 13, 2017
(as of board presentation)
May 16, 2017
November 15, 2017
US$ 28.00 million
Ministry of Humanitarian Action, Solidarity and National Reconciliation
2017
US$ 28.00 million
B
Not Applicable
June 30, 2024
Yes
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
IDA Grant | 28.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 28.00 |
IBRD + IDA Commitment | 28.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 28.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 24, 2024 | IDA-D7560 | Loan Disb | 82,314.44 |
Dec 27, 2019 | IDA-D1920 | Loan Disb | 10,242,776.00 |
May 6, 2024 | IDA-D7560 | Loan Disb | 65,509.34 |
May 16, 2017 | IDA-D1920 | Loan Commitment | 28,000,000.00 |
Dec 4, 2020 | IDA-D7560 | Loan Commitment | 16,000,000.00 |
Aug 8, 2024 | IDA-D7560 | Loan Disb | 43,918.23 |
Apr 24, 2024 | IDA-D7560 | Loan Disb | 474,786.00 |
Apr 24, 2024 | IDA-D1920 | Loan Disb | 847,310.44 |
Jan 22, 2024 | IDA-D7560 | Loan Disb | -533,708.00 |
May 28, 2024 | IDA-D7560 | Loan Disb | -133,427.02 |
Jun 5, 2023 | IDA-D7560 | Loan Disb | 3,500,000.00 |
Nov 2, 2023 | IDA-D1920 | Loan Disb | 326,157.88 |
Feb 1, 2023 | IDA-D7560 | Loan Disb | 4,000,000.00 |
Apr 27, 2022 | IDA-D7560 | Loan Disb | 4,000,000.00 |
Aug 12, 2021 | IDA-D7560 | Loan Disb | 4,000,000.00 |
Oct 7, 2020 | IDA-D1920 | Loan Disb | 2,716,251.00 |
Feb 14, 2018 | IDA-D1920 | Loan Disb | 5,777,680.00 |
Feb 14, 2018 | IDA-D1920 | Loan Disb | 1,415,717.60 |
Dec 8, 2017 | IDA-D1920 | Loan Disb | 353,929.40 |
Mar 26, 2019 | IDA-D1920 | Loan Disb | 7,337,496.00 |
Jul 15, 2019 | IDA-D1920 | Loan Disb | -162,254.14 |
May 6, 2024 | IDA-D1920 | Loan Disb | 110,394.22 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-06-28 |
Overall Implementation Progress (IP) | Satisfactory | 2024-06-28 |
Project Management | Satisfactory | 2024-06-28 |
Overall Safeguards Rating | Satisfactory | 2024-06-28 |
Procurement | Satisfactory | 2024-06-28 |
Financial Management | Satisfactory | 2024-06-28 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-06-28 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with improved urban living conditions | Value | 0.00 | 101230.00 | 99000.00 |
Date | November 15, 2017 | November 16, 2023 | April 29, 2024 | |
Comment |
Female direct recipients of cash transfers | Value | 0.00 | 68.25 | 50.00 |
Date | November 13, 2020 | September 25, 2023 | April 29, 2024 | |
Comment |
Beneficiaries of Safety net programs affected by COVID-19 | Value | 0.00 | 6470.00 | 30000.00 |
Date | October 19, 2020 | September 25, 2023 | April 29, 2024 | |
Comment |
of which female | Value | 0.00 | 0.00 | 50.00 |
Date | June 30, 2017 | June 30, 2021 | ||
Comment |
of which displaced | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2017 | June 30, 2021 | ||
Comment |
of which female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Beneficiaries of Safety net programs affected by climate-related crises. | Value | 0.00 | 21355.00 | 15000.00 |
Date | November 10, 2020 | September 25, 2023 | April 29, 2024 | |
Comment |
of which female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Direct project beneficiaries | Value | 0.00 | 388460.00 | 324000.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Beneficiaries of safety nets programs | Value | 0.00 | 244525.00 | 225000.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Female beneficiaries | Value | 0.00 | 60.00 | 50.00 |
Date | June 30, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
of which female | Value | 0.00 | 60.00 | 50.00 |
Date | August 1, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
of which displaced | Value | 0.00 | 80.00 | 30.00 |
Date | June 30, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
of which displaced | Value | 0.00 | 80.00 | 30.00 |
Date | August 1, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project | Value | 0.00 | 170544.00 | 99000.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Registry of beneficiaries of safety nets program | Value | No | Yes | Yes |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Participants in consultation activities during project implementation (number) | Value | 0.00 | 2560.00 | 2200.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Participants in consultation activities during project implementation - female | Value | 0.00 | 954.00 | 900.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
of which female | Value | 0.00 | 94905.00 | 45000.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Cash transfer payments received by beneficiaries within five days of scheduled date | Value | 0.00 | 94.00 | 90.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 5.00 | 5.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Number of households who have benefited from at least one cash transfer payment | Value | 0.00 | 48905.00 | 45000.00 |
Date | October 19, 2020 | September 25, 2023 | April 29, 2024 | |
Comment |
of which displaced | Value | 0.00 | 1965.00 | 1300.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Person-days of employment created | Value | 0.00 | 120415.00 | 80000.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Grievances registered related to delivery of project benefits addressed within the project GRM timeframe (%) | Value | 0.00 | 85.00 | 80.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
of which affected by COVID-19 | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
of which affected by climate-related crises | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
of which displaced | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
Amount of cash transfers made to households (CFAF) | Value | 3000000000.00 | 9351395113.00 | 9490000000.00 |
Date | October 19, 2020 | November 16, 2023 | April 29, 2024 | |
Comment |
of which female | Value | 0.00 | 0.00 | 30.00 |
Date | June 30, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
of which affected by COVID-19 | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
of which affected by climate-related crises | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Training sessions (accompanying measures/peaceful co-existence activities) successfully delivered to beneficiaries | Value | 0.00 | 1760.00 | 500.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Beneficiaries who report accompanying measures/peaceful co-existence activities have benefitted their community | Value | 0.00 | 0.00 | 70.00 |
Date | June 30, 2017 | February 9, 2018 | June 30, 2021 | |
Comment |
of which women | Value | 0.00 | 73.48 | 50.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
of which displaced | Value | 0.00 | 78.76 | 30.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Beneficiary households reporting to have increased their assets because of the safety nets program | Value | 0.00 | 94.71 | 60.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Beneficiary households reporting to have better met their consumption need because of the project | Value | 0.00 | 94.19 | 60.00 |
Date | November 15, 2017 | September 25, 2023 | April 29, 2024 | |
Comment |
Social Registry (SR) has been developed and deployed | Value | No | Yes | Yes |
Date | October 19, 2020 | September 25, 2023 | April 29, 2024 | |
Comment |